HomeMy WebLinkAboutChange Order Nos. 3 & 4 - INDOT - Bendix Dr., Lathrop to Indiana Toll Road - Rieth-Riley Construction1316 COUNTY -CITY BUILDING 227 W. JEFFERSON BOULEVARD SOUTH BEND, INDIANA 46601-1830 CITY OF SOUTH BEND JAMES MUELLER, MAYOR BOARD OF PUBLIC WORKS November 10, 2020 Mr. Joshua McCormick Rieth-Riley Construction Co., Inc. 25200 State Road 23 South Bend, IN 46614 j mcc ormickgrieth-riley. com RE: Change Order Nos. 3 & 4 — Bendix Dr., Lathrop to Indiana Toll Road Project No. 114-065 Dear Mr. McCormick: PHoNE 574/235-9251 FAx 574/235-9171 The Board of Public Works, at its meeting held on November 10, 2020, approved Change Order No. 3, for an increase of $4,166.80 (the city pays 20% or $833.36); with an additional five (5) days, bringing the current contract amount to $4,096,097.03 and a new completion date of September 23, 2020. The Board of Public Works also approved Change Order No. 4 for an increase of four (4) days bringing the current completion date to September 27, 2020. Enclosed are copies of the Change Orders for your records. If you have any further questions regarding this matter, please call this office at (574) 235-9251. Sincerely, s/Linda M. Martin, Clerk Enclosure GARY A. GILOT ELIZABETH A. MARADIK THERESE J. DORAU JORDAN V. GATHERS JOSEPH R. MOLNAR Contract No:R -37497 Change Order No.: 003 INDIANA Department of Transportation Construction Change Order and Time Extension Summary Contract Information Contract No.: R -37497 Letting Date:09/11/2019 District:LAPORTE DISTRICT AE:Patterson, Patrick PE/S:Dietz, Don Change Order Information Change Order No.: 003 EWA: Y or Force Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: ERRORS & OMISSIONS, Construct Related Description: Extra Costs Associated with Plan Changes Original Contract Amount $ 4,089,000.00 Current Change Order Amount $ 4,166.80 Percent: 0.102 % Total Previous Approved Changes $ 2,930.23 Percent: 0.072 % Total Change To -Date $ 7,097.03 Percent: 0.174 % Modified Contract Amount $ 4,096,097.03 Time Extension Information Date Initiated 00/00/0000 Original Contract Time Time Element Description: Current Time Extension Previous Time Approved Revised Contract Time Date Completed 00/00/0000 Page: 1 Status:Draft SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) SS Days 0 SP Days 5 SP Days Value $ 0.00 SS Days by AE: DCE: SCE: DDCM: SS Days SP Days Value $ SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -37497 Change Order No.: 003 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority AE: DCE: SCE: * DDCM: ($ per Change Order) (-LE$250K-)(-LE$750K-)(--LE$2M--)(--GT$2M--) (Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days) Verbal Approval Required? Y / N If Y, Total Change To-Date>5%? Scope/Design Recommendation Required? Date Issued Y / N If Y , Copy to Program Budget Manager_ Y / N If Y, Referred to Project Manager(PM) Date to Date Returned Approval Authority Concurs with PM? Y / N If Y, Concurrence by Date If N,Resolution: Approved Disapproved Resolved by Date LPA Signatures Required? Y / N If Y, Date to LPA Date Returned FHWA Signatures Required? Y / N If Y, Date to FHWA Date Returned * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer Comments: Date Contract No:R -37497 Change Order No:003 INDIANA Department of Transportation Contract: R -37497 Project: 1400634 - State:1400634001-C4 Change Order Nbr: 003 Date:10/06/2020 Page: 3 Change Order Description: Extra Costs Associated with Plan Changes Reason Code: ERRORS & OMISSIONS, Construct Related CLN PCN PLN Item Code Unit Unit Price co oty Comment Amount Change 0125 1400634 0125 105-06807 LS 4,166.800 1.000 Item Description: ADDITIONAL Supplemental Descriptionl: Additional cost associaes with plan change. Supplemental Description2: Milestone Time Adjustment Milestone Nbr: 02 Amount:$ 4,166.80 Total Value for Change Order 003 = $ 4,166.80 Milestone Description: INTERMEDIATE COMPLETION DATE Original Completion dt: 09/1812020 Adj compl dt 09/23/2020 Adj No. of Days 5 Explanation: A time extension Is being granted because revision of the road forced a rescheduling of the subgrade treatment by 5 days. The area was completed and had to be regraded and casting readjusted as well. Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation This change order is for additional costs associated with the plan changes on Bandix Rd between Sugar Maple and Nimtz parkway. Upon initial completion of the excavation and grading of the proposed Bandix Rd, there are several conflicts with In the new alignment of Bandix that do not allow for the completon of the road as designed. Choice Light has a fiber optic line within the proposed road limits. There is also a handhole containing the fiber optid line as well as a street light foundation within the limits of the new roadway. A design change was needed and the road had to be regraded to meet the requirements of the design change. This change order Includes all of the associated costs of the contractor to make the neccessaty changes. Costs for construction engineering and grading are Included in this change order. Five additional days will be granted due to this change order. All Items deemed reasonable based on a review of the documents. Change Order Explanation for Specific Line Item ... «,,,,,,,,,,,,,,,,,,»,.,..... ,...... ....,..,....,.,.,,.,,,.,,,,,,«»,,..,«...... ,,... .,,.... ,..,...,«,«.,,... *..,,. It is the intent of the parties that this change order is full and complete compensation for the work describe above. Notification and consent to this change order is hereby acknowledged. Contractor: K1= Date: 7- o16��% Signed By: / ..«,.«,.,,,.„..........................»,....,......,.„„«......,,,,.........,,.....,...,,.».«,.,..,.,,,...,.,.,... NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Contract No:R -37497 INDIANA Change Order No:003 Department of Transportation ***R******kkk*kkk**k****k*********kk**k****k*k**k***kk***k*****k***R**R***R***kk*****R*k*********YRYR##*RRRItRRRYY#Y#R**YR#RR HOARD OF PUBLIC WORKS APPROVED FOR LOCAL PUBLIC AGENCY Gary A. 01,1, President Therese J. D— , Member -gzi�a,d-1- (I,/% -:11� Elizabeth A. Mmadik, Member Jmdan V. Gathers, Member ATTEST: tea ctrmnx Joseph K Molnar, Member Linda M. Marti¢, Clerk AA SUBMITTED FOR CONSIDERATION PETS Date: 10/06/2020 Page: 4 November 10, 2020 (DATE) (DATE) APPROVED FOR INDIANA DEPARTMENT OF TRANSPORTATION Approval Level Name of Approver Date Status CHANGE ORDER REQUEST FORM CONTRACT NO. R-37497 PROJECT DESCRIPTION (route / intersection / bridge no(s).) DATE OF SUBMISSION 5/5/2020 ROAD RECONSTRUCTION ON BENDIX DRIVE FROM .10 MILES NORTH OF LATHROP ROAD TO 1-80 CHANGE ORDER REQUEST SUMMARY Edge of Pavement Revision Costs. After Changes where made anew DESCRIPTION GPS model had to be made and sub grade needed to be regraded. PROPOSED SOLUTION SUMMARY NOTE: Upon request from Engineer, enter detailed description on page 2. ONSET DATE OF CHANGE 4/20/2020 PROPOSED COST AND TIME ADJUSTMENT COST COSTINCREASE/(DECREASE): $ 4,166.80 The cost adjustment shall include lump sum and estimated totaled unit -priced item costs. Attach a separate sheet of unit price items including item description, unit of measurement, estimated quantity and unit price. CHECK APPROPRIATE BOXES PER APPROPRIATE BASIS OF COST CHANGE: 111109.03 Altered Quantities ❑ 109.05(a) Agreed Price ❑ 109.05(b) Force Account ❑ 109.05.02 Delay Costs PROPOSED COST CHANGE INCLUDES: ❑ Labor ❑ Material ❑ Equipment ❑ Lease Agreement B Subcontractor TIME ADJUSTMENT INCREASE/(DECREASE): CHECK APPROPRIATE BOXES PER APPROPRIATE BASIS OF TIME CHANGE: (work days) 5 ❑ 108.08(a) Excusable, Non-Compensable ❑ 108.08(b) Excusable, Compensable NOTE: If Compensable, attach details based on 109.05.2(o) Allowable Delay Costs, SUPPLEMENTAL INFORMATION Additional information may be entered by the contractor. CHANGE ORDER ORIGINATION: DOCUMENTS AFFECTED: ❑ Contract Specifications (ref. doc name/no.) ❑ Contract Plans (ref. doc name/no.) A INDOT/LPA CHANGE ORDER AFFECTS DBE PARTICIPATION: W yes ❑ no (if yes, attach details) ❑ Contractor CHANGE ORDER REQUEST FORM CONTRACT NO. R-37497 UPON WRITTEN REQUEST FROM THE ENGINEER, PROVIDE ADDITIONAL DETAIL DATE RECEIVED REQUEST FOR SUBMITTAL DATE OF ADDITIONAL DETAIL ADDITIONAL DETAIL DETAILED DESCRIPTION / JUSTIFICATION: (Include location(s), actions of contractor, owner, and other stakeholders, key events and related couse(s), discoveries, discussions, meetings, and effect on the contract if no action is taken. Also include references to key documents attached or available to support this change order request.) PROPOSED SOLUTION —ADDITIONAL DETAILS: (Include proposed scope of work, means & methods, materials, equipment, utility relocation required, subcontracted scope and the effect on the contract schedule. Also include references to attached documents including, but not limited to, sketches, calculations, photos, material information, and submittals and meeting minutes.) SIGNATURES Contractor: Name: (print) Rieth-Riley Construction Co., Inc. Jeremy Jankoviak (signature) Date: 5/5/2020 Project Engineer/Supervisor: (signature is to acknowledge receipt of the document and does not signify agreement of the change order) Name: (print) (signature) NOTE: The Contractor and PE/s should retain a signed copy of this document for record. Date: Page 2 CHANGE ORDER REQUEST FORM CONTRACT NO. R-37497 ATTACHMENT: UNIT PRICE ITEMS DETAIL Attach or paste a unit price item detail. Page 3 Rieth-Riley Construction Co., Inc. MATERIAL 109.05 (b)(3) Monutactured Dewription Quantity Unit Unit Price Extonction $ S $ S 3 S $ S $ $ S S MATERIALS PURCHASED MATERIALS MANUFACTURED TOTAL: LINE(18)+(19) 12 % x LINE (20) GRAND TOTAL FOR MATERIALS. LINE (20) � (21) EQUIPMENT 109.05 (b)(4) $0.00 (18) $0.00 (19) $0.00 (20) $0.00 (21) $0.00 (22) F_quipmont8 CONTRACTOR OWNED EQUIPMENT FHWA HOURLY RATE HOURS EXTENSION $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0,00 $0.00 $0,00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Trucking - Striaght Time $0.00 Trucking . Over Time $0.00 Trucking. Douala Time D. TOTAL EQUIPMENT $0.00 (23) TOTAL TRUCKING - n-w (24) FUEL, LUBRICANTS AND TRANSPORTATION COSTS (25) TOTAL LINES (23) + (24) + (25) ,� (26) 12 % x LINE (26) $0.0 (27) GRAND TOTAL FOR EQUIPMENT: LINES (26)+ (27) n-W (28) SUBCONTRACTORS 109.05 (b)(6) TOTAL SUBCONTRACT WEEK ENDING $3,847.65 (29) 7 %x LINE (30) $269.34 (32) GRAND TOTAL FOR SUBCONTRACTORS: UNES (30) + (31) + (32) $4,116.99 (33) Irr.�c��rrv�c� c.�.r„nr�ir��rrrealf:rxlna�a TOTAL UNES (12). (17), (22), (28) b (33) $4,116.99 (34) 1.1 %OF BOND RATE BASED UPON LINE (34) $45.29 (35) 10 % x LINE (35) $4.53 (38) TOTAL EXTRA WORK LINES: (34) + (35) + (36) $4,166.80 137) Page 2 of 2 2010 Went Street— Mishawaka, In.46545 Phone (574)256 - 2467 Fax (574256 - 2473 Rieth Riley Construction May 4, 2020 25200 SR 23 South Bend, Indiana 46614 Attn: Mr. Jeremy Jankoviak Re: GPS Model Adjustment Jeremy, As you are aware there were a few issues discovered in relation to grading and utilities on phase 1 of R-37497 project. Designer issued an addendum to address issues resulting in modification of our GPS model and subgrade. Below please find C/O request for this said work, R&R Model Adjustment Cost $1,310.40 R&R Cost to Adjust Subgrade $2,537.25 Total C/O #1 $3,847.65 Thank you, Terry Opaczewski R&R Excavating JOB #4690-627-A02 • ' o000000-aoa Contract No:R -37497 Change Order No.: 004 INDIANA Department of Transportation Construction Change Order and Time Extension Summary Contract Information Contract No.: R -37497 Letting Date:09/11/2019 District:LAPORTE DISTRICT AE:Patterson, Patrick PE/S:Dietz, Don Change Order Information Change Order No.: 004 EWA: N or Force Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: CHANGED COND, Utility Related Description: Utility Delay Original Contract Amount Current Change Order Amount Total Previous Approved Changes Total Change To -Date Modified Contract Amount Time Extension Information Date Initiated 00/00/0000 Original Contract Time Time Element Description: Current Time Extension Previous Time Approved Revised Contract Time $ 4,089,000.00 $ 0.00 $ 2,930.23 $ 2,930.23 $ 4,091,930.23 Date Completed 00/00/0000 Percent: 0.000 % Percent: 0.072 % Percent: 0.072 % Page:1 Status:Draft SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) SS Days 0 SP Days 4 SP Days Value $ 0.00 SS Days by AE: DCE: SCE: DDCM: SS Days SP Days Value $ SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -37497 Change Order No.: 004 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority AE: DCE: SCE: * DDCM: ($ per Change Order) (- LE $ 250K-) (- LE $ 750K -) ( -- LE $ 2 M --) (-- GT $ 2 M -- ) (Days per Contract) ( 50 SS days ) ( 100 SS days) ( 200 SS Days) ( GT 200 SS days) Verbal Approval Required? Total Change To-Date>5%I Scope/Design Recommendation Required? Y / N If Y, by Date Issued Y / N If Y, Copy to Program Budget Manager Y / N If Y, Referred to Project Manager(PM) Date to PM Approval Authority Concurs with PM? Y / N If Y, Concurrence LPA Signatures Required? FHWA Signatures Required? If N,Resolution: Approved Resolved by. Y / N If Y. Date to LPA Date Returned Date Disapproved Date Date Returned Y / N If Y, Date to FHWA Date Returned * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer Comments: Date Contract No:R -37497 INDIANA Date:09/15/2020 Change Order No:004 Department of Transportation Page: 3 Contract: R -37497 Project: State:140063400LC4 Change Order Nbr. 004 Change Order Description: Utility Delay Reason Code: CHANGED COND, Utility Related CLN PCN PLN Item Code Unit Unit Price Co CRY Comment Amount Change Total Value for Change Order 004 = 6 0.00 Milestone Tim Adjustment Milestone Nbr: 02 Milestone Description: INTERMEDIATE COMPLETION DATE Original Completion dl: 09118f2020 Adj comp) dt 09/2212020 Ad) No. of Days 4 Explanation: An oxtonslon of the clalondar days Is being added to the Intermediate completion date due to a delay In the verification of a 12 Inch abandoned gas main on Bendlx Drive. Whereas, the Standard Specifications forthla contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation A time extension of 4 days is being glvon to the Intermediate completion date for the delay of verification of the vacated 12Inch existing gas main on Bondix Dr. The existing gas main was relocated prior to the contractor beginning construction. The main was encountered during the Installation of the storm sewer for phase II on Bondix. At the precon, NIPSCo staled they could be on alto within 24 hours to verify any encountered pipes, NIPSCo was notified on Monday morning July 0, 2020 at about 10 am. NIPSCo was not able to be on alto for verification until Wednesday July B, 2020 to confirm the goo main had been vacated. All work on the project was hafted until NIPSCo had confirmed the existing main had been vacated. A (inlay of 3 calendar days is the result. The Intermediate completion date Is being extended out 4 days to account for Sunday September 20th. No additional payment will be mode for this change order. Change Order Explanation for Specific Line Item HYf f/HYff IMiHR/YYi1YYHfY HfYHHiHftHY1YY W Y.15YHYY/Y/fYHYHYY.YRYIHYf YIR....RH.Yf HY VH.Y/YYYYHfIHHHHM41/fA it Is the Intent of the parties that this change order Is full and complote compenoatlon for the work doseribe above. Notification and con )t to th/ls change order Is hereby acknowledged. Contractor,_..�N��_�p signedBy:_�/...`/ .�__........ Dole,.— . . ..... w.IH..IYRRHR....IIIHVYRH..... H....WHIR..IIR.YH1H..... NIHfIHAYRHiIH IHYHRYIHHI/H4RHII NOTE: Other raciulred State and FNWA signatures will be obtained olactronically through the SlteManager system. Contract NOR -37497 INDIANA Change Order No:004 Department of Transportation •+wwwwwxrwtrwwxwxx+x+tttrtxkxktrtt#arkrx aitktxkktx#wtr###r+#tt#ik#ttr#+kRk###fi#fitk BOARD OF PUBLIC WORKS tfieiwfi#iwkrfiWfi#k#x##W#fi#Wfi#WWxx#kWkfi#Wfikx# APPROVED FOR LOCAL PUBLIC AGENCY Gary A. Gil,S President Therese J. D—a, Member Elizabeth A. Maradik, Member Jordan V. Gathers, Member ATTEST: 2ixdr cGfman Joseph R Molnar, Member Linda M. Martin, Clerk SUBMITTED FOR CONSIDERATION PE1S krtkrwr;trxwwkxfwwtwrwxwkwikxxwkwkt#wtkrtr#trwrktrxrrwrw+t+wrti#tktk+ixttsarrtk#wtr•+#t•#ttkt#rr+r#ktr #e##it#kk+t#r;;;r;krrw Date:0911512020 Page: 4 November 10, 2020 (DATE) (DATE) APPROVED FOR INDIANA DEPARTMENT OF TRANSPORTATION Approval Level Name of Approver Date Status -`HILEY CONSTRUCTION CO., In. 100% Quality • 100% Employee Owned • Over 100 Years 7/22/2020 Don Dietz Construction Engineer Lawson -Fisher associates P.C. Project: INDOT R-37497-A Road Reconstruction of Bendix Dr. Re: Delay for Utility Location Dear Mr. Dietz, In Phase II of construction we encountered an abandoned gas line on the east side of the road. This was discovered on Monday 7/6/20. We waited until late Wednesday 7/8/20 before it was verified that the line was abandoned. We are requesting 5 days added to the intermediate completion date/completion date of the project. Five days are requested, because regular (Non -Overtime) workdays were used under the delay. With the intermediate completion date being on a Friday. We will incur additional overtime cost if we work on Saturday and Sunday. We were delayed a Monday, Tuesday, and Wednesday of work and would like to gain a Monday, Tuesday, and Wednesday of work because of the Utility Delay. We are requesting the new completion date of September 23rd 2020. If you have any questions, please do not hesitate to reach out to us. Respectfully, RIETH-RILEY CONSTRUCTION CO., INC. Jeremy Jankoviak Estimator 4 u,,•1 5 Va d-."J v voo- P.D. Box 1775.25200 S.R. 23 - South Bend, IN 46634 !DK Phone: (574) 288-8321 , www.rieth-riley.com Y BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM Date October 20, 2020 Department Public Name Scott BPW Date October 27, 2020 Phone Extension 9245 Required Prior to Submittal to Board BPW Attorney ® Attorney Name Clara McDaniels Dept. Attorney ❑ Attorney Name Purchasing ❑ Michael Schmidt Check the Appropriate Item Type — Required. for All Submissions ❑ Professional Services Agreement ❑ Contract ❑ Proposal ❑ Open Market Contract ❑ Amendment/Addendum ❑ Special Purchase, QPA ❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet ❑ Quote Opening ❑ Quote Award ❑ Reject Bids/Quotes ❑ Proposal Opening ❑ C/O & PCA No. ❑ PCA ® Chg. Order, No. 4 ❑ Traffic Control ❑ Resolution n Other: n Ease./Encroach Information Company or Vendor Name Rieth-Riley Construction New Vendor MBE/WBE Contractor Project Name Project Number Funding Source Account No. Amount Terms of Contract ❑ Yes❑ If Yes, Approved by Purchasing ® No ❑ WBE Completed E-Verify Form Attached ❑❑ Yes No Bendix Dr., Lathrop to Indiana Toll Road 114-065 LRSA - Streets & Alleys 251-06-600-506-442001 4 days Unit Price Purpose/Description _Change Order No. 4 for the vacation of the 12 in existing gas main on Bendix Dr. Additional 4 days to intermediate completion date. For Change Orders Only Amount of ❑ Increase $ ❑ Decrease ($ ) Previous Amount $ Increase Current Percent of Change: Decrease ( %) New Amount $ Increase Total Percent of Change: Decrease (%) Time Extension Amount: 4 days New Intermediate Completion Date: 9/27/2020 BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM Date October 20, 2020 Department Public Name Scott BPW Date November 10, 2020 Phone Extension 9245 Required Prior to Submittal to Board BPW Attorney ® Attorney Name Clara McDaniels Dept. Attorney ❑ Attorney Name Purchasing ❑ Michael Schmidt Check the Appropriate Item Type — Required. for All Submissions ❑ Professional Services Agreement ❑ Contract ❑ Proposal ❑ Open Market Contract ❑ Amendment/Addendum ❑ Special Purchase, QPA ❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet ❑ Quote Opening ❑ Quote Award ❑ Reject Bids/Quotes ❑ Proposal Opening ❑ C/O & PCA No. ❑ PCA ® Chg. Order, No. 3 ❑ Traffic Control ❑ Resolution n Other: n Ease./Encroach Information Company or Vendor Name Rieth-Riley Construction New Vendor MBE/WBE Contractor Project Name Project Number Funding Source Account No. Amount Terms of Contract Purpose/Description ❑ Yes❑ If Yes, Approved by Purchasing ® No ❑ WBE Completed E-Verify Form Attached ❑❑ Yes No Bendix Dr., Lathrop to Indiana Toll Road 114-065 LRSA - Streets & Alleys 251-06-600-506-442001 $833.36 (20% of $4,166.80) Unit Price Additional costs for the excavation and grading at Bendix between Sugar Maple and Nimtz Parkway due to fiber optic lines. For Change Orders Only Amount of ❑ Increase $ 4,166.8 ❑ Decrease ($ ) Previous Amount Current Percent of Change: New Amount Total Percent of Change: Time Extension Amount: New Intermediate Completion Date: $ 4,091,930.23 INDOT TOAL Increase 0.102% Decrease % $ 4,096,097.03 Increase 0.174% Decrease °/( o) 5 days 9/23/2020