HomeMy WebLinkAboutOpening & Award Bids - Century Center Esports Arena Rebid Proj No. 119-106CR - ggCircuit LLC
GARY A. GILOT ELIZABETH A. MARADIK THERESE J. DORAU JORDAN V. GATHERS JOSEPH R. MOLNAR
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
September 8, 2020
Mr. Zack Johnson
ggCircuit LLC
2303 S. 3rd. St.
Terre Haute, IN 47802
zack.johnson@ggcircuit.com
RE: Award Bid – Century Center Esports Arena – Project No. 119-106CR
Dear Mr. Johnson:
The Board of Public Works, at its meeting held on September 8, 2020, awarded the above
referenced project to you in the amount of $378,882.59. Enclosed please find a signed
Bid/Proposal form.
Please forward the following documents in one submittal by September 22, 2020 to my
attention for Board of Public Works approval to lhensley@southbendin.gov:
1) One (1) signed original of the Public Works Contract (enclosed)
2) Labor & Material Payment Bond
3) Performance Bond (125% of Bid Amount)
4) Certificate of Insurance naming the City of South Bend as an additional insured
5) Item #4 for all subcontractors you use
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
s/Linda M. Martin, Clerk
Enclosures
BOARD OF PUBLIC WORKS
CITY OF SOUTH BEND, INDIANA
PUBLIC WORKS CONTRACT
THIS AGREEMENT, made and entered into this 8th Day of September, 2020, by and between,
ggCircuit LLC, 2303 S. 3rd. St., Terre Haute, IN 47802, HEREINAFTER called the Contractor,
and the Board of Public Works herein called the "Board".
WITNESSETH: That the Contractor covenants and agrees to make the following improvement,
as fully set out in the Request for Quotations, Standard Specifications, Special Provisions, Plans,
and Bid Proposals, all of which are set forth as a part of this Contract, for:
PROJECT NO. 119-106CR
DESCRIPTION: CENTURY CENTER ESPORTS ARENA
COMPLETION DATE: SEE SPECIFICATIONS
AMOUNT: $378,882.59
FUNDING: HOTEL/MOTEL TAX FUND
The unit prices for this improvement were those prices as received and accepted by the Board on
the 8th Day of September, 2020.
The Contractor further agrees to notify the Engineer when this improvement is completed. This
notification shall be in the form of a Completion Affidavit, signed by the Contractor. Upon final
acceptance of the improvement by the Engineer, the Contractors final estimate will be presented
to the Board for final Payment with one (1) copy of the Completion Affidavit and one (1) copy of
a Waiver of Lien.
BOARD OF PUBLIC WORKS GGCIRCUIT, LLC
Gary A. Gilot, President Elizabeth A. Maradik, Member Printed Name
Therese J. Dorau, Member Jordan V. Gathers, Member Signature
Joseph R. Molnar,
Member
Attest: Linda M. Martin,
Clerk
CERTIFICATION (To be completed if Contractor is a Corporation)
I,, certify that I am Secretary of the Corporation named as
Contractor herein; that who signed this Agreement on behalf of the Contractor
was then of said Corporation; that said agreement was duly signed for and in
behalf of said Corporation by authority of its governing body, and is within the scope of its
corporate powers.
Secretary Corporate Seal
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Linda M. Martin, Clerk
Board of Public Works
FROM: Becca Plantz, Project Engineer
SUBJECT: Award Project No. 119-106CR
Century Center Esports Arena
DATE: September 8, 2020
On September 8, 2020 the Board of Public Works opened bids for the above project. I have
reviewed them and two bids are missing required documentation. TPC Technologies, Inc. filled
out the information and documentation for already being a pre-qualified bidder with the City of
South Bend although they are not. Nelco Media was missing a bid bond or surety check as well
as missing information from their responsible bidder ordinance requirements. Both companies
will be contacted and requested to follow up with that documentation as soon as possible to
become pre-qualified bidders if interested. All other bids are correct and include all required
documentation.
The bidders ranked as follows:
Bidder Total Bid Amount
1. ggCircuit LLC $378,882.59
2. Nelco Media $399,225.97
3. Martell Electric, LLC $399,994.00
4. TPC Technologies, Inc. $619,371.55
I recommend award of a contract for Century Center Esports Arena to the lowest responsive /
responsible bidder, ggCircuit LLC in the amount of $378,882.59.
Sufficient funds have been appropriated from Hotel Motel Tax Fund, 7304.42010.000.0099.
Please call with your questions (5998).
Enc. Century Center Bid Tabulation
BID TABULATION
Century Center Esports Arena
Project No: 119-106CR
For Bids Due: September 8, 2020
BASE BID
Item No.Description Quantity Unit Unit Price Item Total Unit Price Item Total Unit Price Item Total Unit Price Item Total
1 Material Procurement per attached BOM 1 LS $ 279,037.59 279,037.59$ $330,337.97 330,337.97$ $ 291,196.00 291,196.00$ $559,446.55 559,446.55$
2 Staging/Scenic/Rigging Labor 1 LS $ 43,910.00 43,910.00$ $ 11,000.00 11,000.00$ $ 41,276.00 41,276.00$ $ 18,900.00 18,900.00$
3 Low Voltage Labor 1 LS $ 900.00 900.00$ $ 3,000.00 3,000.00$ $ 8,975.00 8,975.00$ $ 675.00 675.00$
4 IT/Networking Labor 1 LS $ 13,365.00 13,365.00$ $ 5,000.00 5,000.00$ $ 23,819.00 23,819.00$ $ 16,181.25 16,181.25$
5 Audio/Video Labor 1 LS $ 5,220.00 5,220.00$ $ 42,388.00 42,388.00$ $ 3,340.00 3,340.00$ $ 6,525.00 6,525.00$
6 Lighting Labor 1 LS $ 11,700.00 11,700.00$ $ 5,000.00 5,000.00$ $ 20,241.00 20,241.00$ $ 17,643.75 17,643.75$
7 Other Labor 1 LS 24,750.00$ 24,750.00$ 2,500.00$ 2,500.00$ 11,147.00$ 11,147.00$ -$
Total 378,882.59$ 399,225.97$ 399,994.00$ 619,371.55$
I hereby certify that the above truly and accurately represents bids received for this project on September 8, 2020.
Rebecca Plantz, Project Engineer
ggCircuit LLC
Non-Collusion Affadavit Y
Nelco Media, Inc.Martell Electric, LLC
BASE 378,882.59$
Y Y
TPC Technologies, Inc.
Y
399,225.97$ 399,994.00$ 619,371.55$
Page 1 of 1
CEN785< CEN7E5 E63O576 A5ENA
3URMHFW 1R. 11 / 10 &5
WKR WH AUH 3
CRQWUDFWRU¶V BLG FRU PXEOLF WRUN CKHFNOLVW FRU BLGGHUV 4
BLG SHFXULW\ 5
CRQWUDFWRUV BLG FRUP 7
PDUW I 7
PDUW II 8
6HFWLRQ I E[SHULHQFH QXHVWLRQQDLUH 8
AOLHQZDUH & BHVW BX\ 9
GDPH6WRS 10
CKULVWLDQ BURWKHUV CROOHJH HLJK 6FKRRO (CBCH6) 11
RRVH HXOPDQ IQVWLWXWH RI 7HFKQRORJ\ 12
6HFWLRQ II PODQ AQG ETXLSPHQW QXHVWLRQQDLUH 13
6HFWLRQ III CRQWUDFWRU ¶V FLQDQFLDO 6WDWHPHQW 15
CRQWUDFWRU¶V NRQ-CROOXVLRQ DQG NRQ-DHEDUPHQW AIILGDYLW, ... 19
BLG/PURSRVDO - BDVH BLG 25
PURRI RI MBE/WBE PDUWLFLSDWLRQ GRDO FRUP [MWBE-1.0] 26
AFNQRZOHGJH RHFHLSW RI AGGHQGXP(V) LQFOXGHG ZLWK WKH ELG. 29
PURSRVDO SWDWHPHQWV DQG OWKHU AIILGDYLWV 30
PUH-QXDOLILFDWLRQ CKHFNOLVW 30
PUH-QXDOLILFDWLRQ LHWWHU 33
PUH-QXDOLILFDWLRQ AWWDFKPHQWV 36
BXVLQHVV 9HULILFDWLRQ 36
LLVW IGHQWLI\LQJ AOO FRUPHU BXVLQHVV NDPHV 38
DHWHUPLQDWLRQV RI 9LRODWLRQV 38
6WDIILQJ CDSDELOLW\ 6WDWHPHQW 38
CRUH CDSDELOLWLHV: 38
6WDWHPHQW AERXW EPSOR\HH CODVVLILFDWLRQ 39
EPSOR\PHQW CDWHJRULHV 39
E[HPSW DQG NRQH[HPSW 39
ASSUHQWLFHVKLS DQG 7UDLQLQJ PURJUDPV 40
EPSOR\HH DUXJ 7HVWLQJ PURJUDP 41
6WDWHPHQW RI AQ\ 7D[ LLHQV/DHOLQTXHQFLHV 43
6WDWHPHQW RI 6LPLODU PURMHFWV 43
PURSRVDO AGGHQGXPV 44
AGGLWLRQDO RHFRPPHQGDWLRQV 44
PC & CRQVROH GDPH LLVW 45
BLOO RI MDWHULDOV 47
:KR :H $UH
JJ&LUFXLW //& KDV EHHQ LQ WKH HVSRUWV VSDFH DQG EULFN DQG PRUWDU JDPLQJ ORFDWLRQV IRU 1
\HDUV. 1RZ D JOREDO HVSRUWV VRIWZDUH SRZHUKRXVH, JJ&LUFXLW¶V VRIWZDUH WRROV DUH DGRSWHG DW
RYHU 1,000 ORFDWLRQV LQ ERWK HQWHUWDLQPHQW DQG UHWDLO.
JJ&LUFXLW HVSRUWV VHUYLFHV WHDP KDV HQJDJHG RYHU 100 JDPLQJ ORFDWLRQV LQ WKH ODVW \HDU. )URP
VWDUWXS FRQVXOWLQJ WR LQ-SHUVRQ VHWXS, ZH WDNH RXU ZLGH EUHDGWK RI SK\VLFDO HVSRUWV VSDFHV DQG
LPSOHPHQW WKH WRROV WR LQFUHDVH HDVH RI XVH, SOD\HU HQJDJHPHQW DQG ORFDWLRQ HIILFLHQF\.
Version 4/2/2019 Contractor’s Bid for Public Works - 1
CITY OF SOUTH BEND, INDIANA
CONTRACTOR’S BID FOR PUBLIC WORK
CHECKLIST FOR BIDDERS
Project Name Century Center Esports Arena
Project No. 119-106CR
For Bids Due September 8, 2020 by 9:30 AM Local Time
From time to time the South Bend Board of Public Works finds it necessary to reject a bid because
it does not comply with statutory requirements. In preparing your bid, please use the following
checklist in order to make sure that your bid is done in the proper manner.
Proper bid security included. The bidder has the option of providing either a Certified Check
or Bid Bond.
Bid prepared on the City of South Bend Contractor’s Bid for Public Work Form, completely
executed.
Contractor’s Non-Collusion and Non-Debarment Affidavit, Certification Regarding Investments
with Iran, Employment Eligibility Verification, Non-Discrimination Commitment, and
Certification of use of United States Steel Products or Foundry Products.
Proof of MBE/WBE Participation Goal Form [MWBE-1.0]. If minimum participation goal is not
met, also provide Evidence of Good Faith Efforts Form [MWBE-2.0] and MBE/WBE Contacted
Form [MWBE-2.1].
Acknowledge Receipt of _____ Addendum(s) included with the bid.
All required additional information is included with the bid.
Proposal statements and other affidavits all signed by the proper party with name either
printed or typed underneath signature.
This checklist submitted with the Bid.
This checklist is provided for bidder’s use in assuring compliance with required
documentation; however, it does not include all specifications requirements and does not
relieve the bidder of the need to read and comply with the specifications.
Bidder: Date:
By Authorized Representative:
Signature:
Print Name & Title:
X
X
X
X
X
X
X
X
ggCircuit LLC 9/3/2020
Zack Johnson, CEO
BLG SHFXULW\
JJCLUFXLW LLC LV FXUUHQWO\ LQ WKH SURFHVV RI ERQGLQJ RXU ELG ZLWK HDUWIRUG FLQDQFLDO PURGXFWV. :H
KDYH DWWDFKHG SURRI RI D FDVKLHU'V FKHFN PDGH SD\DEOH WR WKH CLW\ RI SRXWK BHQG, IQGLDQD
UHSUHVHQWLQJ 5% RI RXU ELG DPRXQW WR VHFXUH RXU ELG.
SWaWePeQW FURP OXU AJeQW:
TR :KRP IW MD\ CRQFHUQ,
I UHSUHVHQW GGCLUFXLW DV WKHLU LQVXUDQFH DJHQW. :H DUH LQ WKH SURFHVV RI VHFXULQJ WKH UHTXLUHG
ELG ERQG IURP HDUWIRUG FLQDQFLDO PURGXFWV. I ZLOO IROORZ XS ZLWK WKH UHTXLUHG SURRI RI FRYHUDJH DV
VRRQ DV SRVVLEOH. POHDVH IHHO IUHH WR UHDFK RXW WR PH GLUHFWO\ ZLWK DQ\ TXHVWLRQV.
TKDQN <RX,
CDOYLQ GLOPDQ
IQVXUDQFH AGYLVHU
P: 612-812-9972
E: FDOYLQ.JLOPDQ@JPDLO.FRP
AGYDQFH IQVXUDQFH AJHQF\
5241 9LNLQJ DULYH EGLQD, MN 55435
Version 4/2/2019 Contractor’s Bid for Public Works - 2
CITY OF SOUTH BEND, INDIANA
CONTRACTOR’S BID FOR PUBLIC WORK
Project Name Century Center Esports Arena
Project No. 119-106CR
For Bids Due September 8, 2020 by 9:30 AM Local Time
PART I
(Must be completed for all bids. Please type or print)
Date: Bidder (Firm):
Address:
City/State/Zip: Telephone Number: ( )
Agent of Bidder (if Applicable):
Pursuant to notices given, the undersigned offers to furnish labor and/or material necessary to complete the
public works project of:
the City of South Bend, Indiana, in accordance with plans and specifications prepared by:
and dated for the sum of (enter the Total Bid as shown on the Proposal)
($ )
(Enter sum of Total Base Bid plus Alternates shown on Proposal) (Numerical)
The undersigned further agrees to furnish a bond or certified check with this bid for an amount specified in
the notice of the letting. If alternative bids apply, the undersigned submits a proposal for each in accordance
with the notice. Any addendums attached will be specifically referenced at the applicable page.
If additional units of material included in the contract are needed, the cost of units must be the same as that
shown in the original contract if accepted by the City of South Bend. If the bid is to be awarded on a unit
basis, the itemization of the units shall be shown on a separate attachment.
ACCEPTANCE
The above bid is accepted this day of 20
Subject to the following conditions:
BOARD OF PUBLIC WORKS
Gary A. Gilot, President Jordan V. Gathers, Member
Elizabeth A. Maradik, Member Therese J. Dorau, Member
Joseph R. Molnar, Member Attest: Linda M. Martin, Clerk
PART II
By
(Signature)
(Printed Name of Person Signing)
ggCircuit LLC9/3/2020
2303 S. 3rd Street
Terre Haute, IN 47802 812 230-5671
N/A
Century Center Esports Arena Project No. 119-106CR
SimplyNew, LLC 12575 Beatrice Street Playa Vista, CA 90066
9/3/2020
Zack Johnson, CEO
3DUW ,,
6HFWLRQ , ([SHULHQFH 4XHVWLRQQDLUH
1.$WWDFK LQIRUPDWLRQ UHJDUGLQJ SURMHFWV \RXU RUJDQL]DWLRQ KDV FRPSOHWHG IRU WKH SHULRG RI
RQH (1) \HDU SULRU WR WKH GDWH RI WKH FXUUHQW ELG.
3OHDVH VHH WKH IROORZLQJ FDVH VWXGLHV.
2.$WWDFK D OLVWLQJ RI SXEOLF ZRUNV SURMHFWV FXUUHQWO\ LQ SURFHVV RI FRQVWUXFWLRQ E\ \RXU
RUJDQL]DWLRQ.
1/$
3.$WWDFK LQIRUPDWLRQ UHJDUGLQJ DQ\ IDLOXUH WR FRPSOHWH DQ\ ZRUN DZDUGHG WR \RX DQG WKH
ORFDWLRQ WKHUHRI.
1/$
.$WWDFK UHIHUHQFHV IURP SULYDWH ILUPV IRU ZKLFK \RX KDYH SHUIRUPHG ZRUN.
6DUDK :DJJ
0DQDJHU 'XUKDP &ROOHJH (VSRUWV $UHQD
6DUDK.:DJJ#GXUKDPFROOHJH.FD (0) 20-22
-DVRQ +DQVHQ
0DQDJHU RI 3URJUDP 2SHUDWLRQV, 7KH +8% #8:
MDVRQK#XZ.HGX (20) 3-
-LP %URFNPDQ
(VSRUWV 'LUHFWRU, &KULVWLDQ %URWKHUV &ROOHJH +LJK 6FKRRO
EURFNPDQ-#FKFKV.RUJ (201) 0-2
0DUF 8SWPRUH
,QQRYDWLRQ 3URGXFW 0DQDJHU, *DPHVWRS
0DUF8SWPRUH#JDPHVWRS.FRP
$QGUHZ 0LHVQHU
'LUHFWRU RI 7HFKQRORJ\ & /LYH (YHQWV, &RPSOH[LW\ *DPLQJ
DQGUHZ.PLHVQHU#FRPSOH[LW\JDPLQJ.FRP
AOLHQZDUH & BHVW BX\
6SDFH: 9DULHG
6WDWLRQV: VWDWLRQV, 00+ ORFDWLRQV
6XPPDU\: 'HOO DQG $OLHQZDUH EHJDQ D SDUWQHUVKLS ZLWK JJ&LUFXLW WR EXLOG D FXVWRP YHUVLRQ RI
JJ/HDS WR LPSOHPHQW LQ NLRVN V\VWHPV WKURXJKRXW WKH %HVW %X\ QHWZRUN. 7KH SURMHFW ZDV WR
SURYLGH LQIRUPDWLRQ DERXW HDFK VSHFLILF PRGHO DQG D PRGH IRU JDPHUV WR HQJDJH LQ 3&
JDPHSOD\ WR WU\ RXW WKH PDFKLQHV ZKLOH LQ-VWRUH. 2Q WRS RI WKLV JJ&LUFXLW SURYLGHG UHPRWH
VXSSRUW WR RQ-VLWH HPSOR\HHV, DQG GHYHORSHG D V\VWHP WR WUDFN XSWLPH & YLVLWRU HQJDJHPHQWV.
3URMHFW IQFOXGHG: 6RIWZDUH, &XVWRP 'HYHORSPHQW, 6KDUHG 6HUYLFHV, 1DWLRQZLGH 6XSSRUW
OXWFRPH:
Ɣ 3& *DPLQJ 6WDWLRQV LQ 00+ /RFDWLRQV
Ɣ $XWRPDWHG 8SGDWHV
Ɣ 6HFXUH 3& 6HWXS
Ɣ &XVWRPHU 7UDFNLQJ
Ɣ 6XSSRUW 7LFNHW 6XEPLVVLRQ
Ɣ 'DWD $QDO\WLFV
GDPH6WRS
DHWDLOV: *DPH6WRS (VSRUWV 3LORW - 13 /RFDWLRQV
6WDWLRQV: $YHUDJH 20 3&V SHU ORFDWLRQ
3URMHFW IQFOXGHG: 'HVLJQ, +DUGZDUH, 6RIWZDUH, *DPH /LFHQVHV, )HHV, ,QVWDOODWLRQ, &XVWRP
'HYHORSPHQW
6XPPDU\: *DPH6WRS DSSURDFKHG JJ&LUFXLW WR DVVLVW WKHP LQ EXLOGLQJ WKH IXWXUH RI WKHLU UHWDLO
ORFDWLRQV. 7KLV LQFOXGHG FXVWRP GHYHORSPHQW RI RXU JJ/HDS HVSRUWV FOLHQW DQG LPSOHPHQWDWLRQ
RI RXU 3;( VHUYLFHV DW WKLUWHHQ RI WKHLU ORFDWLRQV. 2XU VHUYLFHV WHDP EXLOW 3;( VHUYHUV IRU DOO
ORFDWLRQV DV ZHOO DV GLG VRIWZDUH DQG VHWXS RQ-VLWH IRU DOO ORFDWLRQV.
OXWFRPH:
Ɣ $YHUDJH 20 3& *DPLQJ VWDWLRQV LQ HDFK ORFDWLRQ
Ɣ 3;( 6HUYHU
Ɣ JJ/HDS VRIWZDUH, JDPHV DQG PDLQWHQDQFH VXSSRUW
CKULVWLDQ BURWKHUV CROOHJH HLJK 6FKRRO (CBCH6)
6SDFH: 1 VTXDUH IHHW
6WDWLRQV: 2
6XPPDU\: JJ&LUFXLW ZDV DSSURDFKHG WR KHOS
&%&+6 VHW XS WKHLU ILUVW HVSRUW FHQWHU RQ
FDPSXV. :LWK D OLPLWHG EXGJHW DQG VSDFH, WKH
WHDP ZRUNHG ZLWK WKH VFKRRO DQG SUHVHQWHG
YDULRXV VFHQDULRV WR ILW WKHLU OD\RXW, EXGJHW &
VWXGHQW QHHGV. ,W ZDV LGHQWLILHG WKDW QRW DOO
VWXGHQWV ZRXOG ZDQW WR OHDUQ WR FRPSHWH RQ D 3&
DQG WKH VFKRRO DOVR ZDQWHG WR JLYH VWXGHQWV
PDQ\ RSWLRQV IRU WKLV LQLWLDWLYH. JJ&LUFXLW LQVWDOOHG
WKH 3;( 6HUYHU DQG PDQDJHG WKH LQVWDOODWLRQ
SURFHVV ZLWK WKH &%&+6 ,7 VWDII.
3URMHFW IQFOXGHG: 'HVLJQ, +DUGZDUH, 6RIWZDUH, )XUQLWXUH, *DPH /LFHQVHV, )HHV, ,QVWDOODWLRQ,
(OHFWULFDO & 1HWZRUNLQJ
OXWFRPH:
Ɣ 3& *DPLQJ 6WDWLRQV
Ɣ &RQVROH 6WDWLRQV
Ɣ )XUQLWXUH
Ɣ 12[ µ0LUURUHG¶ 6SHFWDWRU 79V
Ɣ 12[ /RJLWHFK 6WUHDPLQJ &DPV
Ɣ 3;( 6HUYHU
Ɣ JJ/HDS VRIWZDUH, JDPHV & PDLQWHQDQFH VXSSRUW
5RVH HXOPDQ IQVWLWXWH RI 7HFKQRORJ\
6SDFH: 00 VTXDUH IHHW
6WDWLRQV: 2
3URMHFW IQFOXGHG: 'HVLJQ, +DUGZDUH, 6RIWZDUH, )XUQLWXUH, *DPH /LFHQVHV, )HHV, ,QVWDOODWLRQ,
(OHFWULFDO & 1HWZRUNLQJ
6XPPDU\: ,Q 201 5RVH +XOPDQ ZDQWHG WR EXLOG D WULDO HVSRUWV FHQWHU RQ FDPSXV. :LWK OLPLWHG
VSDFH DYDLODEOH WKH WHDP ZDV FKDOOHQJHG WR FRPH XS ZLWK DQ HIILFLHQW OD\RXW WR PD[LPL]H WKH
QXPEHU RI VWDWLRQV WR ILW LQWR WKH VSDFH. 7KH WHDP FDPH XS ZLWK D YHU\ HIILFLHQW DQG
FRVW-HIIHFWLYH VROXWLRQ WKDW DOORZHG IRU PD[LPXP JDPLQJ VWDWLRQV DQG D IXQFWLRQDO VHWXS. 7KH
SODQ LV WR DGG WR WKLV VSDFH LQ WKH IXWXUH.
OXWFRPH:
Ɣ 20 3& *DPLQJ 6WDWLRQV
Ɣ 3;( 6HUYHU
Ɣ JJ/HDS VRIWZDUH, JDPHV DQG PDLQWHQDQFH VXSSRUW
Section II Plan And EqXipment QXestionnaire
1.Attach an e[planation of \oXr plan or la\oXt for performing proposed Zork. (E[amples
coXld inclXde a narratiYe of Zhen \oX coXld begin Zork, complete the project, nXmber of
Zorkers, etc. and an\ other information Zhich \oX belieYe ZoXld enable the Cit\ of
SoXth Bend to consider \oXr bid.)
ggCircXit in conjXnction Zith oXr project partners CreatiYe Works haYe oYer 80
emplo\ees speciali]ing in project management, netZorking & IT, esports eYents,
program & deYelopment, bXildoXt & fabrication, lighting technicians and aXdio engineers.
Like most projects Ze deal Zith, ô of the time Zill be spent on material procXrement,
fabrication, and preparation.
Upon being aZarded the SoXth Bend Contract, the folloZing timeline Zill be proposed:
Ɣ Sept 8th : AnnoXncement of contract
Ɣ Sept 9th - Sept 22nd: DiscXss project and change orders Zith Client
Ɣ Sept 23rd: Contact CreatiYe Works, oXr sXb-contracting partner, to start
fabrication Zork for staging, scenic, rigging, lights
Ɣ Sept 23rd: Place orders for compXters and all reqXired BOM materials. DiscXss
change orders Zith the project board.
Ɣ Sept 28 - Oct 30th : ReceiYe, inYentor\ & organi]e BOM
Ɣ NoY 2nd - NoY 13th : BXild & program POS serYer & NetZorking eqXip
Ɣ NoY 23rd - 27th : Prepare transport for BOM and personnel to arriYe on-site for
the project.
Ɣ NoY 30th - Dec 10th : Install project
Ɣ Dec 11th - 12th : Final inspection, QA, clean-Xp.
Ɣ Dec 13th/14th : TXrn oYer to stakeholders
2.Attach a listing of the names and addresses of all sXbcontractors (i.e. persons or firms
oXtside \oXr oZn firm Zho haYe performed part of the Zork) that \oX haYe Xsed on
pXblic Zorks projects dXring the past fiYe (5) \ears along Zith a brief description of the
Zork done b\ each sXbcontractor.
CreatiYe Works, Inc.
CreatiYe Works, Inc. has been creating poZerfXl memories throXgh immersiYe
attractions for the last 22 \ears. Based in MooresYille, IN, CreatiYe Works serYes
Location Based Entertainment YenXes across the coXntr\ and the Zorld; bXilding
attractions like Laser Tag Arenas, Escape Rooms, VirtXal and AXgmented Realit\,
Hi-Tech Mini Golf, in addition to Esports Arenas/LoXnges. CWI is obsessed Zith creating
a space Zhere a gXest can become the main character of their oZn stor\.
CreatiYe Works has proYided cXstom Esports enYironments to single site locations,
mXlti-site cXstomers like GameWorks across the coXntr\, and to RainboZ¶s End
AmXsement Park in NeZ Zealand oYer the last 3 \ears, partnering Zith ggCircXit for
eYer\ project the\ bXild.
3.If \oX intend to sXblet an\ portion of the Zork, attach the name and address of each
sXbcontractor, eqXipment to be Xsed b\ the sXbcontractor, and Zhether \oX Zill reqXire
a bond. HoZeYer, if \oX are Xnable to cXrrentl\ proYide a listing, please Xnderstand a
listing mXst be proYided prior to contract approYal. Until the completion of the proposed
project, \oX are Xnder a continXing obligation to immediatel\ notif\ the Cit\ of SoXth
Bend in the eYent that \oX sXbseqXentl\ determine that \oX Zill Xse a sXbcontractor on
the proposed project.
ż CreatiYe Works, Inc.
350 Bridge St.
MooresYille, IN 46518
No bond reqXired
4.Attach a listing of eqXipment \oX haYe aYailable to Xse for the proposed project.
ż NetZorking tools
ż Ladders
ż As needed, pallet jacks & scissor lifts Zill be rented as Zell as an\ additional
eqXipment
5.HaYe \oX entered into contracts or receiYed offers for all materials Zhich sXbstantiate
the prices Xsed in preparing \oXr proposal? If not, attach an e[planation for the rationale
Xsed Zhich ZoXld corroborate the prices listed.
ż Yes
BID/PROPOSAL
CITY OF SOUTH BEND
Project Name: Century Center Esports Arena
Project Number: 119-106CR
For Bids Due: September 8, 2020 by 9:30 AM Local Time
Contractor Name:
Version 4/2/2019 Contractor’s Bid for Public Works - 7
BASE BID
Item
No. Description Quantity Unit Unit Price Total Amount
1 Material Procurement per attached BOM 1 LS
2 Staging/Scenic/Rigging Labor 1 LS
3 Low Voltage Labor 1 LS
4 IT/Networking Labor 1 LS
5 Audio/Video Labor 1 LS
6 Lighting Labor 1 LS
7 Other Labor 1 LS
BASE BID TOTAL
Bidder (Firm):
Address:
City/State/Zip: Telephone Number: ( )
By
(Signature)
(Printed Name of Person Signing)
$279,037.59$279,037.59
$43,910.00
$900.00
$13,365.00
$5,220.00
$11,700.00
$24,750.00
$43,910.00
$900.00
$13,365.00
$5,220.00
$11,700.00
$24,750.00
$378,882.59
ggCircuit LLC
ggCircuit LLC
2303 S. 3rd Street
Terre Haute, IN 47802 812 230-5671
Zack Johnson, CEO
CITY OF SOUTH BEND MINORITY AND WOMEN BUSINESS ENTERPRISE DIVERSITY DEVELOPMENT PROGRAM FORM MWBE-1.0 MBE/WBE PARTICIPATION Version 4/2/2019 Contractor’s Bid for Public Works - 8 This completed form should be supplied with Bids that pertain to City of South Bend Public Works Projects involving MBE/MBE participation. It is the bidder’s sole responsibility to verify whether any listed minority or woman business meets the qualifications of a Minority or Women’s owned business. Project Number: 119-106CR Project Name: Century Center Esports Arena Bidder: Total Bid Amount: MBE/WBE Goal: Page_______of___ ____ Name & Address of MBE/WBE Primary Contact Person (Name/Telephone) Scope of Work to be Performed (Attach scope/schedule if you need additional space) Dollar Amount of MBE/WBE Component Percentage of Total Bid/Proposal Submitted by: Print Name Signature Date ggCircuit LLCN/A (All work to be completed by ggCircuit LLC & Creative Works)Zack Johnson, CEOJuly 27, 2020
CITY OF SOUTH BEND
MINORITY AND WOMEN BUSINESS ENTERPRISE DIVERSITY
DEVELOPMENT PROGRAM
FORM MWBE-2.0
EVIDENCE OF GOOD FAITH EFFORTS
Version 4/2/2019 Contractor’s Bid for Public Works - 9
This completed form should be included as part of the Bids documents related to City of South Bend Public
Works Projects requiring Good Faith Efforts to obtain MBE/WBE participation. It is the bidder’s sole
responsibility to verify whether any listed minority or woman business meets the qualifications of a Minority
or Women’s owned business as defined by the Indiana Department of Administration (“IDOA”).
Project Number: 119-106CR Date:
Project Name: Century Center Esports Arena
Bidder:
Contact Person: Telephone:
Address:
City: State: Zip:
Email:
To determine whether a bidder has demonstrated good faith efforts to reach the MBE/WBE utilization goals set
forth in the City of South Bend Public Works Project Specifications, the City and its agencies, boards, or
commissions, REQUIRE ALL of the following Good Faith Efforts as listed in the table below*:
EVIDENCE OF GOOD FAITH EFFORTS
MBE/WBE LIST(S): The bidder reviewed the City of South Bend’s Minority and Women Business
Enterprise Diversity Development Program, which uses the IDOA approved list of Minority and Women
Owned Business as found on their website (http://www.in.gov/idoa).
ACTION (ADVERTISE/CONTACT): In order for your bid to be deemed responsive, the City of South
Bend requires that all perspective bidders complete no less than 2 of the following:
1. Attend all pre-bid meetings scheduled by the City to inform MBE/WBEs of contracting and
subcontracting opportunities.
2. Advertise in general circulation and/or trade association publications concerning subcontracting
opportunities, and allow MBE/WBEs reasonable time to respond.
3. Perform any and all necessary steps to provide written notice in a manner reasonably calculated
to inform MBE/WBEs of subcontracting opportunities and allowed sufficient time for them to
participate effectively.
4. Utilize pre-existing services of available community organizations, small and/or disadvantaged
business assistance offices and other organizations that provided assistance in the recruitment
and placement of MBE/WBE firms.
**Bidder must circle or otherwise notate which of the two (2) required actions were performed.
GOOD FAITH NEGOTIATIONS: The bidder negotiated in good faith with interested MBE/WBEs,
including providing such MBE/WBE’s with adequate information about the plans, specifications and other
requirements of the subcontract and did not reject MBE/WBEs as unqualified without sound business
reasons based on a thorough investigation of their capabilities.
SMALL CONTRACT(S): The bidder selected specific portions of the work to be performed by
MBE/WBEs in order to increase the likelihood of meeting the MBE/WBE goals (including breaking down
contracts into smaller units to facilitate MBE/WBE participation)
CONTRACT RECORDS: The bidder has maintained the following records for each MBE/WBE that has
bid on the subcontracting opportunity:
1. Name, address, and telephone number;
2. A description of information provided by the bidder or subcontractor; and
3. A statement of whether an agreement was reached, and if not, why not, including any reasons for
concluding that the MBE/WBE was unqualified to perform the job.
*Proper demonstration of Good Faith Effort requires your initials next to all of the above boxes. Any
omissions shall be considered grounds for rejection of the bid by the Board of Public Works. The City of
South Bend reserves the right to request additional information.
ggCircuit LLC
July 27, 2020
2303 S. 3rd Street
Terre Haute IN 47802
sales@ggcircuit.com
812-230-5671
CITY OF SOUTH BEND
MINORITY AND WOMEN BUSINESS ENTERPRISE DIVERSITY
DEVELOPMENT PROGRAM
FORM MWBE-2.1
MBE/WBE CONTACTED
Version 4/2/2019 Contractor’s Bid for Public Works - 10
This completed form should be supplied with Bids that pertain to City of South Bend Public Works Projects
requiring contacted MBE/WBE to obtain Good Faith Efforts. It is the bidder’s sole responsibility to verify
whether any listed minority or woman business meets the qualifications of a Minority or Women’s owned
business.
PAGE_______OF________
Project Number: 119-106CR MBE/WBE Participation Goal
Project Name: Century Center Esports Arena
Bidder:
By:
(Signature) (Title) (Date)
MBE/WBE Firm
Owner or Contact at MBE/WBE Firm
Telephone
: Fax
: Email:
TYPE OF WORK SOLICITED FOR THIS PROJECT:
RESULTS OF CONTACT WITH THE MBE/WBE FIRM:
MBE/WBE Firm
Owner or Contact at MBE/WBE Firm
Telephone
: Fax
: Email:
TYPE OF WORK SOLICITED FOR THIS PROJECT:
RESULTS OF CONTACT WITH THE MBE/WBE FIRM:
ggCircuit LLC
July 27, 2020CEO
N/A (All work to be completed by ggCircuit LLC & Creativeworks
I 3 16 CouNrv-Ctrv Bunowc
227 W . IrwrxsoN BourBvano
Sounr BsNp, INoraNa 46601-1 830
lo".?gYil'+.i4rr,.,,i,*r''k itc'.,.
I LJi +*S ,v-l.,,, rn:ncx ]. ,'t.,.'B " ;-r..{l},:t :''-,a?.'
i. r'i.-. ']t-. :.
",.,.I-ifi.-.r',''
PHoNE
FAx
TDD
s74t 235-9251
s74t 235-9171
574t 235-5567
Crv or Sours Bswp Jaups MueLLeR, Mavon
BOano OF PUBLIC WORIG
Auzust 25,2020
All Planholders
Linda M. Martin, Clerk, Board of Public Works
Date:
To:
From
Subject
Project Name:
Project No.:
Addendum Nurnber: I
Century Center Esports Arena
119-106CR
ACKNOWLEDGEMENT OF RECEIPT OF ADDENDUM
Date Received:
This addendum is being forwarded to you for the above referenced project.
faxing this sheet to the Board of
within 48 hours of receipt. A copy
at (574) 23s-9171
included with your
Please sign below and acknowledge receipt of this Addendum by
bid package upon submittal.
THIS ADDENDUM MAY AFFECT YOUR BID.
Notes:
Public Works
MUST also be
The attached documents are hereby added to the Specifications and Contract
Documents and become apart of herein.
Company:
Authorized Signature:
Date:
Version 5/16/2019 General Conditions - 8
I. PRE-QUALIFIED BIDDER CHECKLIST
(a) Acknowledgements:
(i) ___ By checking this box, I hereby acknowledge that I am a pre-qualified bidder with
the City of South Bend and that I have met the pre-qualification requirements within
the last twelve (12) months. A copy of my Pre-Qualification verification letter
is attached.
(ii) ___ By checking this box, I hereby acknowledge that the City reserves the right to
request supplemental information, additional verification of any information
provided by me, and may also conduct random inquiries of my current and prior
customers.
(b) Attachments:
(i) ___ Indiana Secretary of State’s on-line records (ie. Business verification) dated within
sixty (60) days of the submission of said document showing that business is in
existence, current with the Indiana Secretary of State’s Business Entity Report,
and eligible for a certificate of good standing. (Not applicable to individuals, sole
proprietors or partnerships).
(ii) ___ Statement on staffing capabilities, including labor sources. This statement
indicates and ensures I have sufficient employees on staff to complete the work. It
outlines how I intend to meet the staffing needs of the work.
(iii) ___ List of projects of similar size and scope of work performed in all areas, including
the State of Indiana, within the last three (3) years.
(iv) ___ For every project, submit evidence of participation in apprenticeship and training
programs, applicable to the work to be performed on the project, which are
approved by and registered with the United States Department of Labor’s Office of
Apprenticeship, or its successor organization.
X
X
X
X
X
X
Version 5/16/2019 General Conditions - 9
II. PRE-QUALIFICATION CHECKLIST (FOR BIDDERS THAT ARE NOT PRE-QUALIFIED)
(a) Acknowledgements:
(i) ___ By checking this box, I hereby acknowledge that I am not a pre-qualified bidder
with the City of South Bend.
(ii) ___ By checking this box, I hereby acknowledge that the City reserves the right to
request supplemental information, additional verification of any information
provided, and may also conduct random inquiries of my current and prior
customers. The City reserved the right to utilize all information provided in this
submission and all information obtained in inquiries or requests to determine if a
bidder is responsive and responsible. Additionally, I acknowledge that all
information provided to the City shall be regarded as public records.
(iii) ___ By checking this box, I hereby acknowledge that copies of all Applicable
apprenticeship certificates or standards for training programs applicable to the
work performed on the project may be requested at any time and shall be furnished
upon request.
(iv) ___ By checking this box, I hereby acknowledge and ensure that I and all sub-
contractors, from whom I have accepted a bid and/or intend to hire to perform work
on the public work project, are properly licensed. Furthermore, I acknowledge my
understanding that it is my responsibility to ensure that all sub-contractors have
the necessary licenses to undertake the work called for in this bid. If a sub-
contractor loses their license at any point, it is the responsibility of that sub-
contractor to notify the City.
(b) Attachments:
(i) ___ Indiana Secretary of State’s on-line records (ie. Business verification) dated within
sixty (60) days of the submission of said document showing that business is in
existence, current with the Indiana Secretary of State’s Business Entity Report,
and eligible for a certificate of good standing. (Not applicable to individuals, sole
proprietors or partnerships).
(ii) ___ List identifying all former business names.
(iii) ___ Any determinations by a court or governmental agency any violations of federal
state, or local laws including, but not limited to, violations of contracting or antitrust
laws, tax or licensing laws, environmental laws, Occupational Safety and Health
Act (OSHA), or federal Davis-Bacon and related Acts, within the preceding five (5)
years.
(iv) ___ Statement about staffing capabilities, including labor sources. This statement
indicates and ensures I have sufficient employees on staff to complete the work I
am bidding on OR outlines how I intend to meet the staffing needs of the work.
(v) ___ Statement that individuals who will perform work on the public work project on my
behalf will be properly classified as an employee or as an independent contractor
under all applicable state and federal laws and local ordinances.
(vi) ___ For every project, submit evidence of participation in apprenticeship and training
programs, applicable to the work to be performed on the project, which are
approved by and registered with the United States Department of Labor’s Office of
Apprenticeship, or its successor organization.
(vii) ___ Copy of a written plan for employee drug testing that covers all of my employees
who will perform work on the public work project and meets or exceeds the
requirements set forth in IC 4-13-18-5 or IC 4-13-18-6.
(viii) ___ Evidence that I am utilizing a surety company which is on the Bureau of Fiscal
Service “Department of Treasury’s Listing of Approved Sureties” as required in the
bid specifications or contract.
Version 5/16/2019 General Conditions - 10
(ix) ___ Written statement of any federal, state or local tax liens or tax delinquencies owed
to any federal, state or local taxing body in the preceding three years.
(i) ___ List of projects of similar size and scope of work performed in all areas, including
the State of Indiana, within three (3) years prior to the date on which the bid is due.
Date: ___________________________________________
________________________________________________
(Sign Here)
________________________________________________
(Print Name Here)
________________________________________________
(Name of Company)
________________________________________________
(Address of Company)
________________________________________________
(City)
________________________________________________
(State)
________________________________________________
(Telephone Number)
9/3/2020
Zack Johnson
ggCircuit LLC
2303 S. 3rd Street
Terre Haute
Indiana
(812) 230-5671
State of Indiana
Office of the Secret ary of State
CERTIFICATE OF EXISTENCE
To Whom These Presents Come, Greeting:
I, CONNIE LAWSON, Secretary of State of Indiana, do hereby certify that I am, by virtue of the laws of
the State of Indiana, the custodian of the corporate records and the proper official to execute this
certificate.
I further certify that records of this office disclose that
GGCIRCUIT, LLC
duly filed the requisite documents to commence business activities under the laws of the State of
Indiana on March 01, 2018, and was in existence or authorized to transact business in the State of
Indiana on July 22, 2020.
I further certify this Domestic Limited Liability Company has filed its most recent report required by
Indiana law with the Secretary of State, or is not yet required to file such report, and that no notice of
withdrawal, dissolution, or expiration has been filed or taken place. All fees, taxes, interest, and
penalties owed to Indiana by the domestic or foreign entity and collected by the Secretary of State
have been paid.
In Witness Whereof, I have caused to be affixed my
signature and the seal of the State of Indiana, at the City
of Indianapolis, July 22, 2020
CONNIE LAWSON
SECRETARY OF STATE
201803011243666 / 20201536353
All certificates should be validated here: https://bsd.sos.in.gov/ValidateCertificate
Expires on August 21, 2020.
State of Indiana
Office of the Secret ary of State
CERTIFICATE OF EXISTENCE
To Whom These Presents Come, Greeting:
I, CONNIE LAWSON, Secretary of State of Indiana, do hereby certify that I am, by virtue of the laws of
the State of Indiana, the custodian of the corporate records and the proper official to execute this
certificate.
I further certify that records of this office disclose that
CREATIVE WORKS, INC.
duly filed the requisite documents to commence business activities under the laws of the State of
Indiana on October 09, 1997, and was in existence or authorized to transact business in the State of
Indiana on July 27, 2020.
I further certify this Domestic For-Profit Corporation has filed its most recent report required by
Indiana law with the Secretary of State, or is not yet required to file such report, and that no notice of
withdrawal, dissolution, or expiration has been filed or taken place. All fees, taxes, interest, and
penalties owed to Indiana by the domestic or foreign entity and collected by the Secretary of State
have been paid.
In Witness Whereof, I have caused to be affixed my
signature and the seal of the State of Indiana, at the City
of Indianapolis, July 27, 2020
CONNIE LAWSON
SECRETARY OF STATE
1997100597 / 20201543129
All certificates should be validated here: https://bsd.sos.in.gov/ValidateCertificate
Expires on August 26, 2020.
/LVW ,GHQWLI\LQJ $OO )RUPHU %XVLQHVV 1DPHV
1HLWKHU JJ&LUFXLW //& RU &UHDWLYH :RUNV, ,QF. KDYH DQ\ SULRU EXVLQHVV QDPHV.
'HWHUPLQDWLRQV RI 9LRODWLRQV
1HLWKHU JJ&LUFXLW //& RU &UHDWLYH :RUNV, ,QF. KDYH DQ\ GHWHUPLQDWLRQV RI YLRODWLRQV ZLWKLQ WKH
SUHFHGLQJ \HDUV.
6WDIILQJ &DSDELOLW\ 6WDWHPHQW
JJ&LUFXLW'V VSHFLDO RSHUDWLRQV WHDP SXOOV IURP 20 \HDUV RI H[SHULHQFH RI RZQLQJ, PDQDJLQJ DQG
UXQQLQJ HVSRUW FHQWHUV WR KHOS \RX JURZ \RXU EXVLQHVV. 7KLV FUDFN FRQVXOWLQJ WHDP FDQ KHOS ZLWK
HYHU\ DVSHFW RI YLVXDOL]LQJ, VHWWLQJ XS, RSHQLQJ DQG RSHUDWLQJ \RXU HVSRUW DUHQD. ,Q SDUWQHUVKLS
ZLWK &UHDWLYH:RUNV, ZH ORRN IRUZDUG WR HQJDJLQJ WKH IROORZLQJ WHDPV
Ɣ JJ&LUFXLW 6SHF2SV 3URIHVVLRQDO 6HUYLFHV 7HDP 3 IXOO-WLPH SURIHVVLRQDO VHUYLFHV WHDP
PHPEHUV IRFXVVHG RQ GHSOR\LQJ EHVW LQ FODVV HVSRUWV WHFKQRORJ\ VROXWLRQV DQG
LQVWDOODWLRQ ODERU.
Ɣ JJ&LUFXLW 6XSSRUW 7HDP VXSSRUW SURIHVVLRQDOV RIIHULQJ RQJRLQJ SURGXFW VXSSRUW IRU
JJ&LUFXLW WHFKQRORJ\ WRROV.
&RUH &DSDELOLWLHV
Ɣ )LQDQFLDO 3ODQQLQJ
Ɣ &HQWHU 'HVLJQ
Ɣ 7HFKQLFDO 6HW 8S DQG 6XSSRUW
Ɣ 2SHUDWLRQV
Ɣ 7UDLQLQJ
Ɣ ,QVWDOODWLRQ
&UHDWLYH :RUNV, ,QF. FXUUHQWO\ HPSOR\V 2 IXOO WLPH VWDII, FRQVLVWLQJ RI IDEULFDWRUV, GHVLJQHUV,
WHFKQLFDO VXSSRUW WHFKQLFLDQV, SURMHFW PDQDJHUV, DGPLQLVWUDWLYH, VDOHV, PDUNHWLQJ, DQG H[HFXWLYH
PDQDJHUV. :H FXVWRP IDEULFDWH WKHPHG HOHPHQWV LQFRUSRUDWLQJ VSHFLDO HIIHFWV IRU RYHU % RI
RXU SURMHFWV DQG KDYH PRUH WKDQ HQRXJK HPSOR\HHV WR FRYHU WKH VFRSH RI ZRUN LQFOXGHG LQ RXU
VXEFRQWUDFWHG SRUWLRQ. ,Q DGGLWLRQ, ZH KDYH PXOWLSOH YHQGRUV IRU HDFK RI WKH YDULRXV SURGXFWV
OLNH WUXVV, OLJKWLQJ, HOHFWULFDO FRPSRQHQWV, HWF. WR HQVXUH ZH FDQ SURFXUH PDWHULDOV QHHGHG IRU
RXU SRUWLRQ.
6WDWHPHQW $ERXW (PSOR\HH &ODVVLILFDWLRQ
JJ&LUFXLW KDV SDUWQHUHG ZLWK )XOO6WDFN 3(2 WR HQVXUH FRPSOLDQFH ZLWK DOO DSSOLFDEOH ODERU ODZV
DQG UHJXODUO\ UHYLHZV HPSOR\PHQW SUDFWLFHV WR HQVXUH WKDW DOO HPSOR\HHV DUH SURSHUO\ FODVVLILHG
DV DQ HPSOR\HH RU DQ LQGHSHQGHQW FRQWUDFWRU.
&UHDWLYH :RUNV, ,QF. KHUHE\ DIILUPV WKDW DOO LQGLYLGXDOV ZKR ZLOO SHUIRUP ZRUN RQ WKH SXEOLF ZRUN
SURMHFW DUH FODVVLILHG DV IXOO-WLPH HPSOR\HHV XQGHU DOO DSSOLFDEOH VWDWH DQG IHGHUDO ODZV DQG ORFDO
RUGLQDQFHV.
Employment Categories
FullTime Emplosee
An emplosee who works ÄÁ hours or more per work week is considered fulltime The
emplosee is entitled to all benefits
PartTime Emplosee
An emplosee who works less than ÄÁ hours per week is considered parttime Parttime
emplosees are onls eligible for retirement plan participation and are not eligible for health
dental vision life or ans paid time off plans
TemporarsIntern Emplosee
TemporarsIntern emplosees are hired for a specific period of time project or assignment This
emplosee is paid for actual hours worked and is not eligible for benefits Emplosees hired for a
specific project or period of time will change to parttime status if emplosed besond ÂÃÁ dass
([HPSW DQG 1RQH[HPSW
Emplosees are also classified as nonerempt or erempt emplosees in accordance with the
provisions of the Federal Fair Labor Standards Act ¥FLSA¦ and ans applicable laws FullStack pass
overtime in accordance with the FLSA and ans additional applicable law Overtime pas will not
be paid when positions meet the FLSA guidelines for eremption
$SSUHQWLFHVKLS DQG 7UDLQLQJ 3URJUDPV
JJ&LUFXLW UHJXODUO\ HQJDJHV HPSOR\HHV WR WUDLQ DQG DFTXLUH FHUWLILFDWLRQV LQ WKHLU DUHD RI LPSDFW.
([DPSOHV LQFOXGH 07&1$ - 0LNURWLN &HUWLILHG 1HWZRUN $VVRFLDWH FHUWLILFDWLRQV IRU DOO RI RXU
6SHF2SV SURIHVVLRQDO VHUYLFHV WHDP DQG DUH UHYLHZHG RQ D \HDUO\ EDVLV.
&UHDWLYH :RUNV GRHV QRW FXUUHQWO\ KDYH DQ\ DSSUHQWLFHVKLS SURJUDPV UHTXLUHG E\ WKH 8QLWHG
6WDWHV 'HSDUWPHQW RI /DERU¶V 2IILFH RI $SSUHQWLFHVKLS IRU WKH VFRSH RI ZRUN LQ WKLV SURMHFW.
+RZHYHU, ZH GR HQJDJH LQ UHJXODU WUDLQLQJ DQQXDOO\ IRU RXU HPSOR\HHV LQFOXGLQJ
DQWL-KDUDVVPHQW, HTXLSPHQW VDIHW\ SURWRFROV (L.H. IRUNOLIWV, SRZHU WRROV, HWF.) 2XU HPSOR\HHV DUH
UHTXLUHG WR FRPSOHWH SURILFLHQF\ HYDOXDWLRQV ZLWKLQ 0 GD\V RI WKHLU KLUH GDWH WR VKRZ WKH\ DUH
DEOH WR SHUIRUP WKHLU FRUH DUHDV RU UHVSRQVLELOLWLHV.
(PSOR\HH 'UXJ 7HVWLQJ 3URJUDP
JJ&LUFXLW¶V (PSOR\HH 'UXJ 7HVWLQJ 3URJUDP LQFOXGHV UDQGRP WHVWLQJ RI HPSOR\HHV RQ D JLYHQ
TXDOLILHG FRQWUDFW. $W OHDVW WZR SHUFHQW (2%) RI WKH FRQWUDFWRU'V HPSOR\HHV PXVW EH UDQGRPO\
VHOHFWHG HDFK PRQWK IRU WHVWLQJ, DQG HYHU\ HPSOR\HH PXVW VXEPLW WR D GUXJ WHVW HDFK \HDU. 7KLV
WHVW LQFOXGHV D ILYH () VFUHHQ GUXJ SDQHO. 7KRVH ILYH VXEVWDQFHV LQFOXGH DPSKHWDPLQHV,
FRFDLQH, RSLDWHV (2000 QJ/PO), 3&3, DQG 7+&.
,I DQ HPSOR\HH IDLOV D GUXJ WHVW, KH/VKH LV VXEMHFW WR SURJUHVVLYH GLVFLSOLQDU\ DFWLRQ XQGHU WKH
IROORZLQJ SURJUHVVLRQ
1)$IWHU WKH ILUVW SRVLWLYH WHVW, DQ HPSOR\HH PXVW EH VXVSHQGHG IURP ZRUN IRU WKLUW\ (30)
GD\V GLUHFWHG WR D SURJUDP RI WUHDWPHQW RU UHKDELOLWDWLRQ DQG VXEMHFW WR XQDQQRXQFHG
GUXJ WHVWLQJ IRU RQH (1) \HDU, EHJLQQLQJ WKH GD\ WKH HPSOR\HH UHWXUQV WR ZRUN.
2)$IWHU D VHFRQG SRVLWLYH WHVW, DQ HPSOR\HH PXVW EH VXVSHQGHG IURP ZRUN IRU QLQHW\ (0)
GD\V GLUHFWHG WR D SURJUDP RI WUHDWPHQW RU UHKDELOLWDWLRQ DQG VXEMHFW WR XQDQQRXQFHG
GUXJ WHVWLQJ IRU RQH (1) \HDU, EHJLQQLQJ WKH GD\ WKH HPSOR\HH UHWXUQV WR ZRUN.
3)$IWHU D WKLUG RU VXEVHTXHQW SRVLWLYH WHVW, DQ HPSOR\HH PXVW EH VXVSHQGHG IURP ZRUN IRU
RQH (1) \HDU GLUHFWHG WR D SURJUDP RI WUHDWPHQW RU UHKDELOLWDWLRQ DQG VXEMHFW WR
XQDQQRXQFHG GUXJ WHVWLQJ IRU RQH (1) \HDU, EHJLQQLQJ WKH GD\ WKH HPSOR\HH UHWXUQV WR
ZRUN.
,I WKH HPSOR\HH LV VXVSHQGHG, WKH HPSOR\HH LV QRW HOLJLEOH IRU UHLQVWDWHPHQW XQWLO WKH HPSOR\HH
WHVWV QHJDWLYH RQ D ILYH () GUXJ SDQHO WHVW FHUWLILHG E\ D PHGLFDO UHYLHZ RIILFHU. JJ&LUFXLW DOVR
UHVHUYHV WKH ULJKW WR GLVFLSOLQH XS WR LPPHGLDWH GLVPLVVDO XSRQ DQ\ SRVLWLYH ILYH () VFUHHQ GUXJ
SDQHO.
/DVW, JJ&LUFXLW ZLOO GLUHFW DQ HPSOR\HH WR D SURJUDP RI WUHDWPHQW RU UHKDELOLWDWLRQ E\ HLWKHU
DGYLVLQJ WKH HPSOR\HH RI DQ\ SURJUDP RI WUHDWPHQW RU UHKDELOLWDWLRQ FRYHUHG E\ LQVXUDQFH
SURYLGHG E\ WKH HPSOR\HU, RU DGYLVLQJ WKH HPSOR\HH RI DJHQFLHV NQRZQ WR WKH HPSOR\HU WKDW
SURYLGH GUXJ WUHDWPHQW RU UHKDELOLWDWLRQ SURJUDPV.
BBBBBBBBBBBBBBBBBBBBBBBBBBBBB
&UHDWLYH :RUNV LV FRPPLWWHG WR SURYLGLQJ D VDIH,KHDOWK\,DQG SURGXFWLYH ZRUN HQYLURQPHQW.
&RQVLVWHQW ZLWK WKLV FRPPLWPHQW,LW LV WKH LQWHQW RI WKH &RPSDQ\WR PDLQWDLQ D GUXJ DQG
DOFRKRO-IUHH ZRUNSODFH.%HLQJ XQGHU WKH LQIOXHQFH RI DOFRKRO,LOOHJDO GUXJV (DV FODVVLILHG
XQGHU IHGHUDO,VWDWH,RU ORFDO ODZV),RU RWKHU LPSDLULQJ VXEVWDQFHV ZKLOH RQ WKH MRE PD\SRVH
D VHULRXV KHDOWK DQG VDIHW\ ULVN WR RWKHUV, DQG ZLOO QRW EH WROHUDWHG.
3URKLELWHG CRQGXFW
7KH &RPSDQ\H[SUHVVO\SURKLELWV WHDP PHPEHUV IURP HQJDJLQJ LQ WKH IROORZLQJ DFWLYLWLHV
ZKHQ WKH\DUH RQ GXW\RU FRQGXFWLQJ &RPSDQ\EXVLQHVV RU RQ &RPSDQ\SUHPLVHV (ZKHWKHU
RU QRW WKH\DUH ZRUNLQJ)LQFOXGLQJ ZKLOH WUDYHOLQJ RQ EHKDOI RI WKH &RPSDQ\IRU LQVWDOODWLRQV,
WUDGH VKRZV, DQG HYHQWV
Ɣ 7KH XVH RI DOFRKRO GXULQJ QRUPDO ZRUN GXWLHV (H[FOXGLQJ FRPSDQ\VDQFWLRQHG VRFLDO
HYHQWV),WKH DEXVH,RU EHLQJ XQGHU WKH LQIOXHQFH RI LOOHJDO GUXJV,RU RWKHU LPSDLULQJ
VXEVWDQFHV.
Ɣ 7KH SRVVHVVLRQ,VDOH,SXUFKDVH,WUDQVIHU,RU WUDQVLW RI DQ\LOOHJDO RU XQDXWKRUL]HG
GUXJ,LQFOXGLQJ SUHVFULSWLRQ PHGLFDWLRQ WKDW LV QRW SUHVFULEHG WR WKH LQGLYLGXDO,RU
GUXJ-UHODWHG SDUDSKHUQDOLD.
Ɣ 7KH LOOHJDO XVH RU DEXVH RI SUHVFULSWLRQ GUXJV.
:KLOH WKH XVH RI PDULMXDQD KDV EHHQ OHJDOL]HG XQGHU VRPH VWDWH ODZV IRU PHGLFLQDO DQG/RU
UHFUHDWLRQDO XVHV,LW UHPDLQV DQ LOOHJDO GUXJ XQGHU IHGHUDO ODZ.7KH &RPSDQ\GRHV QRW
GLVFULPLQDWH DJDLQVW WHDP PHPEHUV VROHO\RQ WKH EDVLV RI WKHLU ODZIXO RII-GXW\XVH RI
PDULMXDQD.<RX PD\QRW FRQVXPH RU EH XQGHU WKH LQIOXHQFH RI PDULMXDQD ZKLOH RQ GXW\RU DW
ZRUN.,I \RX KDYH D YDOLG SUHVFULSWLRQ IRU PHGLFDO PDULMXDQD,UHIHU WR WKH &RPSDQ\'LVDELOLW\
$FFRPPRGDWLRQ SROLF\ IRU DGGLWLRQDO LQIRUPDWLRQ.
1RWKLQJ LQ WKLV SROLF\LV PHDQW WR SURKLELW \RXU DSSURSULDWH XVH RI RYHU-WKH-FRXQWHU
PHGLFDWLRQ RU RWKHU PHGLFDWLRQ WKDW FDQ OHJDOO\EH SUHVFULEHG XQGHU ERWK IHGHUDO DQG VWDWH
ODZ,LI LW GRHV QRW LPSDLU \RXU MRE SHUIRUPDQFH RU VDIHW\RU WKH VDIHW\RI RWKHUV.,I \RX WDNH
RYHU-WKH-FRXQWHU PHGLFDWLRQ RU RWKHU PHGLFDWLRQ WKDW FDQ OHJDOO\EH SUHVFULEHG XQGHU ERWK
IHGHUDO DQG VWDWH ODZ WR WUHDW D GLVDELOLW\,LQIRUP \RXU 0DQDJHU LI \RX EHOLHYH WKH PHGLFDWLRQ
PD\LPSDLU \RXU MRE SHUIRUPDQFH,VDIHW\,RU WKH VDIHW\RI RWKHUV RU LI \RX EHOLHYH \RX QHHG D
UHDVRQDEOH DFFRPPRGDWLRQ EHIRUH UHSRUWLQJ WR ZRUN ZKLOH XQGHU WKH LQIOXHQFH RI WKDW
PHGLFDWLRQ.
)URP WLPH WR WLPH,WKH &RPSDQ\PD\VSRQVRU VRFLDO RU EXVLQHVV-UHODWHG HYHQWV ZKHUH
DOFRKRO PD\EH VHUYHG.7KLV SROLF\GRHV QRW SURKLELW WKH XVH RU FRQVXPSWLRQ RI DOFRKRO DW
WKHVH HYHQWV.+RZHYHU,LI \RX FKRRVH WR FRQVXPH DOFRKRO DW VXFK HYHQWV,\RX PXVW GR VR
UHVSRQVLEO\DQG PDLQWDLQ \RXU REOLJDWLRQ WR FRQGXFW \RXUVHOI SURSHUO\DQG SURIHVVLRQDOO\DW
DOO WLPHV.'R QRW GULQN DQG GULYH.,QVWHDG,SOHDVH FDOO DQ 8EHU RU DSSRLQW D GHVLJQDWHG
GULYHU.
7UHDWPHQW DQG/RU 5HKDELOLWDWLRQ
7KH &RPSDQ\PD\DVVLVW \RX LQ VHHNLQJ WUHDWPHQW RU UHKDELOLWDWLRQ IRU GUXJ RU DOFRKRO
GHSHQGHQF\.,Q VXFK FDVHV,WKH &RPSDQ\PD\FRQVLGHU \RXU FRQWLQXHG HPSOR\PHQW DV
ORQJ DV FRQFHUQV UHJDUGLQJ VDIHW\,KHDOWK,SURGXFWLRQ,FRPPXQLFDWLRQ,RU RWKHU ZRUN-UHODWHG
PDWWHUV DUH DGHTXDWHO\DGGUHVVHG.7KH &RPSDQ\PD\DOVR UHTXLUH \RX WR REWDLQ D PHGLFDO
FOHDUDQFH DQG DJUHH WR UDQGRP WHVWLQJ DQG D "RQH-VWULNH"UXOH DV D FRQGLWLRQ RI FRQWLQXHG
HPSOR\PHQW.
9LRODWLRQV
9LRODWLRQ RI WKLV SROLF\PD\UHVXOW LQ GLVFLSOLQDU\DFWLRQ,XS WR DQG LQFOXGLQJ WHUPLQDWLRQ RI
HPSOR\PHQW.
6WDWHPHQW RI $Q\ 7D[ /LHQV/'HOLQTXHQFLHV
1HLWKHU JJ&LUFXLW //& RU &UHDWLYH :RUNV, ,QF. FXUUHQWO\ KDYH DQ\ IHGHUDO, VWDWH, RU ORFDO WD[ OLHQV
RU WD[ GHOLQTXHQFLHV RZHG WR DQ\ IHGHUDO, VWDWH, RU ORFDO WD[LQJ ERG\ LQ WKH SUHFHGLQJ WKUHH
\HDUV.
6WDWHPHQW RI 6LPLODU 3URMHFWV
&UHDWLYH :RUNV, ,QF. KDV SURYLGHG IXOO WXUQNH\ (VSRUWV IDFLOLWLHV VLQFH 201. 3URMHFWV LQFOXGH
8UEDQ $LU 6RXWK /DNH 7H[DV, 5DLQERZ¶V (QG $PXVHPHQW 3DUN LQ 1HZ =HDODQG, DQG PXOWLSOH
*DPH:RUNV ORFDWLRQV DFURVV WKH FRXQWU\. 7KHVH SURMHFWV LQFOXGHG FXVWRP EXLOW GHVNV, OLJKWLQJ
DFFHQWV, IXOO HTXLSPHQW QHHGV, WKHPLQJ, HWF. $OO RI WKHVH SURMHFWV KDYH XWLOL]HG JJ&LUFXLW¶V
VRIWZDUH IRU JDPH OLFHQVLQJ DV ZHOO. %H\RQG (VSRUWV IDFLOLWLHV, &UHDWLYH :RUNV, ,QF. GRHV RYHU 0
SURMHFWV D \HDU DQQXDOO\ ZLWK D YDULHW\ RI WKHPHG DWWUDFWLRQV IRU WKH /RFDWLRQ %DVHG
(QWHUWDLQPHQW/)DPLO\ (QWHUWDLQPHQW &HQWHU LQGXVWU\ - LQFOXGLQJ DWWUDFWLRQV OLNH /DVHU 7DJ
$UHQDV, 0LQLDWXUH *ROI &RXUVHV, (VFDSH 5RRPV, 9LUWXDO/$XJPHQWHG 5HDOLW\, DQG PRUH.
JJ&LUFXLW //& KDV H[HFXWHG VLPLODU SURMHFWV IRU *DPH6WRS, 5RVH-+XOPDQ ,QVWLWXWH RI
7HFKQRORJ\, &KULVWLDQ %URWKHUV &ROOHJH +LJK 6FKRRO DQG 'HOO/$OLHQZDUH. 7KHVH SURMHFWV
LQFOXGHG VRXUFLQJ IXUQLWXUH, KDUGZDUH DQG QHWZRUNLQJ HTXLSPHQW DV ZHOO DV VHWWLQJ XS VRIWZDUH
VROXWLRQV IRU WKH 3& FOLHQWV DQG VHUYHUV. JJ&LUFXLW KDV DOVR GHYHORSHG D FXVWRP XVHU LQWHUIDFH
IRU D UHWDLO HQYLURQPHQW IRU %HVW %X\ ORFDWLRQV QDWLRQZLGH.
PURSRVaO AddeQdXPV
AddiWiRQaO RecRPPeQdaWiRQV
BaVed RQ RXU 20+ \eaUV Rf RZQiQg, PaQagiQg, aQd iQVWaOOiQg eVSRUWV ORcaWiRQ gORbaOO\, Whe
fROORZiQg SieceV aUe cUiWicaO WR Whe RSeUaWiRQV Rf aQ eVSRUWV ceQWeU.
Ɣ AOO eVSRUWV ceQWeUV Qeed aQ RSeUaWiQg V\VWeP WR PaQage cXVWRPeUV, gaPe chRiceV, aQd
digiWaO aV ZeOO aV Sh\VicaO SURdXcW VaOeV. AV Whe gORbaO OeadeU iQ WhiV iQdXVWU\, ggCiUcXiW
UecRPPeQdV ggLeaS , RXU eVSRUWV ceQWeU PaQagePeQW V\VWeP.
Ɣ MaiQWaiQiQg PC V\VWeP XSdaWeV, dUiYeUV, aQd gaPe XSdaWeV iV a heUcXOeaQ WaVN RQ Whe
beVW Rf da\V. TR ViPSOif\ WhiV PXQdaQe WaVN, ggCiUcXiW UecRPPeQdV ggRRcN , RXU
eVSRUWV cOieQW bRRW VROXWiRQ. AOO PCV ZiOO bRRW Whe VaPe ZiQdRZV iPage aQd gaPe
OibUaU\, VaYiQg hXQdUedV Rf PaQ hRXUV aQd WhRXVaQdV iQ RSeUaWiRQ cRVWV.
Ɣ IQ RUdeU fRU eVSRUWV ceQWeU VWaNehROdeUV WR fRcXV RQ WheiU bXViQeVV PRdeO, ggCiUcXiW
RffeUV a PaiQWeQaQce SacNage fRU Whe iQVWaOOed ggRRcN VeUYeU. ggCiUcXiW¶V SSecOSV
WeaP ZiOO UePRWe acceVV Whe VeUYeU daiO\ WR XSdaWe Whe gaPeV aQd V\VWeP dUiYeUV
Qeeded WR RSeUaWe aW 100% effecWiYeQeVV.
Ɣ FRU PaQ\ bXViQeVV SURfeVViRQaOV, eVSRUWV RSeUaWiRQV & RWheU eVSRUWV WechQRORgieV aUe
fRUeigQ WR WheP. EVSRUWV iV VWiOO iQ Whe gUaVV-URRWV ShaVe - WheUefRUe, ggCiUcXiW haV
cUeaWed a POaWLQXP SXSSRUW SacNage WhaW giYeV ceQWeUV acceVV WR Whe SURfeVViRQaOV aQd
VXSSRUW VWaff Qeeded WR PaNe VXUe \RXU eVSRUWV ceQWeU iV RSeUaWiQg aW Pa[iPXP
efficieQc\.
Site Management Description QTY Cost Amount
ggLeapȽȽȽSiteȽȽȽLicenseȽȽȽȦȽȾȾ
ǚȽȽȽYearȽ LanȽȽȽCenterȽȽȽManagementȽȽȽSoftƿareȽ ǚȽ ɆǜȐǙǙǙȽ ɆǜȐǙǙǙȽ
InstallationȽ ȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦɣɣɣȽ ɆǛȐǙǞǛȽ
ggRockȽȽȽSiteȽȽȽLicenseȽȽȽȦȽȾȾ
ǚȽȽȽYearȽ LanȽȽȽCenterȽȽȽPXEȽȽȽServerȽȽȽSoftƿareȽ ǚȽ ɆǜȐǙǙǙȽ ɆǜȐǙǙǙȽ
InstallationȽ ȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦȦɣɣɣȽ ɆǛȐǙǞǛȽ
TrainingȽ TrainȽȽȽstaffȽȽȽonȽȽȽggLeapȽȽȽ̽ȽȽȽggRockȽ ǚȽ ɆǞȐǙǙǙȽ ɆǞȐǙǙǙȽ
PXEȽȽȽServerȽȽȽMaintenanceȽȾ
ǚȽȽȽYearȽ DailDžȽȽȽGameȐȽȽȽsoftƿareȐȽȽȽandȽȽȽdriverȽȽȽupdatesȽȾ 1 ɆǜȐǟǙǙȽ ɆǜȐǟǙǙȽ
PlatinumȽȽȽSiteȽȽȽSupportȽȽȽȦȽȾ
ǚȽȽȽYearȽ
remoteȽȽȽsupportȽȽȽofȽȽȽinstalledȽȽȽtechnologiesȽȾ
andȽȽȽsoftƿareȽ ǚȽ ɆǚǙȐǙǙǙȽ ɆǚǙȐǙǙǙȽ
Total: $28,704.00
Ɣ GaPeREADY! iV ZheUe ggCiUcXiW ZiOO SXUchaVe Whe gaPeV aQd cUeaWe WheiU UeVSecWiYe
accRXQWV RQ \RXU behaOf. AfWeUZhich, Ze add WheP WR Whe ggLeaS OiceQVe PaQagePeQW
V\VWeP VR WhaW Whe\ aUe Uead\ WR SOa\ ZheQ \RXU cXVWRPeUV aUe. AOO gaPeV aUe
SXUchaVed digiWaOO\. Each gaPe ZiOO haYe iWV RZQ XQiTXe ePaiO addUeVV aQd XQiTXe
SaVVZRUd.
PC & CRQVROe GaPe LiVW
DaDžȽȽȽǚȽȽȽGameȽȽȽLiƓƟȽ DeƓcƉiƆƟionȽ QTYȽ CoƓƟȽ AmoƧnƟȽ
CODȑMWȽ GameȽȽȽLiceŚƓeȽ ǜǟȽ ɆǟǙȽ ɆǛȐǚǟǙȽ
LefƟȽȽȽǝȽȽȽDeadȽȽȽǛȽ GameȽȽȽLiceŚƓeȽ ǚǛȽ ɆǚǙȽ ɆǚǛǙȽ
MiŚeCƉafƟȽ GameȽȽȽLiceŚƓeȽ ǜǟȽ ɆǜǙȽ ɆǚȐǙǡǙȽ
OƾeƉƿaƟchȽ GameȽȽȽLiceŚƓeȽ ǜǟȽ ɆǜǙȽ ɆǚȐǙǡǙȽ
PUBGȽ GameȽȽȽLiceŚƓeȽ ǚǡȽ ɆǜǙȽ ɆǞǝǙȽ
RaiŚbţƿȽȽȽSiDŽȽ GameȽȽȽLiceŚƓeȽ ǚǡȽ ɆǜǙȽ ɆǞǝǙȽ
RţckeƟȽȽȽLeagƧeȽ GameȽȽȽLiceŚƓeȽ ǜǟȽ ɆǛǙȽ ɆǠǛǙȽ
FallȽȽȽGƧDžƓȽ GameȽȽȽLiceŚƓeȽ ǚǡȽ ɆǛǙȽ ɆǜǟǙȽ
FţƉƟŚiƟeȽ GameȽȽȽLiceŚƓeȽ ǜǟȽ ɆǙȽ ɆǙȽ
AƆeDŽȽȽȽLegeŚdƓȽ GameȽȽȽLiceŚƓeȽ ǜǟȽ ɆǙȽ ɆǙȽ
ValţƉaŚƟȽ GameȽȽȽLiceŚƓeȽ ǜǟȽ ɆǙȽ ɆǙȽ
VaƉiţƧƓȽȽȽgameȽȽȽiŚƓƟallƓȽ IŚƓƟallȽȽȽǛǙȽȽȽţfȽȽȽƟheȽȽȽƟţƆȽȽȽFǛPȽȽȽaŚdȽȽȽPǛPȽȽȽPCȽȽȽGameƓȽ ǚȽ ɆǙȽ ɆǙȽ
XbţDŽȽȽȽGameȽȽȽPaƓƓȽȽȽȦȽȽȽǚȽȽȽYeaƉȽ AcceƓƓȽȽȽƟţȽȽȽhƧŚdƉedƓȽȽȽţfȽȽȽDŽbţDŽȽȽȽƟiƟleƓȽ ǛȽ ɆǚǠǢȏǡǡȽ ɆǜǞǢȏǠǟȽ
PlaDžƓƟaƟiţŚȽȽȽNţƿȽȽȽȦȽȽȽǚȽȾ
YeaƉȽ AcceƓƓȽȽȽƟţȽȽȽhƧŚdƉedƓȽȽȽţfȽȽȽPlaDžƓƟaƟiţŚȽȽȽƟiƟleƓȽ ǛȽ ɆǚǚǢȏǢǡȽ ɆǛǜǢȏǢǟȽ
GameREADYȔȽ PƧƉchaƓeȐȽȽȽcƉeaƟeȽȽȽaccţƧŚƟƓȐȽȽȽcƉeaƟeȽȽȽemailƓȽ ǜǛǜȽ ɆǜǟȽ ɆǚǚȐǟǛǡȽ
ToƟalȑȽ ɆǚǡȐǡǛǠȏǠǛȽ
IQ RUdeU WR PeeW cXVWRPeU e[SecWaWiRQV aQd SURSeUO\ VeUYe Whe cRQVROe eQYiURQPeQW, Whe
fROORZiQg iWePV ZiOO aOVR be Qeeded fRU XbR[ aQd POa\VWaWiRQ SOa\.
AddiƟionalȽȽȽMaƟeƉialƓȽ DeƓcƉiƆƟionȽ QTYȽ CoƓƟȽ AmoƧnƟȽ
BţaƉdȽȽȽGamingȽȽȽTableȽȾ
ChaiƉƓȽȽȽȦȽȽȽǟȝƆeƉȽ SAMEȽȽȽASȽȽȽLANȽȽȽGAMINGȽȽȽCHAIRSȽ ǚǛȽ ɆǜǞǢȽ ɆǝȐǜǙǡȽ
XbţDŽȽȽȽCţnƟƉţlleƉȽ
AddiƟiţnalȽȽȽXbţDŽȽȾ
CţnƟƉţlleƉƓȽ
hƟƟƆƓȑȝȝƟinDžƧƉlȏcţmȝȽ
DžǛmǞmjeƓȽ ǛȽ ɆǠǙȽ ɆǚǝǙȽ
PlaDžƓƟaƟiţnȽȽȽCţnƟƉţlleƉȽ
AddiƟiţnalȽȽȽPSǝȽȾ
CţnƟƉţlleƉƓȽ
hƟƟƆƓȑȝȝƟinDžƧƉlȏcţmȝȽ
DžǛhţhǛdǞȽ ǛȽ ɆǟǞȽ ɆǚǜǙȽ
XbţDŽȽȽȽCţnƟƉţlleƉȽȽȽChaƉgingȽȾ
SƟaƟiţnȽ
NYKOȽȽȽBaƟƟeƉDžȝChaƉgingȽȾ
SƟaƟiţnȽ
hƟƟƆƓȑȝȝƟinDžƧƉlȏcţmȝȽ
DžǟfgƓǡhmȽ ǛȽ ɆǜǙȽ ɆǟǙȽ
PSǝȽȽȽCţnƟƉţlleƉȽȽȽChaƉgingȽȾ
SƟaƟiţnȽ
NYKOȽȽȽBaƟƟeƉDžȝChaƉgingȽȾ
SƟaƟiţnȽ
hƟƟƆƓȑȝȝƟinDžƧƉlȏcţmȝȽ
DžǝƆƉƉƾjbȽ ǛȽ ɆǛǙȽ ɆǝǙȽ
CţnƓţleȽȽȽeDŽƟeƉnalȽȽȽHDDƓȽ
ǝTBȽȽȽEDŽƟeƉnalȽȽȽHaƉdȽȾ
DƉiƾeȽȽȽPSǝȝXbţDŽȽ
hƟƟƆƓȑȝȝƟinDžƧƉlȏcţmȝȽ
DžǟǝlleƟhȽ ǝȽ ɆǚǛǙȽ ɆǝǡǙȽ
ToƟalȑȽ ɆǞȐǚǞǠȏǡǡȽ
BiOO Rf MaWeUiaOV
AƧdĹţȽȽȽ͆ȽȽȽLANȽȽȽCĒŚƟĒƉȽȽȽPAȽ DĒƓcƉĹƆƟĹţŚȽ URLȽȽȽLĹŚŌȽ QTYȽ
JBLȽȽȽEON615Ƚ 15ȸȽȽȽTwoȦWayȽȽȽSpeakersȽ https://tinyurl.com/yyrewv6yȽ 2Ƚ
JBLȽȽȽEON610Ƚ 10ȸȽȽȽTwoȦWayȽȽȽSpeakersȽ https://tinyurl.com/yyrewv6yȽ 2Ƚ
JBLȽȽȽEON618SȽ 18ȸȽȽȽSubwooferȽ https://tinyurl.com/y4er5pu7Ƚ 2Ƚ
MackieȽȽȽProFX12v3Ƚ SoundȽȽȽMixerȽȽȽw/ȽȽȽFXȽ https://tinyurl.com/y5c8plqfȽ 1Ƚ
ShureȽȽȽULXȦDȽ WirelessȽȽȽhandheldȽȽȽMICȽȽȽKitȽ https://tinyurl.com/y4cng5vlȽ 1Ƚ
ShureȽȽȽSM58ȦLCȽ VocalȽȽȽMicrophoneȽ https://tinyurl.com/y6q3pmvvȽ 2Ƚ
MICȽȽȽCableȽ 6ȹȽ https://tinyurl.com/y3ettjxzȽ 2Ƚ
MICȽȽȽCableȽ 50ȹȽ https://tinyurl.com/y5jrpqy9Ƚ 2Ƚ
FƧƉŚĹƓĴĹŚĭƓȽȽȽ͆ȽȽȽGaŘĹŚĭȽ DĒƓcƉĹƆƟĹţŚȽ URLȽȽȽLĹŚŌȽ QTYȽ
BookShelvesȽ WayfairȽȽȽȦȽȽȽAngelicaȽȽȽGeoȽ https://tinyurl.com/y2djt2lqȽ 10Ƚ
EntertainmentȽȽȽCenterȽȽȽȦȽȽȽConsoleȽ WayfairȽȽȽȦȽȽȽAllegraȽ https://tinyurl.com/y3s5w79sȽ 4Ƚ
FoamȽȽȽFlooringȽȽȽTilesȽ 24x24ȽȽȽHighȽȽȽDensityȽȽȽFoamȽ https://tinyurl.com/y2ukx96dȽ 100Ƚ
BoardȽȽȽGamingȽȽȽTablesȽ UltimateȽȽȽGamingȽȽȽTableȽ https://tinyurl.com/yyk7u2wkȽ 2Ƚ
BGTȽȽȽPlayȽȽȽMattȽ TableȽȽȽDropȽȽȽinȽȽȽPlayingȽȽȽMatsȽ https://tinyurl.com/y57et2h6Ƚ 2Ƚ
LANȽȽȽGamingȽȽȽDesksȽ
48ȽȽȽxȽȽȽ30ȽȽȽadjustableȽȽȽheightȽȾ
͆ȽȽȽblackȽȽȽɝȽȽȽwoodȽȽȽtopȽ https://tinyurl.com/y35hdj9eȽ 36Ƚ
ElectricalȽȽȽOutletȽ
DualȽȽȽelectricalȽȽȽoutletȽȾ
15ftȽ https://tinyurl.com/yxm5h5bkȽ 36Ƚ
LANȽȽȽGamingȽȽȽChairsȽ SecretȽȽȽLabȽȽȽOmegaȽ https://tinyurl.com/y4ewghp4Ƚ 36Ƚ
LANȽȽȽSneezeȽȽȽBarrierȽ ClearȽȽȽAcrylicȽȽȽBarrierȽȽȽ48ȸȽ https://tinyurl.com/y484coyrȽ 36Ƚ
EntertainmentȽȽȽConsoleȽȽȽSofasȽ 2ȽȽȽpersonȽȽȽcouchȽ https://tinyurl.com/y5qno7n4Ƚ 4Ƚ
StoolȽ OperationsȽ https://tinyurl.com/yxedrvvsȽ 2Ƚ
GƉĹƆȽȽȽ͆ȽȽȽPƉţdƧcƟĹţŚȽ DĒƓcƉĹƆƟĹţŚȽ QTYȽ
CompleteȽȽȽCustomȽȽȽTrussȽȽȽSystemȽ
ApproxȽȽȽ20ȹx40ȹȽȽȽRiggingȽȽȽforȽȽȽMainȽȽȽStage,ȽȽȽApproxȽȽȽ70ȹx4ȹȽȾ
RiggingȽȽȽforȽȽȽcenterȽȽȽofȽȽȽGamingȽȽȽArea,ȽȽȽ74ȹȽȽȽStraightȽȾ
PerimeterȽȽȽWallȽȽȽRun,74ȹWallȽȽȽRunȽȽȽwithȽȽȽ2ȽȽȽJutȽȽȽOutsȽ
1Ƚ
**ȽȽȽValueȽȽȽengineeredȽȽȽtoȽȽȽfitȽȽȽintoȽȽȽnewȽȽȽbudgetȽȾ
Ⱦ
Ⱦ
Ⱦ
Ⱦ
GƉĹƆȽȽȽ͆ȽȽȽCaŘeƉaȽ DeƓcƉĹƆƟĹţŚȽ URLȽȽȽLĹŚŌȽ QTYȽ
TripodȽȽȽ̽ȽȽȽFluidȽȽȽHeadȽȾ PTZȽȽȽ̽ȽȽȽCAMSȽȾ https:ȝȝtinyurl.comȝy2596n2yȽ 2Ƚ
LĹgĴƟĹŚgȽ DeƓcƉĹƆƟĹţŚȽ QTYȽ
LightingȽȽȽFixtures:ȽȽȽcolorȽȽȽchangingȽȽȽPARsȽȽȽȦȽȽȽStageȽȽȽFrontȽȽȽLightingȽȽȽȦȽȽȽParsȽȾ 16Ƚ
LightingȽȽȽFixtures:ȽȽȽLEDȽȽȽTubeȽȾ
LightingȽȾ
ElationȽȽȽPixelbarsȽȽȽȦȽȽȽQTYȽȽȽReducedȽȽȽtoȽȽȽeliminateȽȽȽoverȽȾ
engineeringȝbestȽȽȽenvironmentalȽȽȽresultsȽȾ 30Ƚ
LightingȽȽȽFixtures:ȽȽȽParȽȽȽCanȽȾ AmericanȽȽȽDJȽȽȽStingerȽȽȽSpotsȽȾ Ⱦ 2Ƚ
LightingȽȽȽFixtures:ȽȽȽHexȽȽȽParsȽȾ
AmericanȽȽȽDJȽȽȽHexȽȽȽParȽȾ
FixturesȽȾ Ⱦ 30Ƚ
SoftwareȽȽȽDMXȽȽȽcontrollerȽȾ Ⱦ Ⱦ 1Ƚ
ȚȚȽȽȽQTYȽȽȽreducedȽȽȽandȽȽȽvalueȽȽȽengineeredȽȽȽtoȽȽȽavoidȽȽȽoverȽȽȽengineeringȽȽȽandȽȽȽnewȽȽȽbudgetȽȾ
ITȽȽȽ͆ȽȽȽPCȽȽȽ̽ȽȽȽCţŚƓţŏeƓȽ DeƓcƉĹƆƟĹţŚȽ URLȽȽȽLĹŚŌȽ QTYȽ
GaPiQg PC i5Ȧ9600KȽȽȽ͆ȽȽȽ16GȽȽȽRAMȽȽȽ͆ȽȽȽ2070ȽȽȽSuperȽȽȽ͆ȽȾ 36Ƚ
PCȽȽȽMonitorsȽ
BenQȽȽȽZOWIEȽȽȽ144hzȽȽȽ͆ȽȽȽ1080pȽȽȽ͆ȽȾ
1msȽȾ https:ȝȝtinyurl.comȝyyky5kyxȽ 36Ƚ
PCȽȽȽKeyboardȽ RedragonȽȽȽK552ȽȾ https:ȝȝtinyurl.comȝyyps2l2yȽ 36Ƚ
PCȽȽȽMouseȽ RedragonȽȽȽM711ȽȾ https:ȝȝtinyurl.comȝy32mthngȽ 36Ƚ
PCȽȽȽHeadsetȽ RedragonȽȽȽH510ȽȽȽ7.1ȽȽȽHeadsetȽȾ https:ȝȝtinyurl.comȝyx92y9rwȽ 36Ƚ
PCȽȽȽMouseȽȽȽPadȽ RedragonȽȽȽP015ȽȾ https:ȝȝtinyurl.comȝy5azrypqȽ 36Ƚ
PXEȽȽȽServerȽȾ
DisklessȽȽȽPCȽȽȽBootȝGameȽȾ
ServerȽȾ
CustomȽȽȽBuildȽȽȽ͆ȽȽȽ8TBȽȽȽGameȽȾ
StorageȽ 1Ƚ
PlaystationȽȾ PS4ȽȽȽProȽȽȽ1TBȽȾ https:ȝȝtinyurl.comȝy5z7tdx8Ƚ 2Ƚ
XboxȽȾ XboxȽȽȽOneȽȽȽXȽȽȽ1TBȽȾ https:ȝȝtinyurl.comȝy5tzf5mzȽ 2Ƚ
ConsoleȽȽȽGamingȽȽȽHeadsetȽȾ
AstroȽȽȽA20ȽȽȽWirelessȽȽȽGamingȽȾ
HeadsetȽȾ https:ȝȝtinyurl.comȝy655dxe5Ƚ 8Ƚ
ButtonȽȽȽPanelȽ ElgatoȽȽȽStreamȽȽȽDeckȽ https:ȝȝtinyurl.comȝy55ocbovȽ 1Ƚ
ȚȚȽȽȽReducedȽȽȽPCȽȽȽspecsȽȽȽtoȽȽȽfitȽȽȽnewȽȽȽbudget.ȽȽȽChangedȽȽȽperipheralȽȽȽforȽȽȽbetterȽȽȽoverallȽȽȽvalueȽȾ
ITȽȽȽ͆ȽȽȽNeƟƿţƉŌĹŚgȽ DeƓcƉĹƆƟĹţŚȽ URLȽȽȽLĹŚŌȽ QTYȽ
MikrotikȽȽȽRouterȽȾ CCR1009Ȧ7GȦ1CȦ1SɝȽ https:ȝȝtinyurl.comȝy3dp99wlȽ 1Ƚ
MikrotikȽȽȽsfpɝȽȽȽswitchȽȾ
CRS317Ȧ1GȦ16SɝRMȽȽȽ͆ȽȽȽ16xȽȽȽsfpɝȽȾ
portsȽ https:ȝȝtinyurl.comȝy6p7sl9gȽ 1Ƚ
NetgearȽȽȽSwitchȽȾ
MS510TXPPȽȽȽ͆ȽȽȽ8ȽȽȽport,ȽȽȽsfpɝ,ȽȾ
PoEȽ https:ȝȝtinyurl.comȝy2akqh6vȽ 6Ƚ
OS2ȽȽȽFiberȽȾ VariousȽȽȽLengthsȽ https:ȝȝtinyurl.comȝy3wzxxbgȽ 1Ƚ
CAT6ȽȾ VariousȽȽȽLengthsȽ https:ȝȝtinyurl.comȝy2wnlewkȽ 1Ƚ
FiberȽȽȽsfpɝȽȽȽTransceiverȽȾ 10GtekȽ https:ȝȝtinyurl.comȝy3bdjnwbȽ 20Ƚ
Wireless AP Meraki https://tinyurl.com/y3pdc2ur 1
** Swapped suggested router/switch for better value
LVIȽȽȽȠLoƿȽȽȽVolƟageȽȽȽInsƟallersȡȽ DescripƟionȽ URLȽȽȽLinkȽ QTYȽ
Network Rack
XRACK Pro2 12U ͆
XRP2-12U-ST-US-BLK https://tinyurl.com/y3sf3yvv 1
Fiber Patch Panel Bittree ͆ DSKP124B-LC https://tinyurl.com/y2zg9sbs 1
Rack Shelf
Middle Atlantic Shelf ͆
MAP-UMS1-11.5 https://tinyurl.com/y3etfk3s 1
UPS rackmount Cyberpower UPS 1500VA/900W https://tinyurl.com/y3dp99wl 1
NDIȽ DescripƟionȽ URLȽȽȽLinkȽ QTYȽ
Birddog Mini NDI Encoder/Decoder https://tinyurl.com/y6exs36n 6
VideoȽȽȽ͆ȽȽȽCAMȽ DescripƟionȽ URLȽȽȽLinkȽ QTYȽ
PTZ Camera PT12X-NDI https://tinyurl.com/y274my84 2
VideoȽȽȽ͆ȽȽȽProdƧcƟionȽ DescripƟionȽ URLȽȽȽLinkȽ QTYȽ
Console Gaming TVs TCL 65" LED TV https://tinyurl.com/yynw7ft5 4
Truss Mounted TVs TCL 75" LED TV https://tinyurl.com/y3wfwzhr 4
** Better value TVs added to fit budget constraints
FƧrnishingsȽȽȽ͆ȽȽȽSƟagingȽȽȽȦȽȽȽCƧsƟomȽȾ
BƧildsȽ DescripƟionȽ URLȽȽȽLinkȽ QTYȽ
Light Box Banners: 36" x 72" H LED Lit Banner Box w/ Hanging Hardware and Printed
Graphic 12
Console Gaming Dividers Custom Built Side Walls w/divider T Wall 2
BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM
Date 09/08/2020
Name Becca Plantz Department Public Works
BPW Date 09/08/2020 Phone Extension 5998
Review and Approval Required Prior to Submittal to Board Diversity Compliance
and Inclusion Officer Officer Name BPW Attorney Attorney Name Clara McDaniels
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution Other: Ease./Encroach
Required Information
Company or Vendor Name
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE WBE Completed E-Verify Form Attached Yes No Project Name Century Center Esports Arena
Project Number 119-106CR
Funding Source Hotel Motel Tax Fund
Account No. 7304.42010.000.0099
Amount
Terms of Contract Lump Sums
Purpose/Description Construction and installation of equipment to make improvements to the
Century Center for eSports Gaming Center and Broadcast Studio.
For Change Orders Only
Amount of Increase Decrease
$
($ ) Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount: New Completion Date:
GARY A. GILOT ELIZABETH A. MARADIK THERESE J. DORAU JORDAN V. GATHERS JOSEPH R. MOLNAR
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
September 8, 2020
Ms. Jennifer Martell
Martell Electric, LLC
4601 Cleveland Rd.
South Bend, IN 46628
areeves@martellelectric.com
RE: Bid Award – Century Center Esports Arena – Project No. 119-106CR
Dear Ms. Martell:
The Board of Public Works, at its meeting held on September 8, 2020, awarded the above
referenced project to ggCircuit LLC, in the amount of $378,882.59.
Thank you for bidding, and we hope you bid with us in the future.
If you have any further questions regarding this matter, please call this office at (574)
235-9251.
Sincerely,
s/Linda M. Martin, Clerk
Enclosure
GARY A. GILOT ELIZABETH A. MARADIK THERESE J. DORAU JORDAN V. GATHERS JOSEPH R. MOLNAR
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
September 8, 2020
Mr. Martin Golob
TPC Technologies, Inc.
185 Bell Rd.
Niles, MI 49120
mgolob@tpctechnologies.com
RE: Bid Award – Century Center Esports Arena – Project No. 119-106CR
Dear Mr. Golob:
The Board of Public Works, at its meeting held on September 8, 2020, awarded the above
referenced project to ggCircuit LLC, in the amount of $378,882.59.
Thank you for bidding, and we hope you bid with us in the future.
If you have any further questions regarding this matter, please call this office at (574)
235-9251.
Sincerely,
s/Linda M. Martin, Clerk
Enclosure
GARY A. GILOT ELIZABETH A. MARADIK THERESE J. DORAU JORDAN V. GATHERS JOSEPH R. MOLNAR
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
September 8, 2020
Mr. Philip Nelson
Nelco Media, Inc.
505 Howard St.
San Antonia, TX 78212
Philip@NelcoMedia.net
RE: Bid Award – Century Center Esports Arena – Project No. 119-106CR
Dear Mr. Nelson:
The Board of Public Works, at its meeting held on September 8, 2020, awarded the above
referenced project to ggCircuit LLC, in the amount of $378,882.59.
Thank you for bidding, and we hope you bid with us in the future.
If you have any further questions regarding this matter, please call this office at (574)
235-9251.
Sincerely,
s/Linda M. Martin, Clerk
Enclosure