HomeMy WebLinkAboutOpen Market Contract - Materials and Installation for Pinhook Water Treatment Plant Exhaust Fans – Ideal Consolidated, Inc.1316 COUNTY -CITY BUILDING
227 W.JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
October 13, 2020
Mr. Fred Mohler
Ideal Consolidated, Inc.
806 W. Sample St.
South Bend, IN 46601
L�. idealcotiso]idatcd.cot-n
RE: Open Market Contract
Dear Mr. Mohler:
PHONE 574/235-9251
FAx 574/ 235-9171
The Board of Public Works, at its meeting held on October 13, 2020, approved the open
market contract for the Pinhook Water Treatment Plant exhaust fans material and installation in
the amount of $27,000.
Enclosed please find a copy of the contract for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
s/Linda M. Martin, Clerk
Enclosure
GARY A. GILOT ELIZABETH A. MARADIK THERESE J. DORAU JORDAN V. GATHERS JOSEPH R. MOLNAR
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Linda M. Martin, Clerk
Board of Public Works
FROM: Finnian Cavanaugh, Project Engineer
SUBJECT: Award Project No. 119-003A
Pinhook WTP Exhaust Fans
DATE: September 28, 2020
On September 8, 2020 the Board of Public Works did not receive quotes for the above project.
Per the Board's recommendation, Engineering reached out to contractors again for an open -
market quote. One response was received on September 22, and I have reviewed it as correct.
The quote ranked as follows:
Quoter
Total Quote
Amount
1. Ideal Consolidated, Inc.
$27,000
I recommend award of a contract for Pinhook WTP Exhaust Fans to the lowest responsive /
responsible quoter, Ideal Consolidated, Inc. in the amount of $27,000.
Sufficient funds have been appropriated from the Water Works Capital fund, 622-06-604-620-
442005--PROJ00000065 as part of project 119-003 Pinhook Water Treatment Plant
Improvements.
Please email with your questions ( y n ou h�Ibendin,,.q yJ or call (5961).
Enc. Quote Tabulation
BOARD OP MIB1.1C WORKS
`fi.K",),_�JJtr
�.
Gar} A. OilAAot, Presi&,nnt
Therew J. Doran, Member
rt _
Nizabetb A. Maradik, Member
J km V. Gath Member
it IHST:
nnrr�r, ctiurnir
_ _
.Joseph R Molnar, Member
Linda M. Martin, Clerk
QUOTE TABULATION
Pin hook WTP Exhaust Fans
119-003A
0
r _
Pinhook WiP Exhaust Fans
Engineer's Estimate
Ideal Consolidated, Inc.
Item No.
Line Item
Quantity
Unit
Unit Price
Cost
Unit Price
Cost
1
Maintenance of Traffic
1
LS
$26,500.00
$26,500.00
$27,000.00
$27,000.00
Total
$26,500.00
$27,000.00
Non -Collusion Affadavit Y
I hereby certify that the above truly and accurately represents bids received for this project on September 22, 2020
Name, Title
5'.\Public Wori:s\Projects\Projects by Ye \2019 Projects\119— Pinhook Waterireatm Ni Improvements\I-Ad—Al BPW Documents\Exhaust Fans\Quote Tabulation OMC 119-003A
6SpUTH 8��d
IZ
SCOPE OF WORK x�PEACE
CITY OF SOUTH BEND
1865
PROJECT NAME: Pinhook Park WTP Improvements — Exhaust Fans
PROJECT NO. 119-003A
QUOTES DUE September 22nd, 2020 at 9:30am local time
Open -market electronic quotes should be submitted to
feveneu c�;:v
PROJECT DESCRIPTION
A. The project includes the furnishing of all equipment, material, insurance, and labor for the complete
installation of two (2) new exhaust fans at the Pinhook Water Treatment Plant within the City of
South Bend, IN.
II. PREVAILING SPECIFCIATIONS AND CONSTRUCTION STANDARDS AND SPECIFICATIONS
A. The City of South Bend's PREVAILING SPECIFICATIONS, most recent version, and
CONSTRUCTION STANDARDS AND SPECIFICATIONS, most recent version, are to be used on this
project.
B. Each Quote provider is specifically instructed to become completely familiar with the most recent
version of the PREVAILING SPECIFICATIONS and the CONSTRUCTION STANDARDS AND
SPECIFICATIONS prior to submitting a quote.
C. Wherever the PREVAILING SPECIFICATIONS refer to "State Specifications," it shall mean the 2020
INDOT Standard Specifications for the letting effective after September 1, 2019.
D. These SPECIAL PROVISIONS will list only "Additions" or "Deletions" to the PREVAILING
SPECIFICATIONS and are to be used only in conjunction with the PREVAILING SPECIFICATIONS.
E. In the event of conflict between the SPECIAL PROVISIONS and the PREVAILING SPECIFICATIONS,
the SPECIAL PROVISIONS will govern.
III. TERM "OR EQUAL"
A. Prevailing Specifications: None
B. Additions
1. Where the term "or equal" is used in these specifications, the Quote provider deviating from
specified item shall file with his/her/its Quote a letter fully explaining and justifying his/her/its
proposed article or equal. The City of South Bend shall be the sole judge in determining if the "or
equal" offered meets the specification.
IV. TAX EXEMPT
A. Prevailing Specifications: None
B. Additions
1. Materials and properties purchased under contract with the Owner that becomes a permanent part
of the structure or facilities constructed are not subject to the Indiana Gross Retail Tax (Sales Tax).
The exemption number will be furnished to the Contractor upon award.
V. INDEMNIFICATION
A. Prevailing Specifications: None
B. Additions
1. Contractor agrees to indemnify, defend and hold harmless the City of South Bend, its agents,
officers and employees, from all costs, losses, claims and suits, including court costs, attorney fees,
and other expenses, arising from or out of the negligent performance of this Contract by Contractor,
Version 2/14/2020 Page - 1 Public Works Quote
or because of arising out of any defect in the goods, materials or equipment supplied by the Quote
provider.
VI. INSURANCE
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 103
B. Additions:
All Contractors and subcontractors doing business with the City of South Bend shall present a
Certificate of Insurance showing coverage in the following minimum amount:
a. General Liability: Premises -Completed Operations or Products, Bodily Injury and Property
Damage Combined Single Limit - $5,000,000.
b. There shall be no exclusion for explosion, collapse or underground hazard.
c. Workmen's Compensation: Statutory State of Indiana Employer's Liability - $100,000.
d. Auto Liability: Bodily Injury and Property Damage Combined Single limit - $1,000,000.
e. The City of South Bend shall be named as additional insured on the Certificate of Insurance.
VII. CONTROL OF WORK
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 105
B. Additions:
1. The complete responsibility for this project lies with the Director of Public Works of the City of South
Bend, Indiana acting through his authorized representatives.
2. Construction Engineering - The Contractor shall provide all the necessary, qualified personnel,
equipment and supplies to perform all work required under this item. There will be no direct payment
for this item.
3. The contractor is responsible to maintain the site which includes but is not limited to; dust control,
site security, erosion control, and protecting adjacent properties.
4. Work hours for the Project shall be from 7:00 a.m. through 6:00 p.m., Monday through Friday. No
work shall be permitted on weekends, Holidays, or after hours unless approved by the City of South
Bend Department of Public Works.
VIII. LEGAL RELATIONS
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 107
B. Additions:
1. The Owner, where mentioned in these documents, is the City of South Bend. The Engineer, where
mentioned in these documents, is the City of South Bend Department of Public Works, Division of
Engineering.
2. The Contractor shall apply for and obtain any and all required permits for the work from local, state,
and federal agencies and shall comply with permit requirements, including the St. Joseph County
/ City of South Bend Building Department.
3. If the Contractor awarded this contract is not a resident of Indiana, within thirty days, the Contractor
shall provide the Owner with proof that the Contractor is duly licensed, qualified and registered with
the Secretary of State of Indiana to engage in business within the State of Indiana.
4. The Contractor shall comply with all provisions of Indiana Code 5-16-13, as amended. The Owner
reserves the right to immediately terminate the public work project awarded should the Contractor
be found to be in violation of any provision of Indiana Code 5-16-13 and such violation shall result
in the forfeiture of Contractor's performance bond to the Owner.
IX. PROSECUTION AND PROGRESS
A. Prevailing Specifications: 2020, INDOT Standard Specifications Sec. 108
B. Additions:
Version 2/14/2020 Page - 2 Public Works Quote
1. The project will have a completion date of December 31st, 2020. The contract time will start when
the Notice to Proceed is delivered and signed.
2. The City, Engineer, and Contractor will hold a pre -construction meeting following award of the
contract. The date of the Notice to Proceed will be agreed at that meeting.
3. Contractor shall provide a schedule to the Owner prior to beginning any work on the site.
X. CHANGE OF CONTRACT TIME
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 108
B. Additions
1. The Contract Time may only be changed by Change Order. Any Claim for an extension in the
Contract Time shall be based on written notice delivered to the Department of Public Works within
seven (7) calendar days of the occurrence of the event giving rise to the claim. Notice of the extent
of the claim with supporting data shall be delivered within fourteen (14) calendar days after such
occurrence unless an official of the Public Works Department allows an additional period of time to
ascertain more accurate data. The Contract Time will be extended in an amount equal to time lost
to delays beyond the control of the Contractor if a claim is made in accordance with this provision.
Such delays shall include acts of neglect by the Public Works employees, or to fires, flood, labor
disputes, epidemics, abnormal weather conditions, governmental procedures, or acts of God.
2. Unless otherwise provided, the Contract time is based upon normal weather conditions. An
extension is granted for weather conditions significantly more severe than normal if the Contractor
demonstrates to the satisfaction of the City that the delay in the progress of the work was due to
such weather. The basis to define normal weather with be the data compiled by the United States
Department of Commerce, National Oceanic and Atmospheric Administration (NOAA).
3. No extension of time will be granted if the Contractor, by his/her/its own action or inaction, including
fault or negligence of Contractor's subcontractors, caused the delay, or for which any remedies are
provided under any other provision of this agreement.
4. The grant of an extension of time under this Section in no way constitutes a waiver by the City of
any rights or remedies existing under this contract at law or in equity.
XI. DEFAULT AND TERMINATION
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 108
B. Additions:
1. Events of Default shall include Contractor's failure to perform any of its obligations under this
contract including failure to commence work at the time specified, failure to perform the work in
accordance with these specifications, unauthorized discontinuation of the work, failure to carry out
the work in a manner acceptable to the City, failure to observe Federal, State, or local laws or
regulations, and failure to comply with any other term of this contract.
2. If an Event of Default occurs, the City shall provide Contractor written notice and may permit
Contractor ten (10) calendar days after the date of the notice to cure the default. If the default is
not cured within the ten (10) day cure period, the City may at any time thereafter terminate this
contract in which case the termination shall be final and effective.
3. Upon an Event of Default, the City may invoke the following remedies in addition to those remedies
provided under separate provisions of this contract, the right of set-off against any payments due
or to become due to the Contractor against the retainage, the right to take over and complete the
Work. If the City notifies Contractor that City is invoking its right to complete the Work, all rights that
the Contractor has in order under Contractor's subcontracts are assigned to the City, subject to the
City's right to take assignment of all or only selected subcontracts at the City's discretion. The sole
obligation accepted by the City under such subcontracts is to pay for Work satisfactorily performed
after the date of the assignment. In the event a conditional assignment has not been executed, the
Contractor shall execute or cause to be executed any assignment, agreement, or other document
that may be necessary in the sole opinion of legal counsel to the City's Board of Public Works to
evidence compliance with this provision. The Contractor shall promptly deliver such documents
upon the City's request. In the case of such assignment, unless otherwise agreed in writing, The
Contractor remains liability to subcontractors for any payment already involved, and for any claim,
suit or cause of action based upon or resulting from any error, omission, negligence or other breach
Version 2/14/2020 Page - 3 Public Works Quote
of contract by the Contractor, its officers, employees, or agents arising prior to the date of
assignment to the City.
XII. LIQUIDATED DAMAGES
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 108
B. Additions:
1. The contractor shall proceed with the work at such rate of progress to insure full completion within
the Contract Time. It is expressly understood and agreed, by and between the Contractor and the
Owner, that the Contract Time for completion of the work described herein is a reasonable time,
taking into consideration the average climatic and economic conditions and other factors prevailing
in the locality of the work, and excludes the time for unavoidable delays which were beyond the
control and without the fault of the Contractor.
2. If the Contractor shall fail to complete the work within the Contract Time, or extension of time
granted by the Owner, then the Contractor will pay to the Owner the amount for liquidated damages
a sum of five hundred dollars ($500.00) for each calendar day that the Contractor shall remain in
default after the time of completion stipulated in the Contract Documents.
3. The Contractor shall not be charged with liquidated damages or any excess cost when the delay
in completion of the work is due to the following and the Contractor has promptly given written
notice of such delay to the Owner and Engineer/Architect.
a. To any preference, priority, or allocation order duly issued by the Owner.
b. To unforeseeable causes beyond the control and without the fault or negligence of the
Contractor, including but not restricted to acts of God, acts of public enemy, acts of the Owner,
acts of another Contractor in the performance of a Contract with the Owner, fires, floods,
epidemics, quarantine restrictions, strikes, freight embargoes, and abnormal and
unforeseeable weather.
XIII. RETAINAGE AND FINAL PAYMENT
A. Prevailing Specifications: 2020, INDOT Standard Specifications Section 109
B. Additions:
1. Payments will be made every thirty (30) calendar days
2. Consistent with provisions of IC 36-1-12-14, the Board of Public Works shall retain a percentage of
payments throughout the duration of the project.
3. Before final payment and retainage are released the Contractor must satisfy the following:
a. All parts and labor meet requirements stated in the specifications.
b. Provide copies of test reports or cut sheets on all materials supplied.
c. Provide As -Built drawings in accordance with the City of South Bend Prevailing Specifications
for Public Works.
d. One (1) copy of the City of South Bend Completion Affidavit and one (1) copy of a Final Waiver
of Lien.
XIV. WARRANTY
A. Prevailing Specifications: None
B. Additions
1. All Parts shall include the following:
a. Performance specifications
b. Bill of Materials
c. Warranties on all parts
d. Installation and safety requirements
Version 2/14/2020 Page - 4 Public Works Quote
XV. OTHER UTILITIES
A. Prevailing Specifications: None
B. Additions:
1. The Contractor shall verify the locations of all utilities by contacting Indiana811 by calling 811 (in
Indiana) or 1-800-382-5544 (outside of Indiana), or via wwwuw,i,nC"I ai,n��„a�,;;�;;�;;oi,r,g, at least two (2)
working days, not counting Saturdays, Sundays or federal and state holidays before proceeding
with construction. It shall also be the Contractor's responsibility to contact any other utility that is
not contacted by Indiana811 and verify the utility locations.
2. The Contractor shall be responsible for working with the other utilities, i.e., gas electric, telephone,
etc. in order to assure that all utilities that need to be replaced or relocated can be done with a
minimum disturbance to service. The Contractor shall also be responsible for coordinating
schedules with the various utilities such that they can proceed with their relocation work as
efficiently as possible.
3. If the odor of natural gas is detected in a work area at any time during the course of work, the
Contractor shall immediately notify NIPSCO at 1-800-634-3524. The Contractor shall also
immediately notify the residents of adjacent properties. The Contractor shall advise the residents
to evacuate their homes immediately if the odor is present within the dwelling.
4. Restoration of sprinkler systems damaged by the Contractor's operations shall be repaired by the
Contractor at no additional cost to the City or the Owner of the system.
XVI. DESCRIPTION OF WORK
A. Prevailing Specifications: None
B. Additions
1. Work to be performed shall include furnishing all equipment, material, insurance, services and
labor for complete installation of two (2) new exhaust fans at the Pinhook Water Treatment
Plant within the City of South Bend.
2. The Contractor shall preserve and protect all surrounding property, structures, tenants, visitors and
their property from damage caused by the Contractor's operations.
3. To schedule a visit to the project location at 2801 Riverside Dr., 46616, contact Bradley
VanOosterum, Manager of Operations, at (574) 235-5670 or bvanoost@southbendin.gov.
XVII. EXHAUST FANS
A. Prevailing Specifications: None
B. Additions
1. The Contractor shall supply and install two (2) 2500cfm wall -mounted exhaust fans at the Pinhook
Water Treatment Plant. One (1) fan shall be installed on the east side of the building, and the other
shall be installed on the west side of the building as shown in the Quote Attachment.
2. The Contractor shall cut two (2) wall penetrations measuring approximately 30"x30" — one (1) for
each exhaust fan. Exterior bricks, where possible, shall be saved and stored at the treatment plant
for future reuse.
3. The interior side of the fan shall be connected to down -facing elbows.
4. The Contractor shall provide and install motor starters for both fans, each operated by timers and
switches just outside of the water treatment rooms.
5. The Contractor shall install electric to both exhaust fans, using Schedule 80 PVC raceway and non-
corrosive supports, junction boxes, and flexible connections.
6. Upon installation, the Contractor shall start up and verify that the system is operational.
XVIII. ATTACHMENTS
A. Prevailing Specifications: City of South Bend CONSTRUCTION STANDARDS AND SPECIFICATIONS
B. Additions:
1. The Quote Attachment consist of four (4) photographs showing installation locations.
2. The CONTRACTOR is responsible for estimating dimensions and quantities of materials.
Version 2/14/2020 Page - 5 Public Works Quote
3. In the event that the Special Provisions and the attachments conflict, the Special Provisions shall
govern.
Version 2/14/2020 Page - 6 Public Works Quote
, oTx aE��
pip
CITY OF SOUTH BEND INDIANA
CONTRACTOR'S QUOTE FOR PUBLIC WORK
PROJECT NAME:
PROJECT NO.
Pinhook Park WTP Improvements — Exhaust Fans
119-003A
QUOTES DUE September 22nd, 2020 at 9:30am local time
Open -market electronic quotes should be submitted to
fcavanau&southbendin.gov
(Must be completed for all quotes. Please type or print)
Date: ` 9/22/2020 Firm: Ideal Consolidated, Inc.
Address: 806 West Sample Street
City/State/Zip: South Bend, IN 46601 Telephone Number: ( 574 ) 282-1228
Agent of Bidder (if Applicable):
Pursuant to notices given, the undersigned offers to furnish labor and/or material necessary to complete the
public works project of:
119-003A Pinhook Park WTP Improvements - Exhaust Fans
the City of South Bend, Indiana, in accordance with plans and specifications prepared by:
The City of South Bend, Department of Public Works, Division of Engineering
and dated September 15th, 2020 for the sum of (enter the Total Quote as shown on the Proposal)
Twenty seven thousand & 00/100 (s 27,000.00 )
(Enter Sum of Total Quote plus Alternates shown on Proposal) (Numerical)
If alternative quotes apply, the undersigned submits a proposal for each in accordance with the notice. Any
addendums attached will be specifically referenced at the applicable page.
If additional units of material included in the contract are needed, the cost of units must be the same as that shown
in the original contract if accepted by the City of South Bend. If the quo is to be awarded on a unit basis, the
itemization of the units shall be shown on a separate attachmen
By
(Signature)
Tim Stuver, Vice President
(Printed Name of Person Signing)
ACCEPTANCE
The above quote is accepted this 13th. day of October, 20 20
Subject to the following conditions:
BOARD OF M �RLJCWORKS
0.- A. c ior:.3 —ids t zb —,e J. n i. Mmnbcr —
tt 1- V-.a-
I7 iabclb .1 M adik, Mc bor Jo,dun V. C tl ,, Me ber
r.irrAr, oPT xi,
Joseph R. Mole Member— —
Linden M. Martin, Clerk
Version 2/14/2020 Page - 7 Public Works Quote
When the prospective Contractor is unable to certify to any of the statements below, it shall attach an explanation to
this Affidavit.
CONTRACTOR'S NON -COLLUSION AND NON -DEBARMENT AFFIDAVIT,
CERTIFICATION REGARDING INVESTMENT WITH IRAN, EMPLOYMENT ELIGIBILITY
VERIFICATION, NON-DISCRIMINATION COMMITMENT AND CERTIFICATION OF USE
OF UNITED STATES STEEL PRODUCTS OR FOUNDRY PRODUCTS
(Must be completed for all quotes and bids. Please type or print)
STATE OF Indiana )
) SS:
St. Joseph COUNTY )
The undersigned Contractor, being duly sworn upon his/her/its oath, affirms under the penalties of perjury that:
1. Contractor has not, nor has any other member, representative, or agent of the firm,
company, corporation or partnership represented by him, entered into any combination, collusion
or agreement with any person relative to the price to be bid by anyone at such letting nor to prevent
any person from bidding nor to induce anyone to refrain from bidding, and that this bid is made
without reference to any other bid and without any agreement, understanding or combination with
any other person in reference to such bidding. Contractor further says that no person or persons,
firms, or corporation has, have or will receive directly or indirectly, any rebate, fee, gift,
commission or thing of value on account of such sale; and
2. Contractor certifies by submission of this proposal that neither contractor nor any of its
principals are presently debarred, suspended, proposed for debarment, declared ineligible, or
voluntarily excluded from participation in this transaction by any Federal department or agency;
and
3. Contractor has not, nor has any successor to, nor an affiliate of, Contractor, engaged in investment
activities in Iran.
For purposes of this Certification, "Iran" means the government of Iran and any agency or
instrumentality of Iran, or as otherwise defined at Ind. Code § 5-22-16.5-5, as amended from
time -to -time.
b. As provided by Ind. Code § 5-22-16.5-8, as amended from time -to -time, a Contractor is
engaged in investment activities in Iran if either:
i. Contractor, its successor or its affiliate, provides goods or services of twenty million
dollars ($20,000,000) or more in value in the energy sector of Iran; or
ii. Contractor, its successor or its affiliate, is a financial institution that extends twenty
million dollars ($20,000,000) or more in credit to another person for forty-five (45)
days or more, if that person will (1) use the credit to provides goods and services in
the energy sector in Iran; and (ii) at the time the financial institution extends credit, is
a person identified on list published by the Indiana Department of Administration.
4. Contractor does not knowingly employ or contract with an unauthorized alien, nor retain
any employee or contract with a person that the Contractor subsequently learns is an unauthorized
Version 2/14/2020 Page - 8 Public Works Quote
alien. Contractor agrees that he/she/it shall enroll in and verify the work eligibility status of all of
Contractor's newly hired employees through the E-Verify Program as defined by I.C. 22-5-1.7-3.
Contractor's documentation of enrollment and participation in the E-Verify Program is included
and attached as part of this bid/quote; and
5. Contractor shall require his/her/its subcontractors performing work under this public
contract to certify that the subcontractors do not knowingly employ or contract with an
unauthorized alien, nor retain any employee or contract with a person that the subcontractor
subsequently learns is an unauthorized alien, and that the subcontractor has enrolled in and is
participating in the E-Verify Program. The Contractor agrees to maintain this certification
throughout the term of the contract with the City of South Bend, and understands that the City
may terminate the contract for default if the Contractor fails to cure a breach of this provision no
later than thirty (30) days after being notified by the City.
6. Persons, firms, partnerships, corporations, associations, or joint venturers awarded a
contract by the City of South Bend through its agencies, boards, or commissions shall not
discriminate against any employee or applicant for employment in the performance of a City
contract with respect to hire, tenure, terms, conditions, or privileges of employment, or any matter
directly or indirectly related to employment because of race, sex, religion, color, national origin,
ancestry, age, gender expression, gender identity, sexual orientation or disability that does not
affect that person's ability to perform the work.
In awarding contracts for the purchase of work, labor, services, supplies, equipment, materials, or
any combination of the foregoing including, but not limited to, public works contracts awarded
under public bidding laws or other contracts in which public bids are not required by law, the City,
its agencies, boards, or commissions will consider the Contractor's good faith efforts to obtain
participation by those subcontractors certified by the State of Indiana as a Minority Business
("MBE") or as a Women's Business Enterprise ("WBE") as a factor in determining the lowest,
responsible, responsive bidder.
Contractors seeking the award of a City contract cannot be required to award a subcontract to an
MWBE; however, they may not unlawfully discriminate against said MBE/WBE. A finding of
noncompliance or a discriminatory practice shall prohibit that Contractor from being awarded a
City contract for a period of one (1) year from the date of such determination, and such
determination may also be grounds for terminating the contact to which the discriminatory practice
or noncompliance pertains.
7. The undersigned Contractor agrees that the following nondiscrimination commitment shall
be made a part of any contract which it may henceforth enter into with the City of South Bend,
Indiana or any of its agencies, boards or commissions.
Contractor agrees not to discriminate against or intimidate any employee or applicant for
employment in the performance of this contract with privileges of employment, or any matter
directly or indirectly related to employment, because of race, religion, color, sex, gender
expression, gender identity, sexual orientation, handicap, national origin or ancestry. Breach of
this provision may be regarded as material breach of contract.
I, the undersigned bidder or agent as contractor on a public works project, understand my statutory
obligations to the use of steel products or foundry products made in the United States (LC. 5-16-
8-1). I hereby certify that I and all subcontractors employed by me for this project will use steel
Version 2/14/2020 Page - 9 Public Works Quote
products or foundry products made in the United States on this project if awarded. I understand I
have an affirmative duty to notify the City in my bid that my proposal does not include the use of
steel products or foundry products made in the United States. I understand it is my sole obligation
and responsibility to provide a justification to the City, subject to review and approval, why the
cost of United States made steel or foundry products is unreasonable. Prior to award and upon
submission of bid which does not use steel products or foundry products made in the United States,
the City, through its director of public works, shall make a determination if the price of United
States made steel or foundry is unreasonable. I understand that violations hereunder may result in
forfeiture of contractual payments.
I hereby affirm under the penalties of perjury that the facts and information contained in the foregoing bid for public
works are true and correct.
Dated this 22 day of Sept. , 2020
Printed Name and Title
Subscribed and sworn to before me this 22 day of Sept. , 20 20
My Commission Expires 02/12/26 C4 d
Notary Public
County of Residence St Joseph
gyp;••"•e�s
O
SEAI 0
CART -NA CRUZ
Votary Public, State of Indiana
St. Joseph County
commission N 710388
My Commission Expires
February 12, 2026
Version 2/14/2020 Page - 10 Public Works Quote
QUOTE/PROPOSAL
CITY OF SOUTH BEND
l
PROJECT NAME Pinhook Park WTP Improvements — Exhaust Fans
PROJECT NO. 119-003A
QUOTES DUE September 22nd, 2020 at 9:30am local time
Open -market electronic quotes should be submitted to
fcavanau@southbendin.gov
Item
No.
Description
Quantity
Unit
Unit Price
Total Amount
Supply and install two (2) 2500cfm wall -
1
mounted exhaust fans and electrical
1
LSUM
$ 27,000.00
$ 27,000.00
circuit, according to the intent of the
special provisions and quote attachment
Address: 806 W. Sample St. South Bend, IN 46601
City/State/Zip: South Bend, IN 46601 Telephone Number: ( 574 ) 282-1228
Fax Number: ( 574 ) 282-1128
By
(Signature)
Fred Mohler, Service Manager
(Printed Name of Person Signing)
Version 2/14/2020 Page - 11 Public Works Quote
Quote Attachments: Pinhook WTP Exhaust Fans
Figure .1. West exhaust.fan - approximate interior location in west.filtration roam
Figure 2. West.ian - approximate exterior location
Quote Attachments: Pinhook WTP Exhaust Fans
Figure 3. Fast.ian - approximate interior location in east.iiltration roam
Figure 4. Fast.ian - approximate exterior location
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date:
Name
September 22nd, 2020
Finnian Cavanaugh Department of Public Works — Engineering Division
Phone Extension: 5961 or
BPW Date: October 131h 2020 fcavanau@southbendin.gov
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Clara McDaniels
Dept. Attorney ❑ Attorney Name
Purchasing ❑
Check the Appropriate Item Tvpe — Required for All Submissions
U Professional Services Agreement U Contract U Proposal
® Open Market Contract ❑ Amendment/Addendum ❑ Special Purchase, QPA
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award ❑ Reject Bids/Quotes
❑ Proposal Opening ❑ C/O & PCA No. ❑ PCA
❑ Chg. Order, No. ❑ Traffic Control ❑ Resolution
n Other: n Ease./Encroach
Information
Company or Vendor Name Ideal Consolidated, Inc.
New Vendor
MBE/WBE Contractor
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
U Yes U If Yes, Approved by Purchasing
® No
❑ WBE Completed E-Verify Form Attached ❑ Yes
No
Pinhook Water Treatment Plant Exhaust Fans
119-003A
Water Works Capital
622-06-604-620-442005--PROJ00000065
$27,000
NTE
Materials and installation for new exhaust fans in filtration rooms of
Pinhook WTP. OMC is being pursued with this vendor since no quotes
were received on time for the initial opening of quotes.
For Change Orders Only
Amount of ❑ Increase $
❑ Decrease ($ )
Previous Amount
Increase
Current Percent of Change: Decrease
New Amount $
Increase
Total Percent of Change: Decrease
Time Extension Amount: