August 25, 2020
Mr. Sean Welty
Ancon Construction Company, Inc.
2146 Elkhart Rd.
Goshen, IN 46526
sean@anconconstruction.com
er Park Improvements, Bid Package I
Project No. 118-010A
Dear Mr. Welty:
The Board of Public Works, at its meeting held on August 25, 2020, approved the above
referenced Change Order for an increase of $27,713 and an additional three-hundred and sixteen
(316) days, bringing the current contract amount to $1,412,692.86 and a new completion date
of October 1, 2020.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
s/Linda M. Martin, Clerk
Enclosure