February 23, 2021
Mr. Zack Johnson
ggCircuit, LLC
2303 S. 3rd. St.
Terre Haute, IN 47802
brian.wyrick@ggcircuit.com; zack.johnson@ggcircuit.com
RE: Change Order No. 2 (Final)/Project Completion Affidavit
Century Center Esports Arena – Project No. 119-16CR
Dear Mr. Johnson:
At its February 23, 2021 meeting, the Board of Public Works approved the Final Change
Order for this project, for an increase of $22,594.25 with an additional fifty (50) days. The final
contract amount is $401,476.84 with a new completion date of February 3, 2021.
In addition, the Project Completion Affidavit for this project was approved in the amount
of $401,476.84. Copies of the Change Order and Project Completion Affidavit are enclosed for
your records.
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
/s/ Anne Fuchs
Anne Fuchs, Clerk
Enclosures
AF/lh
119-106CR
February 23, 2021
Category BOM LABOR Category Total Running total
Audio | LAN Center PA bid billed difference bid billed
5,400.95 5,400.95 (0.00)1,980.00 1,980.00 7,380.95 7,380.95
Comments:None
Furnishing | Gaming bid billed difference bid billed
45,407.61 52,856.85 7,449.24 16,110.00 16,110.00 68,966.85 76,347.80
Comments:
ggC submitted bid had $2,768 for foam flooring tiles based on the amazon linked provided from BOM. After a sample was
purchased, it was determined that the foam flooring was not adequate to the needs of the Bendix Arena. Rubber fitlock tiles were
purchased instead with a total cost of: $13,080.60; leaving an overspend of $10,312. Because ggC was dilligent in obtaining the
best prices on other materials in this section, we were able to pass additional savings onto the City of South Bend (hence the total
overage for this section being $7,449.24 instead of the $10,312 that it could have been).
Grip | Production bid billed difference bid billed
51,455.00 51,455.00 0.00 20,060.00 20,060.00 71,515.00 147,862.80
Comments:None
Lighting bid billed difference bid billed
25,611.00 25,611.00 0.00 11,700.00 11,700.00 37,311.00 185,173.80
Comments:None
IT | PC & Console bid billed difference bid billed
87,252.43 78,014.58 (9,237.85)8,910.00 8,910.00 86,924.58 272,098.38
Comments:
The massive savings in this section were gained mostly by leveraging our relationship with HP OMEN and Zowie Benq to obtain
the best pricing on the newest equipment on the market that fit the specs and needs of the Bendix Arena without sacrificing
customer expectations. These savings were passed onto the City of South Bend in order to purchase better equipment &
materials from other sections of the project.
IT | Networking bid billed difference bid billed
6,396.73 5,670.02 (726.71)4,455.00 4,455.00 10,125.02 282,223.40
Comments:Saved some $$ by building equipment instead of ordering pre-builts
LVI bid billed difference bid billed
3,635.99 3,055.45 (580.54)900.00 900.00 3,955.45 286,178.85
Comments:Saved some $$ by building equipment instead of ordering pre-builts
Video Production bid billed difference bid billed
9,192.00 16,732.55 7,540.55 1,440.00 1,440.00 18,172.55 304,351.40
Comments:
#1 The four tvs spec'd in the submitted bid were for the previous generation of xbox and PS4. With the new ones being released
in November, purchasing better tvs to meet customer expectations and output requirements was paramount. #2 In order to meet
the needed functionality of the Bendix Arena with NDI and streaming technology to be shown on the 75" truss mounted TVs,
different models with better integrated software and better picture quality were purchased. ggCircuit used some of the savings
from the "IT | PC & Console" section to make this purchase
Furnishing | Stage bid billed difference bid billed
33,983.00 31,466.88 (2,516.12)7,740.00 7,740.00 39,206.88 343,558.28
Comments:None
Video | CAM bid billed difference bid billed
4,198.00 4,198.00 0.00 360.00 360.00 4,558.00 348,116.28
Comments:None
Grip | CAM bid billed difference bid billed
3,534.00 3,534.00 0.00 360.00 360.00 3,894.00 352,010.28
Comments:None
NDI bid billed difference bid billed
2,970.00 2,970.00 0.00 1,080.00 1,080.00 4,050.00 356,060.28
Comments:None
Other Labor bid billed difference bid billed
0.00 0.00 0.00 24,750.00 24,750.00 24,750.00 380,810.28
Comments:None
Change Orders & Addons:bid billed difference bid billed
0.00 20,665.68 20,665.68 0.00 0.00 20,665.68 401,475.96
Comments:
The following reflects change orders & addons for the project that were not specifically covered in the bid proposal or the
submitted bid by ggCircuit. A description of the products purchased as well as the date and invoice number when we billed for
these is included for easy identification. Nothing above is included below. All labor invoiced above reflects the installation & setup
of equipment and furnishings in the categories above, not below.
Date Invoice Num Amount Memo/Description
10/23/2020 Invoice 1248 800.00 2x Secret Lab Gaming Chair for Admin 800.00
11/06/2020 Invoice 1263 2,268.00 Board gaming Table - chairs | Walnut Jasper 2,268.00
11/06/2020 Invoice 1263 306.00 Board Gaming Table Chairs | FREIGHT 306.00
11/06/2020 Invoice 1263 192.00 Board Gaming Table - cup holders | Walnut Jasper 192.00
11/30/2020 Invoice 1261 5,872.64 HP OMEN 3-year PC Protection Plan 5,872.64
11/30/2020 Invoice 1288 499.90 LAN Gaming Desk x2 | Admin 499.90
12/21/2020 Invoice 1298 307.96 TV Mount Truss (4)307.96
12/21/2020 Invoice 1298 969.12 additional console cntrlr, xbox chargers, headset, game code 969.12
12/28/2020 Invoice 1249 198.00 Speaker Poles for JBL System 198.00
01/31/2021 Invoice 1288 2,590.60 Cable Channels (Guard Dogs) floor 2,590.60
01/31/2021 Invoice 1288 138.02 Board Gaming Table seat cushions 138.02
01/31/2021 Invoice 1288 2,505.23 Production PC w/ dual monitors (Streaming)2,505.23
01/31/2021 Invoice 1288 1,398.06 Stage drape, stage desk drape, admin drape 1,398.06
01/31/2021 Invoice 1288 781.71 Floor Runners (ingress) x3 781.71
01/31/2021 Invoice 1288 943.28 extra (6 of each) Mouse, Keyboard, Headset 943.28
01/31/2021 Invoice 1288 120.89 USB Extenders for USB Hubs | Stage PCs 120.89
01/31/2021 Invoice 1288 731.50 USB Hubs | 36 731.50
01/31/2021 Invoice 1288 42.77 PS5 Controller chargers 42.77
Total :279,036.71 301,630.96 22,594.25 99,845.00 99,845.00 401,475.96
Total without change orders & addons:279,036.71 280,965.28 1,928.57 99,845.00 99,845.00 380,810.28
Total
Summary:Without the change orders and addons, the project went 1928.57 over budget. The much needed and much more expensive
flooring is the culprit. CW has taken out $2517 from their invoice for the Lightbox snafu. We have already updated the digital
invoice sent to the City of South Bend and has been reflected in the above numbers.
2303 S. Third Street
Terre Haute, Indiana 4780
02/18/2021
February 23, 2021
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 02/18/2021
Name Becca Plantz Department Public Works
BPW Date 02/23/2021 Phone Extension 5998
Review and Approval Required Prior to Submittal to Board Diversity Compliance
and Inclusion Officer Officer Name BPW Attorney Attorney Name Clara McDaniels
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. 2 PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name ggCircuit, LLC
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Century Center Esports Arena
Project Number 119-106CR
Funding Source Hotel Motel Tax Fund
Account No. 7304.42010.000.0099
Amount
Terms of Contract Lump Sums
Purpose/Description Change to flooring and products for the construction and installation
of equipment to make improvements to the Century Center for eSports
Gaming Center and Broadcast Studio.
For Change Orders Only
Amount of
Increase
Decrease
$ 22,594.25
($ )
Previous Amount $ 378,882.59
Current Percent of Change:
Increase
Decrease
6%
( %)
New Amount $ 401,476.84
Total Percent of Change:
Increase
Decrease
6%
( %)
Time Extension Amount: 50 days
New Completion Date: February 3, 2021