October 27, 2020
Mr. Jamie Brown
Asphalt Restoration Services, Inc.
PO Box 2484
South Bend, IN 46680
arsllc@comcast.net
RE: Rescind Quotation Award – Notre Dame Triangle Alley Paving
Project No. 119-057R
Dear Mr. Brown:
The Board of Public Works, at its meeting held on October 27, 2020, approved the request to
rescind the award of the above referenced quotation due to your inability to perform due to the
halt of asphalt production in September.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
s/Linda M. Martin, Clerk
What we do today makes a difference!
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS DIVISION OF ENGINEERING
TO: Linda M. Martin, Clerk
Board of Public Works
FROM: Scott Kreeger, Project Engineer
SUBJECT: Rescind Line Contract with ARS
Project Name: Notre Dame Triangle Alley Paving
Project No. 119-057R
DATE: October 22, 2020
On September 22, 2020, the Board of Public Works opened and read bids for the above project.
The bids were reviewed and Asphalt Restoration Services (ARS) was awarded the contract as
the lowest responsive/responsible contractor during the October 13, 2020 Board of Public Works (BPW) meeting. During the October 16th Pre-Construction meeting, the City was informed by ARS the production of the asphalt emulsion mix stopped after September due to the low temperatures. On October 21st, the City extended the following three options to ARS: proceed as quoted with
the October 31st completion date, receive a project extension of November 14, 2020, or reject the
contract award. On October 22, 2020, ARS selected to reject the contract award.
The quoters ranked as follows:
Quoter Base Bid Amount Alternate #1
Amount
1. Walsh & Kelly, Inc.$39,475 NO BID
2.Asphalt Restoration Services NO BID $21,250.00
3. Rieth-Riley Construction Co., Inc.$39,847 $9,285.50*
*Note: Alternate #1, Rieth-Riley Construction Co., Inc. provided unit pricing for materials and
type of work different from the bid specifications. The product the bidder listed is not an
equivalent to the desired work and was therefore not accepted as a bid alternate.
In accordance with the election of the awarded bidder, Engineering requests rescinding the
award to ARS and awarding to the next lowest responsive/responsible bidder, Walsh & Kelly,
Inc., for the base quote amount of $39,475. Sufficient funds have been appropriated from Street
Maintenance (266-06-602-436008).
Pursuant to IC 36-1-12-18 (c), in cases of emergencies, a change order may be issued prior to
commencement of the work. The lost time between the period of award and the original
contractor’s election to reject the bid award; the need for the work to be completed prior to the
What we do today makes a difference!
onset of adverse weather conditions; and due to the limited timing of 2020 project funding,
Engineering requests the Board to approve an emergency change order providing a 14-day time
period for completion of the work to the next lowest responsive/ responsible bidder, Walsh &
Kelly (the Board minutes memorializing the nature of the emergency). The contractor will
receive the same number of days for completion of the work as was included in the original
solicitation. The project completion date will be November 14, 2020.
Please call with your questions (ext. 5998).
Enc. Quote Tabulation and October 21, 2020 E-mail Conversation
QUOTE TABULATIONNotre Dame Triangle Alley PavingProject No: 119‐057RFor Quotes Due: September 22, 2020Item No. Line Item Quantity UnitUnit Price Cost Unit Price Cost Unit Price Cost Unit Price Cost1Milling, Up to 1.5"1,150SYD$1.35 $1,552.50 No Bid $11.00 $12,650.00 $9.50 $10,925.002HMA Surface, 9.5 mm – Type B166TONS$70.00 $11,620.00 No Bid $127.00 $21,082.00 $150.00 $24,900.003HMA for Patching10SYD$20.00 $200.00 No Bid $250.00 $2,500.00 $175.00 $1,750.004Tack Coat1TONS$10.00 $10.00 No Bid $465.00 $465.00 $150.00 $150.005Adjust Inlet to Grade7EA$350.00 $2,450.00 No Bid $450.00 $3,150.00 $250.00 $1,750.00Base Quote Total$15,832.50 $39,847.00 $39,475.00Item No. Line Item Quantity UnitUnit Price Cost Unit Price Cost Unit Price Cost Unit Price Cost1Patch, Infrared, 5 ft. by 7 ft. by 2 in. depth30EA$185.00 $5,550.00 $200.00 $6,000.00 $182.00 $5,460.00 No Bid2Cracks in Asphalt Pavement, Fill430LFT$0.65 $279.50 $1.00 $430.00 $2.85 $1,225.50 No Bid3Asphalt Emulsion2,600SYD$5.00 $13,000.00 $5.70 $14,820.00 $1.00 $2,600.00 No BidAlternate #1 Total$18,829.50 $21,250.00 $9,285.50I hereby certify that the above truly and accurately represents quotes received for this project on September 22, 2020Scott Kreeger, Engineer IAsphalt Restoration ServicesWalsh & Kelly, Inc.Non-Collusion AffadavitYYEngineer's EstimateBase QuoteAlternate #1Engineer's EstimateAsphalt Restoration ServicesWalsh & Kelly, Inc.Rieth‐Riley Construction Co., Inc.Rieth‐Riley Construction Co., Inc.*YNote*: On Alternate #1, Rieth‐Riley Construction provided unit pricing for products differing from the quote specifications.S:\Public Works\Projects\Projects by Year\2019 Projects\119‐057R Notre Dame Triangle Alley Paving (Rebid)\1 ‐ Admin\1 ‐ BPW Documents\ND_Alley Tab
From:Ars
To:Scott Kreeger
Subject:Re: ARS Contract Agreement - Notre Dame Triangle Alley Paving
Date:Wednesday, October 21, 2020 10:05:31 PM
I can not do what your asking in the alluded time. The temperatures for liquid road need to be
no lower the 50 degrees at night and around 80 degrees during the day.
Asphalt Restoration Services very much appreciates the opportunity, but we have no other
choice but to rescind from this contract.
We look forward to future projects with the city of South Bend.
Thank you again and I’m sorry we couldn’t be of service at this time.
Thank you,
Jamie Brown
On Oct 21, 2020, at 7:24 PM, Scott Kreeger <skreeger@southbendin.gov> wrote:
Jamie,
During the Notre Dame Triangle Alley Paving Pre-Construction meeting, it was brought
to our attention ARS would not be able to meet the project completion date of October
31, 2020. It was the City’s intention to complete this project as soon as possible and
before the new year as promised to the local community. After further review of the
contract agreement, the City sees three options for ARS in regards to the awarded
contract:
1. Proceed as quoted. For any work incomplete after October 31, 2020, $500 of
liquidated damages will be assess for each calendar day until the work is
completed.
2. The City can extend the contract completion date to November 14, 2020 in
order to provide ARS additional days to complete the entirety of the project.
Liquidated damages will be assessed after this date for any work incomplete.
3. ARS rescinds from the awarded contract agreement. No damages will be
assessed.
Please feel free to reach out to me via e-mail with any questions.
Regards,
Scott Kreeger
Project Engineer
(574) 235-9245
skreeger@southbendin.gov
City of South Bend
227 W. Jefferson Blvd., Ste. 1316
South Bend, IN 46601
IMPORTANT NOTICE! This E-Mail transmission and any accompanying
attachments may contain confidential information intended only for the use of the
individual or entity named above. Any dissemination, distribution, copying or
action taken in reliance on the contents of this E-Mail by anyone other than the
intended recipient is strictly prohibited and is not intended to, in anyway, waive
privilege or confidentiality. If you have received this E-Mail in error please
immediately delete it and notify sender at the above E-Mail address. Please note
that incoming e-mails are not routinely screened for response deadlines, and as
such, please notify the sender separately by fax of any message containing
deadlines. In addition, E-Mail information cannot be guaranteed to be secure or
error-free as information could be intercepted, corrupted, lost, destroyed, arrive
late or incomplete, or contain virus. Therefore, the sender does not accept liability
for any errors or omissions in the contents of this message which arise as a
consequence of E-Mail transmission. If verification is required, please request a
hard-copy version.
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 10/22/2020
Name Scott Kreeger
Department Public
Works
BPW Date 10/27/2020 Phone Extension 9245
Required Prior to Submittal to Board
BPW Attorney Attorney Name Clara McDaniels
Dept. Attorney Attorney Name
Purchasing Michael Schmidt
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Rescind Contract Ease./Encroach
Required Information
Company or Vendor Name Asphalt Restoration Services
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Notre Dame Triangle Alley Paving
Project Number 119-057R
Funding Source Street Maintenance
Account No. 266-06-602-436008
Amount
Terms of Contract Unit Price
Purpose/Description ______Rescind quote agreement___________________________________
For Change Orders Only
Amount of Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: