JANUARY 12, 2021
CITY OF SOUTH BEND:
COAL LINE TRAIL (PHASE I) FROM
LINCOLN WAY WEST TO RIVERSIDE DR.
CLIENT FOCUSED. • TRUST. • WORK HARD. TOGETHER. • KNOWLEDGE.
MARK HERALD, PE
Northern Region Director
Project Manager
mherald@vsengineering.com
C: 260.348.1768
VS Engineering: 95%
McCormick Engineering (DBE): 5%
10305-A Dawson’s Creek Blvd. • Fort Wayne, IN 46825
260.489.6635
www.vsengineering.com
January 12, 2021
Mr. Kyle Silveus, Assistant City Engineer
227 W. Jefferson Blvd. 1316 County-City Building
South Bend, IN 46601
Re: City of South Bend Coal Line Trail (Phase I) from Lincoln Way West to Riverside Dr. (Des. 1401810) in LaPorte District
Dear Mr. Silveus:
VS ENGINEERING (VS) is pleased to submit our Letter of Interest for construction inspection services for your Coal
Line Trail (Phase I) project. Our VS Team understands that this project will not only provide pedestrian connectivity
in the area, but will implement an aesthetic enhancement to the corridor. Our team clearly recognizes that this project is
not simply a pedestrian improvement, but also creates an asset for future economic development and aids in beautification
efforts. When completed, it will be a tremendous asset for years to come, and will continue to shine a spotlight on the City
as being a great place to live, work and play.
Our team will be led by Mark Herald, PE, who has over 17 years of experience in transportation engineering on both locally
and federally funded projects, including for the City of South Bend, La Porte County, the City of Warsaw, the City of Fort
Wayne, and other communities in Northern Indiana. Mark is a proven leader, and will be a strong partner for you from start
to finish. Mark and the rest of our VS Engineering construction inspection team are interested in exploring opportunities to
provide savings to the City’s taxpayers much needed funds, particularly in a time when local funds will likely diminish
due to the current health pandemic.
As with most infrastructure projects, local residents typically have concerns about how projects will affect their daily lives.
At VS, we understand the City of South Bend’s strong interest in keeping the public informed of ongoing construction
projects as you detail many of your projects on the City’s website in your ongoing efforts towards increased transparency.
We know that our work reflects on you and understand your need for a superior and worry-free project. We pledge
to be excellent representatives for the City in communicating with the hundreds of affected citizens who live in this highly
residential and commercial area.
Our assigned Project Supervisor, Bill Kreger, is based out of our La Porte office, along with Project Inspector Fidel Chavez.
Bill has been assigned full-time/on-site and brings with him over 10 years of experience in the areas of civil engineering,
construction management and QC inspection. He has supervised roadway projects that match the same critical construction
elements as the Coal Line Trail project, including the recent highly-lauded Maplecrest Road project, during which this VS
team attended neighborhood public meetings to discuss the project’s impact on the residents’ daily lives. We listened to
their concerns, and developed a working relationship with those individuals we would normally see on the job site. Having
a Project Supervisor who is willing to listen and inform the residents is imperative to comforting the minds of the public.
Thank you for your thoughtful consideration of our locally-based VS Engineering team. We bring to you decades of experience,
a strong understanding of the importance and impact of the finished project, and a passion for continuing to make the City
of South Bend shine. We are capable. We understand. We are ready!
Respectfully Submitted,
SANJAY PATEL, PE
President/CEO
Principal-in-Charge
sbpatel@vsengineering.com
C: 317.626.0070
Our experienced team ensures critical construction
supervision and inspection tasks are at the forefront,
beginning with positive and effective communication
with the INDOT Area Engineer. Our construction
administration and inspection tasks are
numerous and broad.
• Pre-construction Conference
• SiteManager and Project Documentation
• Field Inspection and Contract Oversight
• Extensive Project Te sting Implementation
• Positive Communication (internal & external)
• Bi-weekly Progress Meetings (issuance of minutes)
• Pro-active Maintenance of Tr affic
• Daily Erosion Control Inspections
• Weekly/Monthly Project Status Updates
• Change Order / Budget Management
• Schedule Management
• Timely and Accurate Final Construction Records
We have selected this team carefully to provide
the most efficient team possible for the City of
South Bend. The two leaders on this project,
Mark and Bill, are both long-term northern
Indiana residents and are therefore readily
available for all project tasks. Both have
worked in and around South Bend. Bill will be finishing up another local project and will be able to transition into this project with ease. He is
experienced working with City officials,
familiar with the process of public
communication, and knowledgeable regarding
what is expected when representing South
Bend.
Our construction services team, led by Mark Herald, PE, has the depth and bredth to provide the necessary services — including project management, project supervision and construction inspection — to lead this project and provide support for the City of South Bend. Inspection for the project will be lead by Bill Kreger, who has been TRUSTED for over 10 years to successfully deliver construction projects. Bill’s experience while working at INDOT allows him to assist in training and mentoring VS project supervisors and inspectors across our company, and ensures that our staff are technically sound and well organized to provide high-quality construction supervision and inspection. The result of this training is a robust VS construction inspection team with decades of experience on federally and locally funded projects.
THE VS TEAM LOCAL CAPACIT Y YOU SEEK EXPERIENCE YOU SEEK
VS ENGINEERING, INC. | LETTER OF INTEREST • 2
CITY OF SOUTH BEND
KYLE SILVEUS, PE — ASSISTANT CITY ENGINEER
PROJECT MANAGER &
NORTHERN REGION DIRECTORMark Herald, PE
PRINCIPAL-IN-CHARGE
Sanjay Patel, PE
PROJECT SUPERVISOR
*Bill Kreger
*VS Engineering La Porte Office
1 McCormick Engineering, LLC (DBE)
UTILITIES SPECIALIST
Joe Dluzak
CONSTRUCTION INSPECTORS
Andrew Matney, EI
*Fidel Chavez
Andy Holman
1 John Beer
QA/QC
Jerry Crothers
YOUR PROJECT TEAM
SOUTH BEND • COAL LINE TRAIL (PHASE I)
VS ENGINEERING, INC. | LETTER OF INTEREST • 3
BILL KREGER | PROJECT SUPERVISOR
9 YEARS OF EXPERIENCE
EDUCATION
BROWN MACKIE COLLEGE
CERTIFICATIONS
INDOT Field Proficiency
(All Categories)
INDOT Site Manager
Software
INDOT Certified Technician
Bill joined the VS team full time after working for 8 years for the Indiana Department of
Transportation (INDOT). He has supervised construction inspection on several projects
relating to roadway construction including asphalt resurfacing, asphalt patching, traffic signal
rehabilitations, and bridge deck overlays. Bill is an INDOT Certified Technician and is fully Field
Proficient. He has also passed the INDOT SiteManager certification training.
PROJECT SUPERVISOR EXPERIENCE
Asphalt Resurface (INDOT)—LaPorte District: Contract R-37738 ($4,200,000 Construction
Cost)
Signal Rehabilitation (INDOT)—Fort Wayne District: Contract T-36023 ($180,000
Construction Cost)
Asphalt Resurface (INDOT)—Fort Wayne District: Contract RS-34904 ($305,000
Construction Cost)
Asphalt Resurface (INDOT)—Fort Wayne District: Contract RS-38695—3 Des Numbers
($3,900,000 Construction Cost)
Asphalt Resurface (INDOT)—Fort Wayne District: Contract RS-39653 ($900,000
Construction Cost)
Asphalt Resurface (INDOT)— Fort Wayne District: Contract RS-39652 ($2,000,000
Construction Amount)
Asphalt Resurface (INDOT)—Fort Wayne District: Contract RS-40829 ($1,800,000
Construction Cost)
Asphalt Patching (INDOT)—Fort Wayne District: Contract RS-41337—5 Des Numbers
($1,900,000 Construction Cost)
MARK HERALD, PE | PROJECT MANAGER
17 YEARS OF EXPERIENCE
EDUCATION
B.S., CIVIL ENGINEERING
INDIANA INSTITUTE OF
TECHNOLOGY
REGISTRATIONS
PE — IN
CERTIFICATIONS
INDOT Utility Coordinator
INDOT Certified Technician
ACEC Leadership Training
Graduate
Mark serves as Project Manager for the firm’s transportation projects. Managing an inspection
project requires a different technique than typical projects, and Mark excels in these areas. He
understands that various project types may require shifting staff efforts towards the project
at hand, which is paramount to its success. Mark’s multitasking skills “kick in” when leading
project teams, and he knows how to think with innovation to find the most cost-effective
engineering solution for any given scope and budget. Communication—even within this VS Team—
must stand out, beginning at the top. Mark is expert at driving timely project input from partners
and subconsultants, acting on small issues before they become big problems.
CONSTRUCTION PROJECT MANAGEMENT EXPERIENCE
Auburn Road Reconstruction – City of Fort Wayne
Covington Road Trail – City of Fort Wayne
Lake Ave. Roadway Diet – City of Fort Wayne
Argonne Road/Parker Street Corridor – City of Warsaw
Market Street Roadway Design – City of Warsaw
Traffic Signal Preemption – City of Angola
Traffic Signal Preemption – City of Marion
Safe Routes to School – City of Butler
Brian’s Place Extension – City of Kendallville
Fort Wayne Utilities – On-Call Inspection
INDOT Fort Wayne District – On-Call Construction Inspection
I-69 Preventative Maintenance HMA Overlay
US 224 Reconstruction in Decatur
PROJE CT MANAGEMENT
SOUTH BEND • COAL LINE TRAIL (PHASE I)
VS ENGINEERING, INC. | LETTER OF INTEREST • 4
ANDREW MATNEY, EI | PROJECT INSPECTOR
4 YEARS OF EXPERIENCE
EDUCATION
B.S., CIVIL ENGINEERING
PURDUE UNIVERSITY FORT
WAYNE (IPFW)
REGISTRATIONS
EI — IN
CERTIFICATIONS
INDOT Field Proficiency
(All Categories)
INDOT Site Manager
Software
Proficient in PMIS
INDOT Certified Technician
Andrew is a Project Inspector with field experience in construction inspection on several projects, in addition to field experience in data collection for asset management plans. He also has significant experience working within GIS databases, specifically with ARCGIS.
Andrew is thoroughly experienced in the supervision of construction work, compliance review with contract documents, preparation of construction related reports and records, testing of materials, and serving as a liaison between the client and contractors. He has on-site experience to include reading and interpretation of contract documents, quality control, material on-site delivery approval and material testing.
NOTABLE EXPERIENCE
MIC Trail Construction Inspection – Muncie, IN
Northwest Trail Construction Inspection – Goshen, IN
Maplecrest Road Widening Construction Inspection – Fort Wayne, IN
Citizen’s Square Parking Lot Reconstruction – Fort Wayne, IN
Fort Wayne Children’s Zoo Force Main – Fort Wayne, IN
Greyhawk Subdivision Water Main – Fort Wayne, IN
Northwest Drive Septic Elimination – Fort Wayne, IN
2016 General Manhole Rehabilitation – Fort Wayne, IN
AEP Service Center Sanitary – Fort Wayne, IN
Brantford Court Culvert Replacement – Fort Wayne, IN
Creighton-Home Sewer Separation – Fort Wayne, IN
JOHN BEER | PROJECT INSPECTOR — MCCORMICK ENGINEERING
25 YEARS OF EXPERIENCE
CERTIFICATIONS
INDOT Site Manager
Software
INDOT Certified Technician
John is an experienced technician with over 25 years in the construction industry. Observation experience includes performance of material testing, monitoring daily construction activities and preparing Daily Work Reports for roadway reconstruction, bridge deck replacement and telecommunication fiber installation projects.
NOTABLE EXPERIENCE
INDOT On-Call, SR 331 over US 30 Bridge Deck Overlay - Marshall County
Indiana Toll Road Concessions, ITS Phase II, Elkhart, LaGrange - Steuben & Porter Counties
Bridge Rehabilitation Projects - DeKalb, Fulton, Huntington, Marshall, Kosciusko, LaGrange
and Tipton Counties
Kercher Road Phase 2 Reconstruction, Goshen, Indiana
Handley Elementary Safe Routes to School, LaPorte, Indiana
PROJE CT INSPECTORS
SOUTH BEND • COAL LINE TRAIL (PHASE I)
VS ENGINEERING, INC. | LETTER OF INTEREST • 5
JOE DLUZAK | UTILITIES SPECIALIST
Joe has over 41 years of professional experience and serves as Project Manager for the firm’s transportation projects. His experience includes design of transportation and civil site projects—including INDOT and locally funded, pavement rehabilitation and widening with curbs, gutters and sidewalks, storm sewers with storm water drainage, and trails.
Joe also has a vast amount of experience in many subdivision and commercial development projects. His design experience is complimented by his strong organization and communication skills. Joe is an INDOT Certified Utility Coordinator and he is proficient in AutoCAD and Civil3D.
NOTABLE EXPERIENCE
City of South Bend - Dubail Avenue: This 0.75-mile project provided improvements to the roadway, pedestrian facilities, and on street parking. The design allows for motorists to safely park their vehicles on street and for the traveling public to traverse Dubail Ave. New ADA-compliant sidewalks and residential/commercial driveway improvements were also included. This roadway rehabilitation design included detail-oriented design to coordinate existing utilities, street lighting, and traffic operations. Within this corridor are two elementary school buildings, in which design of the school bus and parent drop off locations were included. As lead design engineer, Joe was responsible for all design-related activities such as setting alignments and all geometrics. Joe spearheaded the lines of communication with the client, stakeholders, and all associated parties involved with the project.
City of Fort Wayne - Hobson Road
City of Fort Wayne - Pufferbelly Trail
41 YEARS OF EXPERIENCE
EDUCATION
B.S., ARCHITECTURAL
ENGINEERING
ITT TECHNICAL INSTITUTE
CERTIFICATIONS
INDOT Certified Utility
Coordinator
JERRY CROTHERS | QA/QC
36 YEARS OF EXPERIENCE
CERTIFICATIONS
INDOT SiteManager
Software
INDOT Certified Technician
INDOT FIELD PROFICIENT
Proficient in Project
Management Information
System (PMIS)
Jerry serves as Quality Assurance for the firm. He has over 36 years of on-site construction
inspection experience of both new construction and rehabilitation construction projects
throughout northeastern Indiana. Jerry was a long-time employee with INDOT’s Fort Wayne District,
where he managed projects from simple pavement resurfacing to complex interstate highway
construction. He has complete knowledge of INDOT project reporting procedures along with the
associated paper work and final records to close out a project. Jerry has specifically supervised
LPA Construction Inspection over the past 10 years. These Construction Inspection contracts
have required coordination of several inspectors and contractors, at many different simultaneous
locations. His skills in supervision of transportation projects allow him to service each client’s
needs, all the while balancing staff assignments, reports and other project related matters. Jerry
was the Project Supervisor for the City of Fort Wayne’s Maplecrest Road Widening and Dupont
Road Widening, which have become the City’s standard for urban roadway construction.
LOCAL EXPERIENCE
Dupont Road Widening from Lima Rd. to Coldwater Rd. — City of Fort Wayne
Maplecrest Road Widening from Lake Ave. to State Blvd. — City of Fort Wayne
Auburn Rd. Widening Over I-69 — City of Fort Wayne
Covington Rd. Trail from W. Hamilton Road to Braemar Dr. & Scott Road to Braemar Dr. —
City of Fort Wayne
Wayne Trace Roadway Reconstruction and Storm Sewer — City of Fort Wayne
SR 3 from Carroll Road to just north of Town of Huntertown
SR 101 from US 224 to SR 124 – Adams County, IN
I-69 from Dupont Road/SR 1 to the Cedar Creek bridge – DeKalb County/Allen County
US 224 Reconstruction – Decatur
PROJE CT INSPECTORS
SOUTH BEND • COAL LINE TRAIL (PHASE I)
The main purpose for this project is to provide pedestrian access and improve pedestrian safety. The Coal Line Trail project will provide
a paved multi-use trail link between West Lincoln Way and Riverside Drive on the northwest side of downtown South Bend. This
project will allow pedestrians to safely travel the 0.8-mile-long corridor through a mixture of residential and commercial areas while
experiencing minimal vehicular traffic.
The majority of the railroad corridor within the project limits is relatively clear, although some of the rails are still present. Upon our on-
site field visit, we noticed the railroad bed ballast stone is still largely in place, which provides an ideal subbase for a recreational trail
construction. The vehicular bridge on Portage Avenue over the railroad bed was recently reconstructed and provisions were included
to allow the trail to be constructed under the roadway through a precast concrete tunnel. Along the railroad corridor, there are five at
grade crossings with residential streets and a commercial property near Riverside Drive.
The City of South Bend has taken great strides
in developing the “walkability” of the City by
improving sidewalks, curb ramps, adding multi-
use trails, and upgrading crosswalks. These
pedestrian friendly improvements are evident
when visiting downtown South Bend, and
observing the trails, sidewalks, curb ramps, and
street lighting in locations along the Saint Joseph
River. This particular section of the Coal Line
Trail is the first phase of the project. The next
phase will continue the trail to the east across
Riverside Drive and across the Saint Joseph River
along the existing, abandoned rail bridge over
the river. Once completed, this trail will provide
safe pedestrian connectivity to South Bend’s
Muessel Grove Park, Brownfield Park, and Holy
Cross School.
Construction activities will include constructing the recreational trail, at grade crossings, as well as trail ancillary items such as
rest nodes with benches, and possibly vehicular parking areas. This team has direct, recent experience with this same type of
construction inspection project. Constructing the trail under live traffic conditions will require special attention to ensure the safety
of the vehicular traffic. As this team did on the Dupont Road project and the Maplecrest Road phases in Fort Wayne, we are prepared
to work with the City of South Bend’s Engineering staff to ensure any relocations or alterations of their facilities are carried out to the
City’s expectations, and accurately documented in the City’s record system with detailed daily reporting. Bill Kreger, Fidel Chavez,
and John Beer are all trained in utilities inspection as well as roadway inspection, and will be prepared to provide the highest level of
documentation on all City utility relocation inspection.
VS ENGINEERING, INC. | LETTER OF INTEREST • 6
It is our promise to
monitor contract
quantities, manage and
negotiate all change
orders fairly, and
maximize the work that
is completed for each
dollar you spend.
Communication between
the VS Project Team,
the contractor, City
officials and the public
will be key in adhering to
the project schedule.
The VS Team will remain
proactive in preventing
delays to construction by
ensuring smooth and
efficient coordination
bewteen the contractor
and utilities.
A Project Supervisor
who is willing to listen to
and inform local
residents of project
progress is essential in
appeasing the minds of
the public.
The VS Team’s decades of
traffic control experience
will help to implement
traffic schemes in order
to provide safety for
motorists traveling
through and living in
South Bend.
PROJE CT APPROACH
SOUTH BEND • COAL LINE TRAIL (PHASE I)
PROJECT UNDERSTANDING
VS ENGINEERING, INC. | LETTER OF INTEREST • 7
VS OFFERS A TRUE 3RD PA RT Y APPROACH CHECKLISTProject Super visor reviews construction documents for constructability, value engineering and schedule prior to kick-off meeting with the City and INDOT District Staf f.
Daily reports generated by all inspectors and reviewed by project super visor include actual quantities installed, quality of workmanship and other pertinent field information.
Daily inspection of all work to assure conformance with plans and INDOT specifications, including materials conforming to approved material list(s).
Te sting of materials including concrete, asphalt and subgrade and reporting and documenting materials received including verification of INDOT approved sources and acceptance.
Project Supervisor generated repor ts into daily, weekly and monthly repor ts, reviewed prior to submission.
Accurate construction reporting including daily, weekly and monthly reports, and regular interaction with contractor for clarification/interpretation of requirements.
Assurance of proper installation, monitoring and maintenance of Rule 5 erosion control measures.
Tr acking progress of work on a unit price basis for accurate and accountable contractor pay vouchers.
Progress meetings as well as strong support of all teaming effor ts to complete projects according to all contract documents, on-time and within budget.
Assurance of proper and safe maintenance of traf fic measures during on-going construction to protect all workers, as well as citizens and the motoring public.
Quality Control/Quality Assurance (QA/QC) where applicable, and final project accounting and project close-out ahead of schedule.
Maintaining files of all work item invoices, weigh tickets & material certifications, and Change Orders when required, including verification, review and recommendation.
Regular interaction with contractor for clarification/interpretation of requirements, and availability to citizens to answer questions and concerns, where required.
PROJE CT APPROACH
SOUTH BEND • COAL LINE TRAIL (PHASE I)
Project Manager Mark Herald, PE, and Project Supervisor Bill Kreger possess the experience and the availability to assist the City, if the
need arises, with constructability reviews and claim resolution. Their experience with value engineering will allow the City to effectively
manage cost overruns by finding ways to allocate the work to meet the budget and the initial scope. Mark and Bill have worked together
on inspection projects for the past 3 years. This teamwork has allowed them to establish a proven system that provides a quality service
to all of their clients.
We will be the City’s partner on this project – including
necessary commitment to the safety of the motoring public
and residents alike during construction.
We will provide a local construction inspection team who
are familiar with the project area and are fully capable of
working with the City of South Bend and INDOT.
We will identify project hurdles prior to preconstruction
meetings and submit memorandum detailing all findings to
City staff in an effort to minimize owner risk. No hiccups
during construction!
We will be the eyes and ears of the project, ensuring the
City receives a quality-constructed project that will stand
the test of time.
VS PROJECT TEAM BRINGS ADDED VALUE
This area sees significant daily traffic and is located within a unique mixture of dense residential and commercial properties. All residential
and business owners must have ample access to their homes and business locations maintained through all phases of construction.
During demolition of the existing drives and prior to reconstruction, compacted stone temporary access drives will be vital for each
impacted property. Some businesses have an alternate access either to the rear or side of the property. In the event of freshly poured
concrete, the temporary use of these alternate access points will be necessary. Deliveries for these businesses must be maintained
throughout the construction process as well.
During the construction of similar projects such as Maplecrest Road – Lake Avenue to State Boulevard, and Dupont Road, this VS team
attended neighborhood public meetings to discuss the project’s impact on the resident’s daily lives. We listened to their concerns,
and developed a working relationship with those individuals we would normally see on the job site. Having a Project Supervisor who is
willing to listen and inform the residents is imperative to appeasing the minds of the public. Bill will provide weekly progress reports to
all necessary parties. These weekly reports are emailed to all recipients and include a detailed summary of the daily activities on the
project, as well as what to expect in the short term future.
Integrated into our public outreach plan is constant coordination with Law Enforcement, Fire, EMS and the School Corporation. We
recognize the impacts a construction project has on your public safety departments so we make it a priority to consistently communicate
with each entity regarding closures, detours, etc.
PUBLIC OUTREACH
VS ENGINEERING, INC. | LETTER OF INTEREST • 8
SAFETY IS PRIORITY #1
VS is 100% committed to workplace and traffic safety. Not only has our staff completed OSHA 10-hour Safety Training—
we are supplied with appropriate personal protective equipment and fully committed to the following goals:
Work zone safety is everyone’s responsibility
Cooperation with contractor, City and INDOT to identify the most appropriate means of communication and
physical protection for safe travel and work
Lane/Road Restriction Form updates when traffic patterns change
Updating INDOT CARS system to ensure INDOT and public have accurate information; phone calls to the TMC to
update INDOT personnel
Coordination with City staff to ensure they are able to inform the public
PROJE CT APPROACH
SOUTH BEND • COAL LINE TRAIL (PHASE I)
Making the most of your money isn’t just for the frugal grocery getter. The ability to get more for your money means that more projects
get funded, more roads and bridges get built and maintained, and the more you can provide to the community. We recognize this at
VS and we are committed to monitoring our inspection budgets in the same manner you monitor your budgets. Our fees are based on
conversations with City staff, and review of the plans, and include only the hours that are necessary to provide you with the high-quality
support you expect that will, in turn, provide a high-quality project.
PROTECTING BUDGETS
Our project staff understands that we are being trusted to act on your behalf, and spend your money efficiently as possible. It is our
promise to monitor contract quantities, manage and negotiate all change orders fairly, and also maximize the work that is completed
for each dollar you spend. No one wants to spend unnecessarily, and this VS team will ensure that you don’t.
CHANGE ORDER CONTROL
VS understands that unforeseen complications can occur during construction. Even the best set of plans can’t predict a completely
unknown condition that ends up costing you time or money. Our team uses their vast experience to quickly trouble shoot conflicts
with as little impact to the budget and schedule as possible. Early identification and communication provide for more time to develop
the most efficient solution and implement it. Whatever the challenge, VS is ready to give you a proper, lasting solution. We accept all
responsibility for completing your project on-time and in-budget.
BUDGET & CHANGE ORDER MANAGEMENT
The City of South Bend, as well as the other communities within St. Joseph County, take on many construction projects each year. At
times, these projects overlap, have street closures that aren’t communicated to the public in advance, create unexpected inconveniences
for delivery drivers, etc., causing residents and business owners to become rather unhappy about their daily commutes through the
area. Because of these numerous perceived inconveniences, local residents may be quick to judge the City and the contractor and
quick to anger with even more infrastructure improvement projects that could impact their daily travel. Bill will be the first line of
defense to ensure businesses and residents are well informed throughout the project.
The construction phasing allows for the entire project to be constructed under operating vehicle traffic at the intersecting streets,
without a posted detour route. This will likely result in a significant amount of daily traffic along the corridor under construction. Major
traffic generators east of the project, such as the University of Notre Dame and downtown South Bend to the southeast will add to
the traffic volume during rush hour times. An important key to an effective maintenance of traffic plan is to have a strong, experienced
Project Supervisor who can assure the traffic is being maintained in the most efficient way to benefit the contractor, City, business
owners, and pedestrians.
Mark and Bill will review the MOT Plan with the City and contractor to coordinate construction with other active infrastructure
projects that may impact traffic flow. Bill will also discuss construction phasing, special events within the area, potential expediting
of construction activities, and MOT communication protocol. Bill will constantly monitor how effective the maintenance of traffic is
working, will complete daily checks of construction signs, and proactively communicate to City officials any changes.
MAINTENANCE OF TRAFFIC (MOT)
VS ENGINEERING, INC. | LETTER OF INTEREST • 9
PROJE CT APPROACH
SOUTH BEND • COAL LINE TRAIL (PHASE I)
Quality Control is always a vital key in any project. To ensure that the City’s
quality standards are met, VS follows strict guidelines and reporting to
ensure that everything is tracked, checked, and documented. Quantities
are tracked, and verified with contractor throughout the project
progress. Daily communication resolves any issues that may occur,
and quantities are reviewed at the scheduled progress meetings.
A critical deliverable on this project is the final construction
record. Quantities are tracked through the duration of the project
to ensure on-time delivery of the final report. VS is committed
to submitting the final construction record within 30 days of the
last day of work. Through our QA/QC measures, we can assure
this project will be handled with the level of customer service you
expect from VS, resulting in minimal impacts to your staff.
QA/QC
As with any construction project, it is critical to be aware of the existing
utility locations and to make certain that ground markings are maintained
throughout the project, ensuring that any utilities within the construction
limits that aren’t being relocated are protected during construction. There
are overhead and underground facilities within the project. Given the nature
of this project, it is likely relocation of some utilities will be required in order
to allow for successful construction.
VS has multiple staff members that are certified utility coordinators selected
for this project. In addition, Mark will be supported by Joe Dluzak, who has
over 35 years of utility coordination experience and has coordinated with
utilities throughout the State. Their knowledge, experience, and contacts
will help ensure that the utility relocations are completed on time so that
construction of this project is not delayed due to lack of coordination.
UTILITY COORDINATION
Communication between Mark, Bill, the contractor, and the public will be key. Constant communication between Bill and City staff will
serve to improve the public’s knowledge of construction activity. The primary method of communicating the construction activities will
be through a weekly or bi-weekly progress meeting with the entire project team. These progress meetings will allow the contractor to
state his construction schedule, address any concerns, and give any updates that are necessary. Progress meetings also allow City
officials to give their input based on their intimate knowledge of the community.
Bill will oversee all on-site activities and will be the City’s eyes and ears to keep this project on time and on budget. Bill will work
with Mark, as well as City staff, and the Site Superintendent to determine that level of effort and construction oversight based on the
contractor’s schedule.
Given the nature and location of the work activities, there may be occasions where multiple inspectors are needed to oversee
all construction activities. It is anticipated that this project will require one full-time Project Supervisor and an additional Project
Inspector (during multiple construction activities) to maintain communication and coordination between the City, the contractor, and
the public.
COMMUNICATION
VS ENGINEERING, INC. | LETTER OF INTEREST • 10
PROJE CT APPROACH
SOUTH BEND • COAL LINE TRAIL (PHASE I)
4TH STREET HERITAGE TRAIL
City of Huntingburg
The City of Huntingburg retained VS Engineering as the prime consultant
for the 4th Street Heritage Trail project. The 4th Street Heritage Trail
is part of Huntingburg’s Stellar Community Designation and the sister
project to the recently completed Market Street Park.
The project lies within the City of Huntingburg’s (federally registered)
historic central business district. The project served to remove and
replace existing 4th Street with a curbless, flex street that will allow
business owners to utilize space in front of their business for commercial
purposes or parking.
Given the amount of businesses on 4th Street, and the importance of them
to the City of Huntingburg, VS along with our project partners, developed
a robust communication strategy that included public meetings, local
office hours, social media campaigns, weekly construction update email
blasts and frequent door to door communications during construction.
Other elements of the project included:
Permeable and Unit Pavers
Enclosed Storm Sewerage
Lighting and Electrical Outlets (including USB ports)
Full ADA Compliance
Bollard Flex Design
MOT plan that ensured access to businesses throughout construction
COVINGTON ROAD: RECREATIONAL TRAIL
City of Fort Wayne
The purpose of this project was to construct a recreational trail using current
design standards, thus improving the serviceability and safety for both vehicular
and pedestrian traffic. The project included a 10’-wide asphalt trail, storm
sewer, asphalt milling and resurfacing, two pedestrian bridges, curb, curb ramp
construction, significant modular block wall construction & pavement markings.
The new trail was part of the City’s River Greenway system. It is located along
a local collector in a residential area, on the southwest side of the City of Fort
Wayne. Part of this project was located along the frontage of Sycamore Hills Golf
Club. Sycamore Hills Golf Club hosted the Junior PGA Golf National Tournament
during the same time as construction. Coordination with the golf club and City
officials during this time was crucial to accommodate the large crowds and
national media. VS provided an array of services for the project, including:
• Complete construction inspection services
• Coordinate all construction related activities
• Preparation of daily construction records on SiteManager
• Utility coordination
• Alternative analysis and selection of preferred alternative
• Prepared payment estimates
• Construction of a Hawk pedestrian traffic signal
• Over a mile in length of new asphalt recreational trail construction
• Material and post-construction testing
• Completion of project final record documents
Inspection
VS ENGINEERING, INC. | LETTER OF INTEREST • 11
Design & Inspection
RELEVANT PROJECTS
SOUTH BEND • COAL LINE TRAIL (PHASE I)
MUNCIE INDUSTRIAL CENTER TRAIL
Delaware County
VS provided construction management and engineering services for this
four (4) mile long, 10’ wide HMA multi-use trail. The Muncie Industrial Center
Trail project was an Indiana Department of Natural Resources Next Level
Trails Round 2 grant finalist. The project was awarded bid at the contract
price of $3,297,000 and construction began in June 2020. The project will
complete construction in May 2021. The project included construction along
Tillotson Avenue from 26th Street to Memorial Drive. From Tillotson Avenue,
the trail extends along 26th Street to Cowan Road. South Delaware County
lacks connectivity between communities. Construction inspection of all
clearing and grubbing, demolition, erosion and sediment control measures,
surface restoration including roadway replacement, sidewalk replacement,
curb replacement, tree removal, fence removal and replacement, and water
service repair was included on this project.
During construction, VS provided observation and inspection of the quality
of work and tracked quantity of item installed for the construction of the
trail. Shop drawings from the contractor were reviewed to be applicable and
accurate to the work detailed in the plans and specifications provided by
VS. Questions from the Contractor were answered and information required
was relayed to the Contractor. Construction inspection included submittal
review, risk management, and utility conflict resolution.
Design & Inspection
BEFORE CONSTRUCTION OF TRAIL
AFTER CONSTRUCTION OF TRAIL
SARE ROAD: TRAIL & INTERSECTION IMPROVEMENTS
City of Bloomington (Ongoing)
VS provided construction inspection for the 0.6 mile segment of
trail from Buttonwood Lane to Renwick Apartments for the City of
Bloomington. The goal of this project was to construct an asphalt
multi-use trail and connect two existing trails along Sare Road. The
project also upgraded the intersection geometrics and signals at
the intersection of Sare Road and Moore’s Pike while also making
improvements to the superstructure of the bridge over Jackson Creek.
Included in the final project was the asphalt multi-use trail with new
curb ramps, new concrete curb & gutter, bridge superstructure work,
new concrete sidewalk, and upgraded signal components. The project
required coordination with utilities as well as local residents and the
motoring public. VS staff were made constantly available to project
officials and the public throughout all construction phases to address
any questions or concerns relating to the project. The firm provided an
array of services for the project, including:
Complete construction inspection services
Administer project progress meetings
Provided weekly progress updates to the client
Coordinate all construction related activities
Remained in contact with the City of Bloomington representatives
Utility coordination
Prepared payment estimates
Material testing
Inspection
VS ENGINEERING, INC. | LETTER OF INTEREST • 12
RELEVANT PROJECTS
SOUTH BEND • COAL LINE TRAIL (PHASE I)
(Rev. 06/27/2018)
Request for Proposal Number:
RFP Item Description:
Affirmative Action Certification (AAC) for Disadvantaged Business Enterprises (DBE)
I hereby certify that my company intends to affirmatively seek out and consider Disadvantaged Business Enterprises (DBEs)
certified by the State of Indiana’s DBE Program and the Kentucky Transportation Cabinet (KYTC) DBE Program to participate as
part of this proposal. An Agreement between INDOT and KYTC established reciprocal acceptance of certification of DBE firms in
their respective states under the Unified Certification Program (UCP) pursuant to 49 CFR §26.81(e) and (f).
I acknowledge that this certification is to be made an integral part of this proposal. I understand and agree that the submission
of a blank certification may cause the proposal to be rejected. I certify that I have consulted the following DBE websites to
confirm that the firms listed below are currently certified DBEs:
INDOT: https://entapps.indot.in.gov/DBELocator/
KYTC: https://transportation.ky.gov/Civil-Rights-and-Small-Business-Development/Pages/Certified-DBE-Directory.aspx
I certify that I have contacted the certified DBEs listed below, and if my company becomes the CONSULTANT, these DBEs have
tentatively agreed to perform the services as indicated. I understand that neither my company nor I will be penalized for DBE
utilization that exceeds the goal. After contract award, any change to the firms listed in this Affirmative Action Certification to
be applied toward the DBE goal must have prior approval by INDOT’s Economic Opportunity Division.
I.DBE Subconsultants to be applied toward DBE goal for the RFP item:
Certified DBE Name Service Planned Estimated Percentage to be
Paid*
%
%
%
%
II.DBE Subconsultants to be utilized beyond the advertised DBE goal for the RFP item:
Certified DBE Name Service Planned Estimated Percentage to be
Paid*
%
%
%
%
Estimated Total Percentage Credited toward DBE Goal:
Estimated Percentage of Voluntary DBE Work Anticipated over DBE Goal:
Company Name:
Signature: Date:
*It is understood that these individual firm percentages are estimates only and that percentages paid may be greater or less as a result of
negotiation of the contract scope of work. My company will use good faith efforts to meet the overall DBE goal through the use of these
or other certified and approved DBE firms.