HomeMy WebLinkAboutOpening of Quotes - East Race Sidewalk Repair Proj No. 117-130 - Walsh & Kelly, Inc.PUBLIC UTILITY
INDEX
SHEET NO.DRAWING INDEX
1 Cover Sheet
2 Index and General Notes
3 Base Quote - Typical Section and General Plan
4 Base Quote and Alternate #1 - Typical Section and General Plan
5 Repair Details and Notes
SIGNATURE
DRAWN:
CHECKED:
DATE
VERTICAL SCALE
DATE
SURVEY BOOK
HORIZONTAL SCALEREVISIONS PROJECT NUMBER
OF
SHEETS
CITY OF SOUTH BEND, INDIANA
EAST RACE
SIDEWALK REPAIR (UNDER COLFAX)
GENERAL NOTES RHK
CMV
-
-
-
MAY, 2018
117-130
25
6/1/18
C ChannelLColfax Ave.Ex. Retaining Wall With Hand Rail
Ex. Sidewalk
Ex. Sidewalk
Sidewalk Under Bridge
Ex. Coaches Area
Ex. Coaches Area
Ex. Retaining Wall With Hand Rail
Ex. Retaining Wall With Hand Rail
Flow
Ex. 12" Dia. Storm Cleanout
Ex. 12" Dia. Cleanout
Ex. 6" Perforated Pipe,
Filter Fabric Wrapped
Ex. 6" Perforated Pipe,
Filter Fabric Wrapped
Ex. 12" Perforated Filter
Fabric wrapped pipe
Ex. 12" Perforated Filter
Fabric wrapped pipe
Ex. 48" Storm Cleanout
MH w/Sump
Concrete Repair Area
(See Details 1 Thru 5 on Sheet 5)
Repair Existing Flap Valve on 4"
Drain Pipe to Seal Watertight
Ex. 4"± Wall Drain
Ex. Inlet with Pump
F
Ex. Sidewalk Ramp
Ex. Retaining Wall
w/Handrail
Ex. Sidewalk Ramp
Clear Roadway
Colfax Bridge
Ex. Bridge Rail
Ex. Bridge
RailEx. Sidewalkon BridgeEx. Sidewalkon BridgeEx. Channel Bottom
A
A
9.5'±112'±
See Concrete
Note 3 (Typ.)
F
9.5'±24'±24'±
Ex. Slope
± 5.1%
Ex. Slope
± 8.6%±8' ClearEx. 4" Concrete Walk
Under Bridge
25'-0" Existing
Channel Bottom
2' Min.
(Varies)
Ex. Coach's Area
2'-0" Min.
Ex. Coach's Area
Ex. 12" Dia. Cleanout
Ex. 1" Weep Hole at 4' Centers
With 1 SF Fabric at Each
Ex. 6" Perforated Pipe,
Filter Fabric Wrapped
Ex. Retaining Wall With
Hand Rail
Ex. 6" Concrete Channel Liner Ex. 12" Perforated Filter
Fabric wrapped pipe
Ex. 2" Pressure Relief Holes. 1 Per
Approx. 4 syd of Liner. With
Gravel Retention Screen
Ex. Grade "B" Borrow or Native Backfill
or Clean Sand. 24" Min. Thickness
Ex. Filter Fabric
Ex. Retaining Wall With
Hand Rail
Ex. Retaining Wall With
Hand Rail
Bottom of Ex. I & M
Duct Bank
Ex. 6" Perforated Pipe,
Filter Fabric Wrapped
Ex. 12" Dia. Cleanout
F
1.5% Max. Cross-slope to East Race Retaining Wall
4"Compacted Subgrade
4.5% Max. Longitudinal Slope as Possible
SIGNATURE
DRAWN:
CHECKED:
DATE
VERTICAL SCALE
DATE
SURVEY BOOK
HORIZONTAL SCALEREVISIONS PROJECT NUMBER
OF
SHEETS
CITY OF SOUTH BEND, INDIANA
EAST RACE
SIDEWALK REPAIR (UNDER COLFAX)
BASE QUOTE
TYPICAL SECTION AND GENERAL PLAN
RHK
CMV
AS NOTED
MAY, 2018
117-130
35
CONCRETE NOTES:
1. Proposed 4" sidewalk shall be graded to drain to existing inlet with pump. Max.
longitudinal slope = 4.5% where possible.
2. Sidewalk shall be removed to existing joints.
3. Preformed
1 2" joint filler shall be placed between proposed sidewalk and existing
structures such as retaining wall, existing sidewalk, etc. Concrete joints in
sidewalk shall be per City of South Bend Standards.
4. The East Race shall be dewatered fully in the concrete repair area prior to any
repair activity for evaluation by the Engineer. The contractor shall coordinate
with the South Bend Parks and Recreation Department to shut the head gates on
the East Race to dewater.
5. See sheet 5 for concrete repair details.
6. Limited clearance and access to work site under bridge.
7. There shall be no disturbance, modifications, or impact to Colfax Bridge or its
appurtenances.
SECTION A-A
EXISTING CHANNEL SECTION
AT COLFAX AVE.
Scale: 3 16" = 1'-0"
GENERAL PLAN
Scale: 1"=10'-0"
NOTE:
Typical section and general plan from as-built drawings. No survey completed in
creating this plan set.
LEGEND:
Remove and Replace 4" Concrete Sidewalk
Concrete Repair
F
SIDEWALK DETAIL
Scale: None
6/1/18
C ChannelLColfax Ave.Ex. Retaining Wall With Hand Rail
Ex. Sidewalk
Ex. Sidewalk
Sidewalk Under Bridge
Ex. Coaches Area
Ex. Coaches Area
Ex. Retaining Wall With Hand Rail
Ex. Retaining Wall With Hand Rail
Flow
Ex. 12" Dia. Cleanout
Ex. 12" Dia. Cleanout
Ex. 6" Perforated Pipe,
Filter Fabric Wrapped
Ex. 6" Perforated Pipe,
Filter Fabric Wrapped
Ex. 12" Perforated Filter
Fabric wrapped pipe
Ex. 12" Perforated Filter
Fabric wrapped pipe
Ex. 48" Cleanout MH
w/Sump
Concrete Repair Area
(See Details 1 Thru 5 on Sheet 5)
Repair Existing Flap Valve on 4"
Drain Pipe to Seal Watertight
Ex. 4"± Wall Drain
Ex. Inlet with Pump F
Ex. Sidewalk Ramp
Ex. Retaining Wall
w/Handrail
Ex. Sidewalk Ramp
Clear Roadway
Colfax Bridge
Ex. Bridge Rail
Ex. Bridge
RailEx. Sidewalkon BridgeEx. Sidewalkon BridgeEx. Channel Bottom
A
A
9.5'±112'±
See Concrete
Note 3 (Typ.)Ex. Slope
± 5.1%
Ex. Slope
± 8.6%±8' ClearEx. 4" Concrete Walk
Under Bridge
25'-0" Existing
Channel Bottom
2' Min.
(Varies)
Ex. Coach's Area
2'-0" Min.
Ex. Coach's Area
Ex. 12" Dia. Cleanout
Ex. 1" Weep Hole at 4' Centers
With 1 SF Fabric at Each
Ex. 6" Perforated Pipe,
Filter Fabric Wrapped
Ex. Retaining Wall With
Hand Rail
Ex. 6" Concrete Channel Liner Ex. 12" Perforated Filter
Fabric wrapped pipe
Ex. 2" Pressure Relief Holes. 1 Per
Approx. 4 syd of Liner. With
Gravel Retention Screen
Ex. Grade "B" Borrow or Native Backfill
or Clean Sand. 24" Min. Thickness
Ex. Filter Fabric
Ex. Retaining Wall With
Hand Rail
Ex. Retaining Wall With
Hand Rail
Bottom of Ex. I & M
Duct Bank
Ex. 6" Perforated Pipe,
Filter Fabric Wrapped
Ex. 12" Dia. Cleanout
F
1.5% Max. Cross-slope to East Race Retaining Wall
4"6" of #8 Stone
on Geotextile
4.5% Max. Longitudinal Slope as Possible
GeotextileEx. Subgrade
SIGNATURE
DRAWN:
CHECKED:
DATE
VERTICAL SCALE
DATE
SURVEY BOOK
HORIZONTAL SCALEREVISIONS PROJECT NUMBER
OF
SHEETS
CITY OF SOUTH BEND, INDIANA
EAST RACE
SIDEWALK REPAIR (UNDER COLFAX)
BASE QUOTE AND ALTERNATE #1
TYPICAL SECTION AND GENERAL PLAN
RHK
CMV
MAY, 2018
117-130
45
SECTION A-A
EXISTING CHANNEL SECTION
AT COLFAX AVE.
Scale: 3 16" = 1'-0"
GENERAL PLAN
Scale: 1"=10'-0"
NOTE:
Typical section and general plan from as-built drawings. No survey completed in
creating this plan set.
LEGEND:
Remove and Replace 4" Concrete Sidewalk
Concrete Repair
F
SIDEWALK DETAIL
Scale: None
6/1/18
CONCRETE NOTES:
1. Proposed 4" sidewalk shall be graded to drain to existing inlet with pump. Max.
longitudinal slope = 4.5% where possible.
2. Sidewalk shall be removed to existing joints.
3. Preformed
1 2" joint filler shall be placed between proposed sidewalk and existing
structures such as retaining wall, existing sidewalk, etc. Concrete joints in
sidewalk shall be per City of South Bend Standards.
4. The East Race shall be dewatered fully in the concrete repair area prior to any
repair activity for evaluation by the Engineer. The contractor shall coordinate
with the South Bend Parks and Recreation Department to shut the head gates on
the East Race to dewater.
5. See sheet 5 for concrete repair details.
6. Limited clearance and access to work site under bridge.
7. There shall be no disturbance, modifications, or impact to Colfax Bridge or its
appurtenances.
1
2
Existing Wall/Slab
TYPICAL CONCRETE JOINT REPAIR
DETAIL 3
Scale: None
1 2
4
3
Water Side
Soil Side
TYPICAL CRACK REPAIR
DETAIL 4
Scale: None
Existing Wall/Slab
TYPICAL DEEP CONCRETE SURFACE REPAIR
DETAIL 1
Scale: None
8
1
2
3 4
6
7
5 WeldTypeS(E)
S(E)
L1
L1 Typ. See 8
SECTION ELEVATION OR PLAN
Boundary of
Spalled Concrete
Required Repair
Layout
6" Min.
(Typ.)
DEEP UNREINFORCED
CONCRETE SURFACE REPAIR
Scale: None
1
SHALLOW UNREINFORCED
CONCRETE SURFACE REPAIR
Scale: None
2
3
4
3
2
DETAIL 5
TYPICAL SHALLOW CONCRETE SURFACE REPAIR
DETAIL 2
Scale: None WeldTypeS(E)
S(E)
L1
L1 Typ. See 8
SECTION ELEVATION OR PLAN
Boundary of
Spalled Concrete
Required Repair
Layout
6" Min.
(Typ.)
14
2
3
5
6
1" Min.
7
SIGNATURE
DRAWN:
CHECKED:
DATE
VERTICAL SCALE
DATE
SURVEY BOOK
HORIZONTAL SCALEREVISIONS PROJECT NUMBER
OF
SHEETS
CITY OF SOUTH BEND, INDIANA
EAST RACE
SIDEWALK REPAIR (UNDER COLFAX)
REPAIR DETAILS
AND NOTES
RHK
CMV
AS NOTED
MAY, 2018
117-130
55
Reconstructed concrete and joint filler material
(Follow requirements of shallow concrete surface repair)
Joint Filler
1
2
Leaking crack
Apply gel epoxy sealer prior to injecting crack injection material.
Remove gel epoxy sealer after sealing work is complete.
Injection ports for hydrophilic crack injection material.
Injection port for epoxy crack injection material shall be directly
into crack.
1
2
3
4
STRUCTURAL REPAIR SCHEDULE
Repair Type Det. Ref. No.Bid Quantity Notes
Deep Concrete Surface Repair Detail 1 & 5 25 SF
As Directed by Engineer
Shallow Concrete Surface Repair Detail 2 & 5 25 SF
As Directed by Engineer
Crack Repair Detail 4 100 LF
As Directed by Engineer
Joint Repair Detail 3 50 LF
As Directed by Engineer
Refer to Specification Section XVIII, Measurement and Payment, for the Final Adjustment of Unit Price Based Bid Quantities.
REPAIR SCHEDULE NOTES:
1. Refer to Specification Section XVIII, Measurement and Payment, for
measurement and payment of structural repair types detailed on Sheet 5.
2. Engineer may direct Contractor to perform repair work that is greater or less than
the estimated quantities identified on the bid form. Contractor shall be paid for
actual quantity of repairs.
Remove existing concrete using hand chipping methods as required. Do not cut
or damage existing reinforcing during concrete removal process.
Remove all deteriorated concrete to sound concrete. Prepare concrete substrate
to obtain a surface profile of 1/8" in depth with a new fractured aggregate
surface.
Where reinforcing steel is present and with active corrosion encountered,
Engineer will review condition of corroded rebar prior to repair. Replacement is
required where loss on rebar cross section is over 10%. After repair where
reinforcing remains, clean reinforcing steel to remove all contaminants and rust.
If reinforcing replacement is required, cut existing corroded reinforcing bar as
required and weld new rebar of same size, as shown. If rebar is not present,
place new #3 rebar in field drilled hole in concrete with an approved chemical
anchor system according to Detail 5.
Surface preparation shall comply with repair mortar manufacturer's instructions.
Install concrete per Project Specification Section XXVIII.
For bid purposes, total depth of repair is equal to member depth.
S, (E) and L1 Definitions correspond to ANSI/AWS D1.4 minimum L1 for bidding
purposes is 3".
1
2
3
4
5
6
7
8
Do not cut reinforcing unless necessary to remove all deteriorated concrete.
Remove all deteriorated concrete to sound concrete. Chip concrete substrate to
obtain a surface profile of 1/8" in depth with a new fractured aggregate surface.
Where reinforcing steel is present and with active corrosion encountered,
Engineer will review condition of corroded rebar prior to repair. Replacement is
required where loss on rebar cross section is over 10%. After repair where
reinforcing remains, clean reinforcing steel to remove all contaminants and rust.
Remove concrete to a depth of 1" minimum behind bar as shown.
If reinforcing replacement is required, cut existing corroded reinforcing bar as
required and weld new rebar of the same size, as shown. If rebar is not present,
place new #3 rebar in field drilled hold in concrete with an approved chemical
anchor system according to detail 5.
Surface preparation shall comply with repair mortar manufacturer's instruction.
Install repair mortar per the manufacturer's requirements.
For bid purposes, assume total depth of repair is 4".
S, (E) and L1 definitions correspond to ANSI/AWS D1.4 minimum L1 for bidding
purposes is 3".
1
2
3
4
5
6
7
8
6" minimum spacing. If overall concrete section is less than 9",
only two rebar required per layer, centered on section. Layers
shall be spaced vertically 12" maximum.
Field drilled hole in concrete. Embed bar 6" with an approved
chemical anchor system.
Minimum Pullout = 6.6 Kips (Typ.)
Install per Specification Section XXIX
Field bend as necessary (Typ.)
Rebar shall be #3
Repair shall be a minimum of 4" deep to require rebar
placement.
1
2
3
4
6/1/18
Version 10/31/2017 Page - 1 Public Works Quote
PROJECT DOCUMENTS
for
EAST RACE SIDEWALK REPAIR (UNDER COLFAX)
City of South Bend
Board of Public Works
117-130
November, 2020
Prepared By
Lawson-Fisher Associates P.C.
525 West Washington Street
South Bend, Indiana 46601
(574) 234-3167 FAX (574) 236-1330
www.lawson-fisher.com
Version 10/31/2017 Page - 2 Public Works Quote
EAST RACE SIDEWALK REPAIR (UNDER COLFAX)
TABLE OF CONTENTS
Page No.
Certification Sheet ............................................................................................................................................ 1
Table of Contents ............................................................................................................................................ 2
Special Provisions ...................................................................................................................................... 3-15
Contractor’s Quote for Public Work ............................................................................................................... 17
Non-Collusion Affidavit ............................................................................................................................. 18-20
Quote/Proposal Sheet .................................................................................................................................... 21
Closure Request Form ............................................................................................................................. 22-23
Project Drawings
Project Location Map and Plans ..................................................................................................... 24-28
Version 10/31/2017 Page - 3 Public Works Quote
SCOPE OF WORK
CITY OF SOUTH BEND
PROJECT NAME: East Race Sidewalk Repairs (Under Colfax)
PROJECT NO. 117-130
QUOTES DUE November 24, 2020 before 9:00 a.m. local time
I. PROJECT DESCRIPTION
A. The project includes the furnishing of all equipment, material, insurance, and labor for the repair of the
cracks, sidewalk, and flap valve along the West side of the East Race under the Colfax Avenue bridge
within the City of South Bend, Indiana. Work to be performed shall include the repair of existing cracks,
removal of existing concrete sidewalk, excavation and placement of #8 stone base drainage layer under
the sidewalk, and replacement of concrete sidewalk as specified in these documents.
II.PREVAILING SPECIFCIATIONS AND DESIGN & CONSTRUCTION STANDARDS
A. The City of South Bend's PREVAILING SPECIFICATIONS, most recent version, and DESIGN &
CONSTRUCTION STANDARDS, most recent version, are to be used on this project.
B. Each Quote provider is specifically instructed to become completely familiar with the most recent
version of the PREVAILING SPECIFICATIONS and the DESIGN & CONSTRUCTION STANDARDS
prior to submitting a quote.
C. Wherever the PREVAILING SPECIFICATIONS refer to “State Specifications,” it shall mean the 2020
INDOT Standard Specifications for the letting effective after September 1, 2019.
D. These SPECIAL PROVISIONS will list only "Additions" or "Deletions" to the PREVAILING
SPECIFICATIONS and are to be used only in conjunction with the PREVAILING SPECIFICATIONS.
E. In the event of conflict between the SPECIAL PROVISIONS and the PREVAILING SPECIFICATIONS,
the SPECIAL PROVISIONS will govern.
III.TERM “OR EQUAL”
A. Prevailing Specifications: None
B. Additions:
1.Where the term "or equal" is used in these specifications, the Quote provider deviating from
specified item shall file with his/her Quote a letter fully explaining and justifying his/her proposed
article or equal. The City of South Bend shall be the sole judge in determining if the “or equal”
offered meets the specification.
IV.TAX EXEMPT
A. Prevailing Specifications: None
B. Additions:
1. Materials and properties purchased under contract with the Owner that becomes a permanent part
of the structure or facilities constructed are not subject to the Indiana Gross Retail Tax (Sales Tax).
The exemption number will be furnished to the Contractor upon award.
Version 10/31/2017 Page - 4 Public Works Quote
V. INDEMNIFICATION
A. Prevailing Specifications: None
B. Additions:
1. Contractor agrees to indemnify, defend and hold harmless the City of South Bend, its agents,
officers and employees, from all costs, losses, claims and suits, including court costs, attorney fees,
and other expenses, arising from or out of the negligent performance of this Contract by Contractor,
or because of arising out of any defect in the goods, materials or equipment supplied by the Quote
provider.
VI. INSURANCE
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 103
B. Additions:
1. All Contractors and subcontractors doing business with the City of South Bend shall present a
Certificate of Insurance showing coverage in the following minimum amount:
a. General Liability: Premises-Completed Operations or Products, Bodily Injury and Property
Damage Combined Single Limit - $5,000,000.
b. There shall be no exclusion for explosion, collapse or underground hazard.
c. Workmen’s Compensation: Statutory State of Indiana Employer's Liability - $100,000.
d. Auto Liability: Bodily Injury and Property Damage Combined Single limit - $1,000,000.
e. The City of South Bend shall be named as additional insured on the Certificate of Insurance.
VII. CONTROL OF WORK
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 105
B. Additions:
1. The complete responsibility for this project lies with the Director of Public Works of the City of South
Bend, Indiana acting through his authorized representatives.
2. Construction Engineering - The Contractor shall provide all the necessary, qualified personnel,
equipment and supplies to perform all work required under this item. There will be no direct payment
for this item.
3. The contractor is responsible to maintain the site which includes but is not limited to; dust control,
site security, erosion control, and protecting adjacent properties.
4. All work activities and closures of the East Race shall be coordinated by the Contractor and
approved by the Parks and Recreation Department such that it does not interfere with scheduled
events at the East Race. No dewatering or restriction of the East Race during the weekends shall
be permitted without prior approval. Work hours for the Project shall be from 7:00 a.m. through 6:00
p.m., Monday through Friday. No work shall be permitted on weekends, Holidays, or after hours
unless approved by the City of South Bend Department of Public Works.
5. Any dewatering required for any work activities shall be incidental to the work item and not be paid
for separately.
VIII. LEGAL RELATIONS
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 107w
B. Additions:
1. The Owner, where mentioned in these documents, is the City of South Bend. The Engineer, where
mentioned in these documents, is Lawson-Fisher Associates P.C.
2. The Contractor shall apply for and obtain any and all required permits for the work from local, state,
and federal agencies and shall comply with permit requirements, including the St. Joseph County
/ City of South Bend Building Department.
3. If the Contractor awarded this contract is not a resident of Indiana, within thirty days, the Contractor
shall provide the Engineer with proof that the Contractor is duly licensed, qualified and registered
with the Secretary of State of Indiana to engage in business within the State of Indiana.
4. The Contractor shall comply with all provisions of Indiana Code 5-16-13, as amended. The Owner
reserves the right to immediately terminate the public work project awarded should the Contractor
Version 10/31/2017 Page - 5 Public Works Quote
be found to be in violation of any provision of Indiana Code 5-16-13 and such violation shall result
in the forfeiture of Contractor’s performance bond to the Owner.
IX. PROSECUTION AND PROGRESS
A. Prevailing Specifications: 2020, INDOT Standard Specifications Sec. 108
B. Additions:
1. The project will have a completion date of twenty-one (21) calendar days for all Base Quote work
and thirty (30) calendar days for all Base Quote and Alternation No. 1 work. The contract time will
start when the Notice to Proceed is delivered and signed. All work shall be completed by October
31, 2021.
2. This project addresses the repair of settled sidewalk along the West side of the East Race under
the Colfax Avenue bridge.
3. The lowest, most responsive Contractor will be awarded this work for completion within the earliest
timeframe possible.
4. The most responsive Contractor should be prepared to have all bonds, insurance and other
documents required herein at project award.
5. All work activities and closures of the East Race shall be coordinated by the Contractor and
approved by the Parks and Recreation Department such that it does not interfere with scheduled
events at the East Race. No dewatering or restriction of the East Race during the weekends shall
be permitted without prior approval.
6. Access to the site shall be through Gintz Avenue and may require coordination due to other projects
in the area.
7. Equipment access under the Colfax bridge will be limited due to restricted headroom. There is
approximately 8-ft. of clearance under the bridge to the finished walk elevation.
8. The City, Engineer, and Contractor will hold a pre-construction meeting following award of the
contract.
9. The Contractor shall be prepared to receive Notice to Proceed coincidental with the Preconstruction
Meeting.
10. Contractor shall provide a schedule to the Owner prior to beginning any work on the site.
X. CHANGE OF CONTRACT TIME
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 108
B. Additions
1. The Contract Time may only be changed by Change Order. Any Claim for an extension in the
Contract Time shall be based on written notice delivered to the Department of Public Works within
seven (7) calendar days of the occurrence of the event giving rise to the claim. Notice of the extent
of the claim with supporting data shall be delivered within fourteen (14) calendar days after such
occurrence unless an official of the Public Works Department allows an additional period of time to
ascertain more accurate data. The Contract Time will be extended in an amount equal to time lost
to delays beyond the control of the Contractor if a claim is made in accordance with this provision.
Such delays shall include acts of neglect by the Public Works employees, or to fires, flood, labor
disputes, epidemics, abnormal weather conditions, governmental procedures, or acts of God.
2. Unless otherwise provided, the Contract time is based upon normal weather conditions. An
extension is granted for weather conditions significantly more severe than normal if the Contractor
demonstrates to the satisfaction of the City that the delay in the progress of the work was due to
such weather. The basis to define normal weather with be the data compiled by the United States
Department of Commerce, National Oceanic and Atmospheric Administration (NOAA).
3. No extension of time will be granted if the Contractor, by his/her/its own action or inaction, including
fault or negligence of Contractor’s subcontractors, caused the delay, or for which any remedies are
provided under any other provision of this agreement.
4. The grant of an extension of time under this Section in no way constitutes a waiver by the City of
any rights or remedies existing under this contract at law or in equity.
Version 10/31/2017 Page - 6 Public Works Quote
XI. DEFAULT AND TERMINATION
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 108
B. Additions:
1. Events of Default shall include Contractor’s failure to perform any of its obligations under this
contract including failure to commence work at the time specified, failure to perform the work in
accordance with these specifications, unauthorized discontinuation of the work, failure to carry out
the work in a manner acceptable to the City, failure to observe Federal, State, or local laws or
regulations, and failure to comply with any other term of this contract.
2. If an Event of Default occurs, the City shall provide Contractor written notice and may permit
Contractor ten (10) calendar days after the date of the notice to cure the default. If the default is
not cured within the ten (10) day cure period, the City may at any time thereafter terminate this
contract in which case the termination shall be final and effective.
3. Upon an Event of Default, the City may invoke the following remedies in addition to those remedies
provided under separate provisions of this contract, the right of set-off against any payments due
or to become due to the Contractor against the retainage, the right to take over and complete the
Work. If the City notifies Contractor that City is invoking its right to complete the Work, all rights that
the Contractor has in order under Contractor’s subcontracts are assigned to the City, subject to the
City’s right to take assignment of all or only selected subcontracts at the City’s discretion. The sole
obligation accepted by the City under such subcontracts is to pay for Work satisfactorily performed
after the date of the assignment. In the event a conditional assignment has not been executed, the
Contractor shall execute or cause to be executed any assignment, agreement, or other document
that may be necessary in the sole opinion of legal counsel to the City’s Board of Public Works to
evidence compliance with this provision. The Contractor shall promptly deliver such documents
upon the City’s request. In the case of such assignment, unless otherwise agreed in writing, The
Contractor remains liability to subcontractors for any payment already involved, and for any claim,
suit or cause of action based upon or resulting from any error, omission, negligence or other breach
of contract by the Contractor, its officers, employees, or agents arising prior to the date of
assignment to the City.
XII. LIQUIDATED DAMAGES
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 108
B. Additions:
1. The contractor shall proceed with the work at such rate of progress to insure full completion within
the Contract Time. It is expressly understood and agreed, by and between the Contractor and the
Owner, that the Contract Time for completion of the work described herein is a reasonable time,
taking into consideration the average climatic and economic conditions and other factors prevailing
in the locality of the work, and excludes the time for unavoidable delays which were beyond the
control and without the fault of the Contractor.
2. If the Contractor shall fail to complete the work within the Contract Time, or extension of time
granted by the Owner, then the Contractor will pay to the Owner the amount for liquidated damages
a sum of five hundred dollars ($500.00) for each calendar day that the Contractor shall remain in
default after the time of completion stipulated in the Contract Documents.
3. The Contractor shall not be charged with liquidated damages or any excess cost when the delay
in completion of the work is due to the following and the Contractor has promptly given written
notice of such delay to the Owner and Engineer/Architect.
a. To any preference, priority, or allocation order duly issued by the Owner.
b. To unforeseeable causes beyond the control and without the fault or negligence of the
Contractor, including but not restricted to acts of God, acts of public enemy, acts of the Owner,
acts of another Contractor in the performance of a Contract with the Owner, fires, floods,
epidemics, quarantine restrictions, strikes, freight embargoes, and abnormal and
unforeseeable weather.
Version 10/31/2017 Page - 7 Public Works Quote
XIII. RETAINAGE AND FINAL PAYMENT
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 109
B. Additions:
1. Payments will be made every thirty (30) calendar days
2. Consistent with provisions of IC 36-1-12-14, the Board of Public Works shall retain a percentage of
payments throughout the duration of the project.
3. Before final payment and retainage are released the Contractor must satisfy the following:
a. All parts and labor meet requirements stated in the specifications.
b. Provide copies of test reports or cut sheets on all materials supplied.
c. Provide As-Built drawings in accordance with the City of South Bend Prevailing Specifications
for Public Works.
d. One (1) copy of the City of South Bend Completion Affidavit and one (1) copy of a Final Waiver
of Lien.
XIV. WARRANTY
A. Prevailing Specifications: None
B. Additions:
1. The Contractor shall provide the following:
a. A Maintenance Bond equal to 10% of the construction cost for a period of 3 years.
XV. OTHER UTILITIES
A. Prevailing Specifications: None
B. Additions:
1. The Contractor shall verify the locations of all utilities by contacting Holey Moley at 1-800-382-5544
at least two (2) working days, not counting Saturdays, Sundays or federal and state holidays before
proceeding with construction. It shall also be the Contractors responsibility to contact any other
utility that is not contacted by Holey Moley and verify the utility locations.
2. The Contractor shall be responsible for working with the other utilities, i.e., gas electric, telephone,
etc. in order to assure that all utilities that need to be replaced or relocated can be done with a
minimum disturbance to service. The Contractor shall also be responsible for coordinating
schedules with the various utilities such that they can proceed with their relocation work as
efficiently as possible.
3. If the odor of natural gas is detected in a work area at any time during the course of work, the
Contractor shall immediately notify NIPSCO at 1-800-634-3524. The Contractor shall also
immediately notify the residents of adjacent properties. The Contractor shall advise the residents
to evacuate their homes immediately if the odor is present within the dwelling.
4. Restoration of sprinkler systems damaged by the Contractor's operations shall be repaired by the
Contractor at no additional cost to the City or the Owner of the system.
5. The following utilities have been identified within or near to the project area. Additional utilities may
be present and the Contractor shall be responsible for all coordination required to complete the
work as shown in the plans.
a. The facilities of American Electric Power (AEP) exist within the project area but are not
expected to be affected by the proposed construction. If questions arise, Antonio Macias of the
utility may be contacted at 574-236-1658.
b. The facilities of AT&T exist within the project area but are not expected to be affected by the
proposed construction. If questions arise, Dennis Bunch of the utility may be contacted at
574-237-8380.
c. The facilities of Comcast exist within the project area but are not expected to be affected by
the proposed construction. If questions arise, Jay Castello of the utility may be contacted at
224-229-5573.
d. The facilities of NIPSCO exist within the project area but are not expected to be affected by the
proposed construction. If questions arise, Richard Wahlgren of the utility may be contacted at
574-284-2277.
Version 10/31/2017 Page - 8 Public Works Quote
e. The facilities of U.S. Signal exist within the project area but are not expected to be affected by
the proposed construction. If questions arise, Charlie Olszewski of the utility may be contacted
at 616-233-7191.
f. The facilities of South Bend Water Works exist within the project area but are not expected to
be affected by the proposed construction. If questions arise, Ed Herman of the utility may be
contacted at 574-245-6108.
XVI. DESCRIPTION OF WORK
A. Prevailing Specifications: None
B. Additions:
1. The project includes the furnishing of all equipment, material, insurance, and labor for the repair
of various channel and retaining wall cracks, removal and replacement of sidewalk, and a flap
valve repair along the West side of the East Race under the Colfax Avenue bridge within the City
of South Bend, Indiana.
2. The Contractor shall preserve and protect all surrounding property, structures, tenants, visitors and
their property from damage caused by the Contractor’s operations.
XVII. PLANS
A. Prevailing Specifications: City of South Bend Design and Construction Standards
B. Additions:
1. The plans consist of 5 Sheets.
2. The work shall conform to the general description and scope described in the plans.
3. The drawings are schematic in nature.
XVIII. QUOTE REQUIREMENTS
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 102.01
B. Additions:
1. The Contractor shall submit the following fully executed documents with his Quotation:
a. Contractor’s Quote for Public Works.
XIX. MOBILIZATION AND DEMOBILIZATION
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 110
B. Additions:
1. The Lump Sum (LS) unit price for this item shall not be more than five (5%) percent of the total of all
other quote items of the proposal.
2. For payment purpose, the mobilization portion of this item will be limited to 75% of the LS price. The
remaining portion will be considered as demobilization when work is completed and upon final site
cleanup.
XX. CONSTRUCTION ENGINEERING
A. Prevailing Specifications: 2020, INDOT Standard Specification Sections 105.08(b), 105.08(c)
B. Additions:
C.
1. The Contractor will provide all work required under this item.
2. The Engineer will be responsible for the horizontal and vertical control points as shown on the
plans.
3. The Contractor will be responsible for all the horizontal alignment from the Engineer's control points
and also the vertical grades shown on the Plans from the Engineer's benchmarks.
4. The Contractor shall be responsible for witnessing the horizontal and vertical points, establishing
construction limits, and maintenance of same for the duration of the project.
Version 10/31/2017 Page - 9 Public Works Quote
5. Construction Engineering will be paid for at the lump sum price bid for this item, and shall not
exceed two (4%) percent of the total of all other bid items of the original proposal.
6. The Contractor shall maintain at the site for the Owner, one (1) record copy of all drawings,
specifications, Addenda, Change Orders and other modifications, in good order and marked
currently to record all changes made during construction.
7. The Contractor shall not be able to make additional costs claim for compressed schedule unless
the delay is attributed to events or the work of others beyond their control.
XXI. MAINTENANCE OF TRAFFIC
A. Prevailing Specifications: 2020, INDOT Standard Specifications Sections 105 & 801
B. Additions:
1. Maintenance of traffic during construction shall conform to the “Indiana Manual on Uniform Traffic
Control Devices” and the City of South Bend Design and Construction Standards.
2. The attached “Traffic Closure Request” form is to be used for any lane restrictions or closures and
required to be filled out and sent to the Department of Public Works
3. The Contractor shall arrange and prosecute the work specified for this contract in such a manner
that traffic on existing streets is unrestricted throughout the Project. The Engineer shall approve
the method of traffic control. No construction equipment, vehicles, materials, supplies or temporary
facilities shall be left unattended in the right-of-way of any street or left parked overnight without
proper marking and lighting
4. The Contractor shall accommodate for any and all pedestrian traffic in their Traffic Control Plan.
Any pedestrian detours and sidewalk closures shall be safe, protected, and free of hazards.
5. After the award of the contract and before beginning the work, the Contractor shall submit his
proposed schedule of operations for the review of the Engineer. This schedule shall be available
at the Preconstruction meeting as further described in the “Prosecution and Progress” section. The
schedule of operations as reviewed by the Engineer shall be maintained at all times.
6. “Road Construction Ahead” signs in each direction, signing for flagging operations and all other
necessary signing shall be provided by the Contractor.
7. This item will not be measured and shall be paid for at the Lump Sum (LS) unit price for
MAINTENANCE OF TRAFFIC.
XXII. CLEARING RIGHT OF WAY
A. Prevailing Specifications: 2020, INDOT Standard Specifications Sections 201, 202
B. Additions:
1. The lump sum price bid for “Clearing Right-of-Way” shall include “Clearing and Grubbing” and
“Removal of Structures and Obstructions” which shall include removal of all brush, trees, other
vegetation, man-made materials, and other items identified on the plans for removal, required to
perform the scope of work, except for those items which are specifically listed in the proposal for
separate payment.
2. Any fencing, including the black raceway fence, or man-made obstructions (i.e. guardrail, utility
markers, landscape rocks, etc.) which are in place at the start of construction shall be carefully
removed. These items shall be restored using recovered serviceable materials. These shall include
obstructions within existing right-of-way impacted by the scope of the work. Removal and
restoration of fencing and other man-made obstacles within the right-of-way will not be paid for
separately and shall be included in the cost of the pay item. Damaged items caused by the
Contractor shall be restored or replaced at no additional cost to the Owner.
3. The Contractor shall provide a pre-construction video record and photo journal of the entire project
area to verify the existing conditions prior to construction.
4. The Contractor shall have all underground utilities field located prior to the start of construction.
The Contractor shall protect existing and relocated utilities from damage.
5. Burial of debris on site will not be allowed. Disposal of debris shall be at an off-site location in an
approved manner according to all County and State Statutes.
6. This item will not be measured, this work shall be paid for at the Lump Sum (LS) unit price for
CLEARING RIGHT-OF-WAY.
Version 10/31/2017 Page - 10 Public Works Quote
XXIII. TEMPORARY EROSION AND SEDIMENT CONTROL
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 205
B. Additions:
1. Temporary erosion and sediment control shall be provided to prevent disturbed soil from leaving
the project site and shall include perimeter protection, temporary surface stabilization, concentrated
flow protection, concrete washouts, and other items as shown on the plans and described in
Section 205 as required.
2. This work will not be measured for payment separately but shall be paid at the contract unit price
for TEMPORARY EROSION AND SEDIMENT CONTROL (LS).
XXIV. COMMON EXCAVATION
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 203
B. Additions:
1. The Contractor shall keep all public roadways, row, and sidewalks that are used for hauling
excavation or borrow material clean and free of any spillage of material. Said public areas shall be
cleaned on a daily basis. The cost of removal of any spillage shall be included in the unit cost of
excavation or borrow material and no further compensation will be made. Failure to comply with this
requirement will result in cleaning of the spillage by the Owner with a back charge of two hundred
fifty dollars ($250.00) per occurrence.
2. The Contractor shall field verify the location of all utilities prior to beginning work.
3. The quantities of excavation shown on the proposal sheet will not be measured separately by the
Engineer. If the Contactor has acceptable data that indicates a excavation quantity error by more
than 10%, then additional measurements will be performed by the Contractor and submitted to the
Engineer for review and determination. Measurement will not include material excavated beyond
authorized limits. If the quantity error is agreed by the Engineer, then the unit price on the proposal
form will be extended.
4. This item in this described work shall be paid for at the contract unit price for COMMON
EXCAVATION per cubic yard (CYS).
XXV. COMPACTED AGGREGATE
A. Prevailing Specifications: City of South Bend Design and Construction Standards 2020, INDOT
Standard Specification Sections 105, 207, 301, and 303.
B. Additions:
1. All coarse aggregate shall be Class D or higher of the specified size. The cost of placing,
compacting, water and incidentals necessary for placement shall be included in the cost of the
compacted aggregate.
2. The condition of the subgrade at the time paving material is placed is required to be in accordance
with INDOT Standard Specifications 105.03 and 207.03.
3. The material type shall be either natural washed stone or limestone placed on geotextile. Materials
such as crushed concrete and slag which are susceptible to leachate shall not be permitted.
4. The quantities of compacted aggregate shown on the proposal sheet will not be measured
separately by the Engineer. If the Contactor has acceptable data that indicates a compacted
aggregate quantity error by more than 10%, then additional measurements will be performed by the
Contractor and submitted to the Engineer for review and determination. Measurement will not
include material installed beyond authorized limits. If the quantity error is agreed by the Engineer,
then the unit price on the proposal form will be extended.
5. The accepted quantity of COMPACTED AGGREGATE, NO. 8 will be paid for at the contract unit
price per ton (TON), complete in place.
Version 10/31/2017 Page - 11 Public Works Quote
XXVI. GEOTEXTILE, TYPE 1A
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 616
B. Additions: None
XXVII. CONCRETE, 4" SIDEWALK
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 604
B. Additions:
1. This pay item shall consist of the labor and materials to construct the 4" concrete sidewalk as shown
on the plans.
2. The finished concrete shall be finished, jointed, and cured in accordance with INDOT Standard
Specification 604.03. Joints shall match existing adjacent concrete sidewalk.
3. Concrete shall be performance based and follow:
a. All concrete shall have limestone aggregate.
b. A minimum 28 day strength of 4,000 PSI.
c. Shall have a 5% to 8% entrained air with an admixture that conforms to ASTM C-260.
d. Slump shall be a maximum of 4".
C. The accepted quantity of CONCRETE, 4" SIDEWALK will be paid at the contract unit price per square
yard (SYS), complete in place.
XXVIII. CONCRETE REPAIR AND REHABILITATION
A. Prevailing Specifications: None.
B. Additions:
1. The Contractor shall provide all labor, materials, equipment, and incidentals as shown, specified,
and required to repair or rehabilitate, as required, all existing concrete shown or indicated in the
Contract Documents as being repaired or rehabilitated.
2. Review installation procedures under this and other Work Items and coordinate the work that must
be installed with or before repair and rehabilitation of concrete.
MATERIALS:
Standards referenced in this Section are:
1. ASTM C109/C109M-16a, Standard Test Method for Compressive Strength of Hydraulic Cement
Mortars (Using 2-in. or [50-mm] Cube Specimens).
2. ASTM C882/C882M-13a, Standard Test Method for Bond Strength of Epoxy-Resin Systems Used
with Concrete by Slant Shear.
3. ASTM D3574-17, Standard Test Methods for Flexible Cellular Materials – Slab, Bonded, and
Molded Urethane Foams.
4. ASTM D1042-12(2017), Standard Test Method for Linear Dimensional Changes of Plastics Caused
by Exposure to Heat and Moisture.
Repair Mortar:
A. Product Description: Repair mortar shall be prepackaged, cement-based product specifically
formulated for repairing concrete surface defects.
B. Products and Manufacturers: Provide one of the following:
1. SikaTop 122 Plus, SikaTop 123 Plus, or SikaTop 126 Plus, by Sika Corporation.
2. DuralTop Gel, DuralTop Flowable Mortar by Euclid Chemical Company.
3. Or approved equal.
Version 10/31/2017 Page - 12 Public Works Quote
C. Materials:
1. Provide a two-component, polymer-modified, Portland cement, fast-setting, trowel-grade mortar.
Repair mortar shall be enhanced with penetrating corrosion inhibitor, and shall have the following
properties:
Physical Property Value ASTM Standard
Minimum Compressive Strength at One Day 2,000 psi C109
Minimum Compressive Strength at 28 Days 6,000 psi C109
Minimum Bond Strength at 28 Days 1,800 psi C882*
* Modified for use with repair mortars.
2. Where the least dimension of the placement in width or thickness exceeds four inches, extend
repair mortar by adding aggregate as recommended by repair mortar manufacturer.
Crack Injection Materials:
A. Structural Crack Repair System:
1. Epoxy for injection shall be low-viscosity, high-modulus moisture insensitive type.
2. Products and Manufacturers: Provide one of the following:
a. Sikadur 35, Hi-Mod L.V. and Sikadur 31, Hi-Mod Gel, by Sika Corporation.
b. Eucopoxy Injection Resin, by Euclid Chemical Company.
c. Or approved equal.
B. Non-structural Crack Repair System:
1. Hydrophobic Polyurethane Chemical Grout:
a. Provide hydrophobic polyurethane that forms a flexible gasket.
b. Products and Manufacturers: Provide one of the following:
1. SikaFix HH LV, by Sika Chemical Company.
2. Hydro Active Flex SLV, by De Neef Construction Chemicals, Inc.
3. Or approved equal.
c. Shrinkage limit shall not exceed 4.0 percent in accordance with ASTM D1042.
d. Minimum elongation of 250 percent in accordance with ASTM D3574.
e. Minimum tensile strength of 150 psi in accordance with ASTM D3574.
2. Hydrophilic Acrylate-Ester Resin:
a. Hydrophilic crack repair system shall be acrylate-ester resin that forms a flexible gasket and
increase in volume by at least 50 percent when in contact with water.
b. Products and Manufacturers: Provide one of the following:
1. Duroseal Multigel 850, manufactured by BBZ USA, Inc.
2. Or approved equal.
SUBMITTALS:
A. Action Submittals: Submit the following:
1. Product Data: Information on all products proposed for use, including manufacturer’s brochures,
technical data, specifications, and other applicable data.
2. Manufacturer’s Instructions: Manufacturer’s recommended procedures for installing materials
proposed for use.
B. The Contractor shall submit any alternate repair mortar or crack injection materials to the engineer for
review and approval.
Version 10/31/2017 Page - 13 Public Works Quote
CONSTRUCTION METHODS:
Inspection:
A. Examine areas and conditions under which the repair Work is to be installed and notify ENGINEER in
writing of conditions detrimental to proper and timely completion of the Work. Do not proceed with the
Work until unsatisfactory conditions have been corrected.
B. Engineer will inspect all surfaces and determine initial location and extents of all concrete repairs and
rehabilitations. Contractor shall coordinate with Engineer with regard to scheduling inspections.
Inspections will be conducted after the area is dewatered by the Contractor. The Contractor shall
coordinate with the South Bend Parks and Recreation Department to shut the head gates on the East
Race to dewater.
Preparation:
A. Surface Preparation:
1. Initial Surface Preparation: Remove by handchipping, abrasive blasting, or hydro blasting all
laitance, foreign material, and unsound concrete from entire area to be repaired. Further roughen
surface as specified in this Section. Where non-shrink grout or repair mortar is used, perform
additional surface preparation, if any, recommended by product manufacturer.
2. Wetting Procedure: Where repair concrete, shotcrete, or cement grout is used, and bonding agent
is not required, or where repair mortar or non-shrink grout manufacturer recommends wet or
saturated surface, perform the following:
a. Continuously apply water for at least four hours to surface being repaired. Where large surface
areas are to be repaired, use fog-spray nozzles, mounted on stands, in sufficient number so
that entire surface to be repaired is contacted by fog spray cloud.
b. Prevent concrete from drying until after repair is completed. Re-wet surfaces not yet repaired
using water sprays at least daily; should more than four days elapse without re-wetting surfaces
not yet repaired, repeat the original saturating procedure.
c. Remove standing water in areas to be repaired before placing repair material. Provide means
to remove excess water from structure.
3. Preparation for Epoxy Bonding Agent: Where repair material manufacturer recommends use of
epoxy-bonding agent, conform to recommendations of both repair material manufacturer and
bonding agent manufacturer.
Installation, General:
A. Care shall be taken to fully consolidate repair material, completely filling all portions of space to be
filled.
B. Bring surface being repaired into alignment with adjacent surfaces, providing uniform, even surface.
Surface repair shall match adjacent existing surfaces in texture and shall receive coatings or surface
treatments, if any, provided for the existing surface adjacent to repaired surface.
C. Curing:
1. Curing of repair mortar and non-shrink grout shall be in accordance with manufacturer’s
recommendations, except that minimum cure period shall be three days.
2. Curing of other materials shall be in accordance with requirements of Section XVII. Concrete 4”
Sidewalk.
Repair of Surface Defects:
A. Surface defects are depressions in a concrete surface that do not extend all the way through the
concrete. Surface defects can result from removal of an embedded item, removal of an intersecting
concrete member, physical damage, or unrepaired rock pockets created during original placement. For
spalls that result from corroded reinforcing steel or other embedment refer to REPAIR OF
DETERIORATED CONCRETE in Work Item.
Version 10/31/2017 Page - 14 Public Works Quote
B. Preparation: Perform the following in addition to requirements of PREPARATION of this Section:
1. Remove by handchipping all loose, damaged concrete to sound material.
2. Where existing reinforcing is exposed, remove concrete to minimum of one-inch around exposed
bars. If existing bars are cut through, cracked, or cross-sectional area is reduced by more than 10
percent from original, immediately notify Engineer.
3. Score-cut perimeter of area to be repaired to minimum depth of 1/2-inch and maximum depth that
will not cut existing reinforcing steel. Chip out existing concrete to the score line so that minimum
thickness of repair mortar will be 1/2-inch.
C. Repair Material:
1. Completely fill the surface defect with specified repair material, in accordance with material
manufacturer’s instructions and the Contract Documents.
2. Perform, with repair mortar, repairs of surface defects in concrete normally in contact with water or
soil, and interior surfaces of structures that contain water.
3. Repair of other surface defects may be by applying repair mortar, repair concrete, shotcrete, or
cement grout, as appropriate.
Repair of Deteriorated Concrete:
A. This Article pertains to deteriorated concrete which has been damaged due to corrosion of reinforcing
steel, physical damage due to abrasion, or damage due to chemical attack. Use repair mortar, as
specified in this Article, for repairing deteriorated concrete.
B. Surface Preparation: In addition to requirements of the PREPARATION section, perform the following
surface preparation:
1. Remove loose, broken, softened, and acid-contaminated concrete by abrasive blasting and
handchipping to sound, uncontaminated concrete.
2. Upon completion of removal of deteriorated concrete, notify ENGINEER in writing. Allow one week
for ENGINEER to evaluate the surface, perform testing for acid contamination if required, determine
if additional concrete shall be removed, and to develop special repair details (if any) required.
Should ENGINEER determine that additional concrete be removed to reach sound,
uncontaminated concrete, allow another one-week period for further evaluation and testing
following the additional removal.
3. Surface preparation shall conform to recommendations of repair mortar manufacturer.
4. Repair and rehabilitate isolated areas of exposed reinforcing bars in accordance the REPAIR OF
SURFACE DEFECTS section. If extensive areas of reinforcing steel are uncovered after removal
of deteriorated concrete, ENGINEER will determine the repair methods required.
C. Repair Mortar Placing:
1. Conform to manufacturer’s recommended procedures for mixing and placing repair mortar.
2. After initial mixing of repair mortar, addition of water is not allowed.
3. Minimum Thickness:
a. Install repair mortar to not less than minimum thickness recommended by manufacturer, and
not less than 1/2-inch.
b. Where removal of deteriorated concrete results in repair thickness of less than minimum
required thickness to return to original concrete surface in isolated areas totaling less than 10
(ten) percent of total repair surface area, remove additional concrete to obtain at least the
required minimum thickness.
c. Where surface area with repair thickness less than minimum required thickness exceeds 10
(ten) percent of total repair area, notify ENGINEER.
d. Provide repair mortar so that minimum cover over existing reinforcing steel is two inches. Do
not place repair mortar creating locally raised areas.
e. Where transitioning to or from wall surfaces not requiring repair, do not feather-out repair mortar
at transition. Instead, form the transition by saw cutting a score line to not less than minimum
required repair mortar depth and chip out concrete to the saw cut line. Do not cut or otherwise
damage reinforcing steel.
4. Place repair mortar to an even, uniform plane to restore concrete member to its original surface.
Out-of-plane tolerance shall be such that the gap between 12-inch long straight edge and repair
mortar surface does not exceed 1/8-inch, and gap between a four-foot long straight edge and repair
Version 10/31/2017 Page - 15 Public Works Quote
mortar surface shall not exceed 1/4-inch. Tolerances specified in this paragraph apply to straight
edges placed in any orientation at any location.
D. Finishing:
1. Provide smooth, steel trowel finish to repair mortar.
2. When completed, there shall be no sharp edges. Provide exterior corners, such as at penetrations,
one-inch radius. Interior corners shall be square.
Crack Injection:
A. Examine areas under which injection Work will be installed and locate cracks that require injection.
Identify and inject cracks greater than 0.010-inch wide in structures that retain or contain water.
B. Install injection material in accordance with crack injection manufacturer’s requirements.
C. After injecting and curing, verify that injected material penetrated the crack adequately and that there
is no visible leakage through the crack. After injecting, if crack continues to leak, re-inject crack at no
additional cost to OWNER until structure is watertight.
D. If proper penetration of crack cannot be achieved, submit to ENGINEER a proposed alternate approach
for modifying the specified injection procedure to properly seal the crack. In concrete cracked as a
result of CONTRACTOR’s operations, perform modifications to crack injection procedure and fully
repair the crack without additional cost to OWNER or extension of the Contract Times.
MEASUREMENT AND PAYMENT:
Deep Concrete Surface Repair and Shallow Concrete Surface Repair shall be measured by the square foot
at the exposed surface of the concrete repair. Once the repair depth reaches one-half of the members
overall depth or deeper, it shall be measured as a Deep Concrete Surface Repair. Crack Repair and Joint
Repair shall be paid for by the linear foot.
The accepted quantities of Deep Concrete Surface Repair and Shallow Concrete Surface Repair shall be
paid for at the contract unit price per square foot. Crack Repair and Joint Repair shall be paid for at the
contract unit price per linear foot.
The estimated volumes shown on the plans shall be used for to determine the unit price per pay item listed
above. The mobilization and demobilization shall be paid for under Item XIX Mobilization and
Demobilization and not this work item.
Reinforcing steel will not be measured and the cost shall be included in the cost of other pay items in this
section.
Any dewatering required for this work shall be incidental to the cost of the work and shall not be paid for
separately.
XXIX. CHANNEL ANCHOR SYSTEM
A. Prevailing Specifications: 2020, INDOT Standard Specification Section 702.
B. Additions:
1. The Chemical Anchor System shall be from the INDOT approved Chemical Anchor Systems listed
which is on the INDOT website under Qualified Materials List and Certified Source Lists.
2. Measurement and Payment.
a. Chemical Anchor Systems will not be measured and the cost shall be included in the cost of
pay items in Section XVIII, Concrete Repair and Rehabilitation.
Version 10/31/2017 Page - 16 Public Works Quote
XXX. EXISTING 4" FLAP VALVE, REPAIR
A. Prevailing Specifications: None.
B. Additions:
1. The Contractor shall clean, repair, adjust, and/or replace, to the satisfaction of the Engineer, the
existing 4” drain flap valve as identified on the plans in order to make it watertight.
2. This work will be counted for payment at the contract unit price for 4” FLAP VALVE, REPAIR
(EACH) and shall include all labor, material and appurtenances required to restore the valves
function.
Version 10/31/2017 Page - 17 Public Works Quote
CITY OF SOUTH BEND, INDIANA
CONTRACTOR’S QUOTE FOR PUBLIC WORK
PROJECT NAME: East Race Sidewalk Repair (Under Colfax)
PROJECT NO. 117-130
QUOTES DUE November 24, 2020 before 9:00 a.m. local time
(Must be completed for all quotes. Please type or print)
Date: Firm:
Address:
City/State/Zip: Telephone Number: ( )
Agent of Bidder (if Applicable):
Pursuant to notices given, the undersigned offers to furnish labor and/or material necessary to complete the
public works project of:
East Race Sidewalk Repair (Under Colfax)
the City of South Bend, Indiana, in accordance with plans and specifications prepared by:
The City of South Bend, Department of Public Works
and dated November 2020 ] for the sum of (enter the Total Quote as shown on the Proposal)
($ )
(Enter Sum of Total Quote plus Alternates shown on Proposal) (Numerical)
If alternative quotes apply, the undersigned submits a proposal for each in accordance with the notice. Any
addendums attached will be specifically referenced at the applicable page.
If additional units of material included in the contract are needed, the cost of units must be the same as that shown
in the original contract if accepted by the City of South Bend. If the quote is to be awarded on a unit basis, the
itemization of the units shall be shown on a separate attachment.
ACCEPTANCE
The above quote is accepted this day of 20
Subject to the following conditions:
BOARD OF PUBLIC WORKS
Gary A. Gilot, President Jordan V. Gathers, Member
Elizabeth A. Maradik, Member Joseph R. Molnar, Member
Therese J. Dorau, Member Attest: Linda M. Martin, Clerk
By
(Signature)
(Printed Name of Person Signing)
Version 10/31/2017 Page - 18 Public Works Quote
When the prospective Contractor is unable to certify to any of the statements below, it shall attach an
explanation to this Affidavit.
CONTRACTOR’S NON-COLLUSION AFFIDAVIT, NON-DEBARMENT AFFIDAVIT,
EMPLOYMENT ELIGIBILITY VERIFICATION, NON-DISCRIMINATION COMMITMENT FOR
CONTRACTORS AND CERTIFICATION OF USE OF UNITED STATES STEEL PRODUCTS
OR FOUNDRY PRODUCTS
(Must be completed for all quotes and bids. Please type or print)
STATE OF INDIANA )
) SS:
COUNTY )
The undersigned Contractor, being duly sworn upon his/her/its oath, affirms under the penalties
of perjury that:
1. Contractor has not, nor has any other member, representative, or agent of the firm,
company, corporation or partnership represented by him, entered into any combination,
collusion or agreement with any person relative to the price to be bid by anyone at such
letting nor to prevent any person from bidding nor to induce anyone to refrain from bidding,
and that this bid is made without reference to any other bid and without any agreement,
understanding or combination with any other person in reference to such bidding.
Contractor further says that no person or persons, firms, or corporation has, have or will
receive directly or indirectly, any rebate, fee, gift, commission or thing of value on account
of such sale; and
2. Contractor certifies by submission of this proposal that neither contractor nor any of its
principals are presently debarred, suspended, proposed for debarment, declared
ineligible, or voluntarily excluded from participation in this transaction by any Federal
department or agency; and
3. Contractor has not, nor has any successor to, nor an affiliate of, Contractor, engaged in
investment activities in Iran.
a. For purposes of this Certification, “Iran” means the government of Iran and any agency
or instrumentality of Iran, or as otherwise defined at Ind. Code § 5-22-16.5-5, as
amended from time-to-time.
b. As provided by Ind. Code § 5-22-16.5-8, as amended from time-to-time, a Contractor
is engaged in investment activities in Iran if either:
i. Contractor, its successor or its affiliate, provides goods or services of twenty
million dollars ($20,000,000) or more in value in the energy sector of Iran; or
ii. Contractor, its successor or its affiliate, is a financial institution that extends
twenty million dollars ($20,000,000) or more in credit to another person for
forty-five (45) days or more, if that person will (i) use the credit to provides
goods and services in the energy sector in Iran; and (ii) at the time the financial
institution extends credit, is a person identified on list published by the Indiana
Department of Administration.
4. Contractor does not knowingly employ or contract with an unauthorized alien, nor retain
any employee or contract with a person that the Contractor subsequently learns is an
Version 10/31/2017 Page - 19 Public Works Quote
unauthorized alien. Contractor agrees that he/she/it shall enroll in and verify the work
eligibility status of all of Contractor’s newly hired employees through the E-Verify Program
as defined by I.C. 22-5-1.7-3. Contractor’s documentation of enrollment and participation
in the E-Verify Program is included and attached as part of this bid/quote; and
5. Contractor shall require his/her/its subcontractors performing work under this public
contract to certify that the subcontractors do not knowingly employ or contract with an
unauthorized alien, nor retain any employee or contract with a person that the
subcontractor subsequently learns is an unauthorized alien, and that the subcontractor
has enrolled in and is participating in the E-Verify Program. The Contractor agrees to
maintain this certification throughout the term of the contract with the City of South Bend,
and understands that the City may terminate the contract for default if the Contractor fails
to cure a breach of this provision no later than thirty (30) days after being notified by the
City.
6. Persons, partnerships, corporations, associations, or joint venturers awarded a contract
by the City of South Bend through its agencies, boards, or commissions shall not
discriminate against any employee or applicant for employment in the performance of a
City contract with respect to hire, tenure, terms, conditions, or privileges of employment,
or any matter directly or indirectly related to employment because of race, sex, religion,
color, national origin, ancestry, age, gender expression, gender identity, sexual orientation
or disability that does not affect that person's ability to perform the work.
In awarding contracts for the purchase of work, labor, services, supplies, equipment,
materials, or any combination of the foregoing including, but not limited to, public works
contracts awarded under public bidding laws or other contracts in which public bids are
not required by law, the City, its agencies, boards, or commissions may consider the
Contractor’s good faith efforts to obtain participation by those Contractors certified by the
State of Indiana as a Minority Business (“MBE”) or as a Women’s Business Enterprise
(“WBE”) as a factor in determining the lowest, responsible, responsive bidder.
In no event shall persons or entities seeking the award of a City contract be required to
award a subcontract to an MBE/WBE; however, it may not unlawfully discriminate against
said WBE/MBE. A finding of a discriminatory practice by the City’s MBE/WBE Utilization
Board shall prohibit that person or entity from being awarded a City contract for a period
of one (1) year from the date of such determination, and such determination may also be
grounds for terminating the contact for which the discriminatory practice or noncompliance
pertains.
7. The undersigned contractor agrees that the following nondiscrimination commitment shall
be made a part of any contract which it may henceforth enter into with the City of South
Bend, Indiana or any of its agencies, boards or commissions.
Contractor agrees not to discriminate against or intimidate any employee or applicant for
employment in the performance of this contract with privileges of employment, or any
matter directly or indirectly related to employment, because of race, religion, color, sex,
gender expression, gender identity, sexual orientation, handicap, national origin or
ancestry. Breach of this provision may be regarded as material breach of contract.
I, the undersigned bidder or agent as contractor on a public works project, understand my
statutory obligations to the use of steel products or foundry products made in the United
States (I.C. 5-16-8-1). I hereby certify that I and all subcontractors employed by me for
this project will use steel products or foundry products on this project if awarded. I
understand that violations hereunder may result in forfeiture of contractual payments.
Version 10/31/2017 Page - 20 Public Works Quote
***
I hereby affirm under the penalties of perjury that the facts and information contained in the foregoing bid
for public works are true and correct.
Dated this day of , 20__
Contractor/Bidder (Firm)
Signature of Contractor/Bidder or Its Agent
Printed Name and Title
Subscribed and sworn to before me this day of , 20
My Commission Expires
Notary Public
County of Residence
Version 10/31/2017 Page - 21 Public Works Quote
Item
No. Description Quantity Unit Unit Price Total Amount
1 Mobilization and Demobilization 1 LSUM $
2 Construction Engineering 1 LSUM $
3 Maintenance of Traffic 1 LSUM $
4 Clearing Right-of-Way 1 LSUM $
5 Temporary Erosion and Sediment
Control 1 LSUM $
8 Sidewalk Remove 51 SYS $
10 4" Plain Concrete Sidewalk 51 SYS $
11 Deep Concrete Surface Repair 25 SF $
12 Shallow Concrete Surface Repair 25 SF $
13 Crack Repair 100 LF $
14 Joint Repair 50 LF $
15 4" Flap Valve, Repair 1 EACH $
Total Amount of Base Quote $
Quote Alternate No. 1
6 Common Excavation 19 CYS $
7 Compacted Aggregate, No. 8 31 TON $
8 Sidewalk Remove 63 SYS $
9 Geotextile, Type 1A 114 SYS $
10 4" Plain Concrete Sidewalk 63 SYS $
Total Amount of Quote Alternate No. 1 $
Total Amount of Base Quote and Alternate No. 1 $
Firm:
Address:
City/State/Zip: Telephone Number: ( )
Fax Number: ( )
By
(Signature)
(Printed Name of Person Signing)
QUOTE/PROPOSAL
CITY OF SOUTH BEND
PROJECT NAME East Race Sidewalk Repair (Under Colfax)
PROJECT NO. 117-130
QUOTES DUE November 24, 2020, before 9:00 a.m. local time
Version 3.3 [1/11/2019]
**SUBMIT 5 WORKING DAYS MINIMUM PRIOR TO PROJECT START DATE
Parking Lane Travel Lane Full Road Closure Alley
Submission Date: Applicant/Company:
Email Address:
Phone #:
Project STREET ADDRESS (eg: 110 W. Smith RD.):
Project Location (Block limits/Streets From and To):
**Requested Start & End Dates:Requested Start & End Times:
Contractor Performing Work:
On-Site Contact: Phone #:
Reason for Closure:
Affected Customers:ATTACH THE FOLLOWING ITEMS: 1. Traffic Control Plan 2.Detour Plan 3. Barricades, Signs, or Flashers Placement
ENGINEERING OFFICE USE ONLY:
Approved Approved as Noted Revise Not Approved
Comments: ____________________________________________________________________________
_________________________________________________________________________________________
City of South Bend/Engineering Division Authorized Signature Date:
SOUTH BEND,INDIANA 46601 TDD 574/ 235-5567
Reason for Closure:
City of South Bend Public Works
Engineering Division
227 W. Jefferson, County City Building 1316
South Bend, IN 46601-1830
PLAN YOUR START DATE ACCORDINGLY TO AVOID DELAYS
Complete 1 - 5 Incomplete submittals cannot be processed; All submittals require occupancy bond and insurance
(Refer to MUTCD for Traffic Control Device Requirements) See reverse for Checklist
Failure to use traffic control for traffic restrictions or closures will result in stop work orders and/or delay in permitting.
Office
Cell
Name:
Office
Cell
Excavation/Boring? > Requires Excavation Form Sidewalk? > Requires Sidewalk permit
New Approach? > Curb Cut application
1
2
3
4
5
Affected Customers:
~ Contractors are responsible for resolving safety issues and access concerns with affected customers ~
Phone: 574.235.9251
TRAFFIC CONTROL AND OCCUPANCY REQUEST
Sidewalk
THIS OCCUPANCY PERMIT REQUEST IS NON-TRANSFERABLE AND A SIGNATURE SUBJECTS THE NAMED CONTRACTOR/PERMITTEE
TO ALL APPLICABLE RULES, DUTIES AND OBLIGATIONS IMPOSED BY THE CITY OF SOUTH BEND MUNICIPAL CODE AND TO ALL
REGULATIONS IMPOSED BY THE SOUTH BEND BOARD OF PUBLIC WORKS.
Applicant Signature _______________________________ Date ________________
**Occupancy beyond 90 days requires completion of Long Term Occupancy Request Application.
Email: rowpermitsoffice@southbendin.gov
Treelawn
TRAFFIC CONTROL CHECKLIST
PURPOSE: SAFETY FOR MOTORISTS, BICYCLISTS, PEDESTRIANS, WORKERS, EMERGENCY
AND ENFORCEMENT PERSONNEL AND EQUIPMENT
•Submit Traffic Control with any Occupancy Request in the City of South Bend.
•Maps shall follow MUTCD Traffic Control Device guidelines, but do not submit
MUTCD examples as your traffic control.
INCLUDE THE FOLLOWING:
Street map showing CURRENT street status
~ Can show aerial or streets only
Street names
Striping and sidewalks
North Arrow
Location of Activity Area and placement of vehicles and equipment in
the work space
Location of manholes or other facilities within work space
Barricades, signs and/or flasher placement
Taper distance/Advanced warning signage
Traffic detour plan
Examples of simple traffic control:
North
North
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 11/16/2020
Name Zach Hurst Department DPW
BPW Date 11/24/2020 Phone Extension 3057
Review and Approval Required Prior to Submittal to Board
Diversity Compliance
and Inclusion Officer Officer Name
BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name East Race Sidewalk Repair
Project Number 117-130
Funding Source Curb & Sidewalk
Account No. PR-00005484
Amount
Terms of Contract Pay Item Contract
Purpose/Description Quote request to perform sidewalk repairs along the East Race, at Colfax
Avenue.
For Change Orders Only
Amount of Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: