HomeMy WebLinkAboutChange Order No 2 - Sewer & Manhole Rehabilitation Huron St. - Inland Waters Pollution Control
P HONE 574/ 235-9251
1316 C OUNTY-C ITY B UILDING
F AX 574/ 235-9171
227 W. J EFFERSON B OULEVARD
S OUTH B END,I NDIANA 46601-1830
C ITY OF S OUTH B END J AMES M UELLER,M AYOR
B OARD OF P UBLIC W ORKS
July 14, 2020
Mr. Jeremy Recklein
Inland Waters Pollution Control, Inc.
4086 Michigan Ave.
Detroit, MI 48210
jrecklein@TEAMIPR.COM
. Sewer & Manhole Rehabilitation
Project No. 118-093
Dear Mr. Recklein:
The Board of Public Works, at its meeting held on July 14, 2020, approved the above
referenced Change Order for an increase of $24,725.10, bringing the current contract amount
to $3,219,379.60.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
s/Linda M. Martin, Clerk
Enclosure
G ARY A. G ILOT E LIZABETH A. M ARADIK T HERESE J. D ORAU J ORDAN V. G ATHERS J OSEPH R. M OLNAR
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
Tfxfs'NboipmfSfibcjmjubujpo
229.1:43
Project Number: _______________ Project Name: __________________________ Change Order #: ____
302103131
DATE INITIATED:BPW DATE:
Brief Summary of Change Order; (Construction Change, Alternative, Substitution, Differing Instructions, Out of Scope, Etc.).
BeefeMjojohpoIvspoTusffuevfupdpmmbqtjohtfxfs/
Attachments: (List documents support changerequired)
DpousbdupsQspqptbm/
35-836/21
Amount of Increase / Decrease: $____________________
Categories (Pick One):
81-489/11
Scope of Work
Previously approved Change Order(s): $___________________
Differing Site Conditions, Changed Conditions
/88
Current Percent of Change: ____________________ %
Conflicted Specifications and Drawings
Failed Materials
4-32:-48:/71
New Total Amount: $____________________
Error
Omission
4/15
Total Percent of Change: ____________________ %
Final Quantity Adjustment
_______________________
753.1732.526/53.16)VujmjuzFyqfotf*
Funding Secured From: __________________________
(filled out by PM)
RECOMMENDEDBY:
KptiFinfs302103131
Project Inspector (Print Name)(Signature)(Date)
REVIEWED BY:
Construction Manager (Print Name)(Signature)(Date)
APPROVED BY:
TvfFmmfoEpvesjdl704103131
Engineering Project Manager (Print Name)(Signature)(Date)
APPROVED BY:
City Engineer (Print Name)(Signature)(Date)
February, 4 2020
City of South Bend
Attn: Josh Ehmer
227 W Jefferson Blvd
South Bend, Indiana 46601
Bid Proposal:Huron St. ER
South Bend, IN
Cured-In-Place Pipe Rehabilitation
Dear Mr.Ehmer,
IPR Great Lakes (IPR GL)is pleased to offer the following proposalpricing to provide cured in place
(CIPP) rehabilitation services of the 10-Inch sanitarysewer lines for the above referenced project. Our
proposal is based on the documents provided by Josh Ehmer dated January 31, 2020, with no addenda
acknowledged. This pricing includes providingall labor, material, supervision, and equipment necessary
to complete the scope of work as listed below.
Scope of work performed by IPR GL:
Provide pre-work submittals.
IPR GL will perform pre-rehab CCTV & cleaning (normal only). Two-wheel drive vehicle access
to manholes is required for this work.IPR GLwill review pre-rehab CCTV data (to be completed
by Others) to confirm that CIPP is viable and to confirm pipe sizes and lengths before ordering
materials or mobilizing our crew(s).
CIPP rehabilitation to be completed per ASTM 1216 standards utilizing water or air inversion &
water or steam curing methods.
Reinstatement of service laterals is via internal robotic cutter only (if required).
IPR GL will perform post lining CCTV inspection upon completion of our CIPP to confirm rehab
work.
CIPP rehabilitation pricing is based on completing diameters & associated quantities as listed in
this proposal’s schedule of values. Any change in overall or segmental length, diameters or liner
thicknesses could result in pricing changes.
Demobilize all construction equipment and clean-up of all identifiable debrisgenerated by IPR GL
crew(s).
Proposal includes costs for one mobilization. Additional mobilizations could result in additional
charges.
IPR GLproposes to complete the above scope ofservices for the prices listed below:
IPR GreatLakes7100 Huron River Dr.Dexter, Michigan 48130
Cured-In-Place Rehabilitation
South Bend, IN - Sewer and Manhole Rehabilitation
2
Item No.DescriptionQtyUnitUnit PriceTotal
1Mobilization1EA$ 6,925.50$ 6,925.50
210" CIPP ER-199LF$ 45.50 $ 4,504.50
10" CIPP ER-2
3292LF$ 45.50 $ 13,295.10
4INTERNAL POINT REPAIR (16")1EA$ 4,525.00$ 4,525.00
$ 29,250.10
4AADD INTERNAL POINT REPAIR (SAME LINE SEGMENT)1LF$ 2,250.00$ 2,250.00
4BADD INTERNAL POINT REPAIR (SEPARATE LINE SEGMENT)1EA$ 3,250.00$ 3,250.00
Thispricingdoes notinclude the cost for the following:
Furnishing Bid, Performance, or Payment Bonds.
Prevailing wages.
Heavy pipe cleaning, including but not limited to grease, roots, tuberculation removal, mechanical
cleaning, debris disposal, dump site, etc.
Prime Bidder/GC is responsible for providing adequate upstream & downstream access to
proposed lines, including but not limited to precast removal/replacement, access/easement
clearing, roads, staging, & inversion areas, etc.(should it be required). IPR GLand/or its
subcontractors must be able to set up over each manhole.
Erosion or site control including plans, permits, implementation, inspection, etc.
Excavation done by others.
Reinstatement of service laterals (other than by internal means only) or lateral rehabilitation or
service reconnections of any kind, including but not limited to pipe bursting or open cut
replacement. Dewatering, grouting, monitoring, point repairs (internal or open cut), new
installation, structure modification, etc. to be handled by Others if required.
Bypasspumping outside of normal flow conditions with IPR GLwork-zone
Traffic control outside of temporary signs and cones.
Testing of any kind.
Site restoration of any kind including but not limited to grading, grassing, concrete, or asphalt
work.
Any permits or fees, including fees for water source for pipe cleaning or rehab. Source and any
associated fees to be provided by Others.
Changes in pipe diameter, quantities, liner thickness, or lengths (overall or segmental) could
resultin pricing changes. Pricing based on completing all listed quantities in one mobilization.
Costs for site specific training/badging (safety, security, or otherwise).
Any work not specifically detailed in this proposal.
Pricing firm for 30 days from date of this proposal.
Removal and replacement of the manhole frame and cover for liner installation.
IPR GreatLakes7100 Huron River Dr.Dexter, Michigan 48130
Cured-In-Place Rehabilitation
South Bend, IN - Sewer and Manhole Rehabilitation
3
Thank you for the opportunity to offer you this proposal. Should you have any questions or require
additional information, please do not hesitate to contact me.
Sincerely,
IPRGreat Lakes
Dwight Silva
Business Development
Cc:Jeremy Recklein, Bid File
IPR GreatLakes7100 Huron River Dr.Dexter, Michigan 48130
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date6/30/2020DepartmentPublic Works
Name Sue Ellen DoudrickDivision/Bureau Engineering
BPW Date 7/14/20 Phone Extension 5992
Required Prior to Submittal to Board
LegalAttorney Name: Clara McDaniels
Controller review is required for all Contracts $5,000.00 or more and
Controller
greater than one year in length per the City Purchasing Policy
Purchasing Michael Schmidt
Check the Appropriate Item Type –Required for All Submissions
AgreementAmendmentContractProposalAddendum
Professional Services Resolution
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award
Change Order No. 2 C/O & PCA No. PCA
Ease/Encroach. Traffic Control:
Other:
Required Information
Company or Vendor Name Inland WatersPollution Control
Yes No If Yes, Approved by
New Vendor Purchasing
MBE/WBE Contractor MBE WBE
MBE/WBE Contractor Requested No Yes Name of Company
Project Name Sewer and Manhole Rehabilitation
Project Number 118-093
Funding Source
Account No.
641-06-602-509-439001
Amount Change Order #2: $ 24,725.10
Terms of Contract Unit prices
Purpose/Description
Emergency Sewer Lining required at Huron Street
See attached change order documentation.
Required Contractor’s Certification FormsAttached(Non-
Collusion, Non-Discrimination, Non-Debarment, E-Verify, Iran, etc.)
Required For Change Orders Only
$ 24,725.10
Increase
Amount of
Decrease$
Previous Amount $ 3,194,654.50
Current Percent of Change: 0.77%
New Amount $3,219,379.60
Total Percent of Change: 3.0%