December 19, 2019
Mr. Jamie Brazeau
ChoiceLight, Inc.
130 S. Main St., Suite 275
South Bend, IN 46601
RE: Lateral Proposals
Dear Mr. Brazeau:
PHONE 574/235-9251
FAx 574/235-9171
The Board of Public Works, at its meeting held on December 19, 2019, approved the
above referenced Metronet buildout for six (6) locations in the amount of $259,312.
Enclosed please find a copy of the agreement for your records.
If you have any further questions regarding this matter, please call this office at (574)
235-9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
GARY A. GILOT GENEVIEVE E. MILLER ELIZABETH A. MARADIK LAURA L. O'SULLIVAN THERESEJ.
J. DORAU
Chdii a e'
Lateral Proposal
City of South Bend
227 W. Jefferson #1200N
South Bend, Indiana, 46601
2626 Gertrude St., South Bend
Proposal for new conduit and fiber at Rum Village:
ChoiceLight,Inc.
130 S. Main St. Suite 275
South Bend, IN 46601
December 5, 2019
D32-0818
• Bore 2-inch & 1-1/4-inch HDPE approx. (4,125') from Gertrude, West along
Ewing to Olive.
• Install Tracer and Pull Rope.
• Install (8) new handholes.
• Install Corning Fiber.
• Install new fiber panel and splice into the Backbone.
• Tie conduit into existing HH.
• Proposal does not include Indiana sales tax.
We hereby propose to furnish material and labor in complete accordance with the above
specifications for the sum of $ 80,955 (Eighty Thousand Nine Hundred Fifty Five Dollars)
All materials are guaranteed to be as specified. All work to be completed in a satisfactory
manner according to standard practices. Any alteration or deviation from the above
specifications or involving extra costs will be executed only upon written orders and will become
an extra charge over and above this proposal. All agreements are contingent upon strikes,
accidents, or delays beyond our control. The Owner will carry fire, tornado, and other necessary
insurance. Our workers are fully covered by Worker's Compensation Insurance. This proposal is
valid for 30 days from issue date.
ACCEPTANCE OF PROPOSAL
The above prices, specifications, and conditions are satisfactory and are hereby accepted. ChoiceLight,
Inc. is authorized to do the work as specified. Payment will be made as stated above.
The undersigned person executing this Proposal represents and certifies that he/she is a duly authorized
officer with authority to execute this Proposal and has the full legal rights, power and authority to enter
into this Proposal and to grant the rights and perform the obligation herein; that no third party consent or
approval is required to grant such right or perform such obligations hereunder.
APPIROVED
of �W.j f.f i
Signature: Date:
Choice
� , a �.
U o h.
Lateral Proposal
City of South Bend
227 W. Jefferson #1200N
South Bend, Indiana, 46601
2801 Riverside Dr., South Bend
Proposal for new conduit and fiber at Pinhook Park:
• Install fiber into the building.
• Install new splice enclosure.
• Splice strands to ChoiceLight backbone.
• Test and label.
• Install 2-inch HDPE 2,700' to the Building.
• Install Tracer and Pull Rope.
• Install (4) new handholes
• Rough -in conduit into the handhole and building.
• Proposal does not include Indiana sales tax.
ChoiceLight,Inc.
130 S. Main St. Suite 275
South Bend, IN 46601
December 5, 2019
D10-0919
We hereby propose to furnish material and labor in complete accordance with the above
specifications for the sum of $ 49,090 (Forty Nine Thousand Ninety Dollars)
All materials are guaranteed to be as specified. All work to be completed in a satisfactory
manner according to standard practices. Any alteration or deviation from the above
specifications or involving extra costs will be executed only upon written orders and will become
an extra charge over and above this proposal. All agreements are contingent upon strikes,
accidents, or delays beyond our control. The Owner will carry fire, tornado, and other necessary
insurance. Our workers are fully covered by Worker's Compensation Insurance. This proposal is
valid for 30 days from issue date.
ACCEPTANCE OF PROPOSAL
The above prices, specifications, and conditions are satisfactory and are hereby accepted. ChoiceLight,
Inc. is authorized to do the work as specified. Payment will be made as stated above.
The undersigned person executing this Proposal represents and certifies that he/she is a duly authorized
officer with authority to execute this Proposal and has the full legal rights, power and authority to enter
into this Proposal and to grant the rights and perform the obligation herein; that no third party consent or
approval is required to grant such right or perform such obligations hereunder.
g fia,� Date,
Si nature; .�.
DEC 119 ,
hoiceLight Inc.
,�.�. r�regfl rytaC carg
6/13/2019
Lateral Proposal
City of South Bend
227 W. Jefferson #1200N
South Bend, Indiana, 46601
907 N. Lafayette Blvd., South Bend
Proposal for new conduit and fiber at Leeper Park:
• Install 48-strand fiber into the building.
• Install new splice enclosure.
• Splice strands to ChoiceLight backbone.
• Test and label.
• Install 2-inch HDPE to the Building.
• Install Tracer and Pull Rope.
• Install (2) new handholes
• Rough -in conduit into the handhole and building.
• Proposal does not include Indiana sales tax.
ChoiceLight,Inc.
130 S. Main St. Suite 275
South Bend, IN 46601
December 10, 2019
D09-0919
We hereby propose to furnish material and labor in complete accordance with the above
specifications for the sum of $ 14,600 (Fourteen Thousand Six Hundred Dollars)
All materials are guaranteed to be as specified. All work to be completed in a satisfactory
manner according to standard practices. Any alteration or deviation from the above
specifications or involving extra costs will be executed only upon written orders and will become
an extra charge over and above this proposal. All agreements are contingent upon strikes,
accidents, or delays beyond our control. The Owner will carry fire, tornado, and other necessary
insurance. Our workers are fully covered by Worker's Compensation Insurance. This proposal is
valid for 30 days from issue date.
ACCEPTANCE OF PROPOSAL
The above prices, specifications, and conditions are satisfactory and are hereby accepted. ChoiceLight,
Inc. is authorized to do the work as specified. Payment will be made as stated above.
The undersigned person executing this Proposal represents and certifies that he/she is a duly authorized
officer with authority to execute this Proposal and has the full legal rights, power and authority to enter
into this Proposal and to grant the rights and perform the obligation herein; that no third party consent or
approval is required to grant such right or perform such obligations hereunder.
Signature: i14wd of 1h,L?SL1iq I ... .._................................ Date:
DEC, 1� 2 I 9
, 9h6ceUght, Inc.
6/13/2019
eight
Lateral Proposal
City of South Bend
227 W. Jefferson #1200N
South Bend, Indiana, 46601
2000 Wall St., South Bend
Proposal for new conduit and fiber at Potawatomi Pool:
• Install 2" HDPE from Wall, East.
• Install new Corning SM fiber.
• Install (2) new handholes.
• Install new fiber patch panel.
• Install new splice enclosure.
• Splice strands to backbone.
• Test and label.
• Proposal does not include Indiana sales tax.
ChoiceLight,Inc.
130 S. Main St. Suite 275
South Bend, IN 46601
December 6, 2019
D13-1219
We hereby propose to furnish material and labor in complete accordance with the above
specifications for the sum of $ 19,450 (Nineteen Thousand Four Hundred Fifty Dollars)
All materials are guaranteed to be as specified. All work to be completed in a satisfactory
manner according to standard practices. Any alteration or deviation from the above
specifications or involving extra costs will be executed only upon written orders and will become
an extra charge over and above this proposal. All agreements are contingent upon strikes,
accidents, or delays beyond our control. The Owner will carry fire, tornado, and other necessary
insurance. Our workers are fully covered by Worker's Compensation Insurance. This proposal is
valid for 30 days from issue date.
ACCEPTANCE OF PROPOSAL
The above prices, specifications, and conditions are satisfactory and are hereby accepted. Choicel-ight,
Inc. is authorized to do the work as specified. Payment will be made as stated above.
The undersigned person executing this Proposal represents and certifies that he/she is a duly authorized
officer with authority to execute this Proposal and has the full legal rights, power and authority to enter
into this Proposal and to grant the rights and perform the obligation herein; that no third party consent or
approval is required to grant such right or perform such obligations hereunder.
Signature: i o F t_ _. _� Date
r
��II Ilio�i.i n,
Lateral Proposal
City of South Bend
227 W. Jefferson #1200N
South Bend, Indiana, 46601
2700 Westmoor St., South Bend
ChoiceLight,Inc.
130 S. Main St. Suite 275
South Bend, IN 46601
December 6, 2019
Proposal for new conduit and fiber at City of South Bend - Kennedy Pool:
D14-1219
• Install 2-inch HDPE from Bendix, North on Eclipse.
• Install new Corning 24 strand SM fiber from backbone at Ironwood.
• Install (2) new handholes.
• Install new fiber patch panel.
• Splice strands to backbone.
• Test and label.
• Proposal does not include Indiana sales tax.
We hereby propose to furnish material and labor in complete accordance with the above
specifications for the sum of $ 23,000 (Twenty Three Thousand Dollars)
All materials are guaranteed to be as specified. All work to be completed in a satisfactory
manner according to standard practices. Any alteration or deviation from the above
specifications or involving extra costs will be executed only upon written orders and will become
an extra charge over and above this proposal. All agreements are contingent upon strikes,
accidents, or delays beyond our control. The Owner will carry fire, tornado, and other necessary
insurance. Our workers are fully covered by Worker's Compensation Insurance. This proposal is
valid for 30 days from issue date.
ACCEPTANCE OF PROPOSAL
The above prices, specifications, and conditions are satisfactory and are hereby accepted. ChoiceLight,
Inc. is authorized to do the work as specified. Payment will be made as stated above.
The undersigned person executing this Proposal represents and certifies that he/she is a duly authorized
officer with authority to execute this Proposal and has the full legal rights, power and authority to enter
into this Proposal and to grant the rights and perform the obligation herein; that no third party consent or
approval is required to grant such right or perform such obligations hereunder.
Signature;, --Date:
Le 1
7 Ch
Rev, 6/1312019
Lateral Proposal
City of South Bend
227 W. Jefferson #1200N
South Bend, Indiana, 46601
1300 S. Mayflower Rd., South Bend
Proposal for new conduit and fiber at Byers Softball Field:
ChoiceLight,Inc.
130 S. Main St. Suite 275
South Bend, IN 46601
December 10, 2019
D11-1219
• Install 2-inch HDPE from Western/SR2, South along Mayflower.
• Install new Corning 24 strand SM fiber from backbone at Western.
• Install (4) new handholes.
• Install new fiber patch panel.
• Splice strands to backbone.
• Test and label.
• Includes discount of $19,000
• Proposal does not include Indiana sales tax.
We hereby propose to furnish material and labor in complete accordance with the above
specifications for the sum of $ 72,177 (Seventy -Two Thousand One Hundred Seventy -Seven
Dollars)
All materials are guaranteed to be as specified. All work to be completed in a satisfactory
manner according to standard practices. Any alteration or deviation from the above
specifications or involving extra costs will be executed only upon written orders and will become
an extra charge over and above this proposal. All agreements are contingent upon strikes,
accidents, or delays beyond our control. The Owner will carry fire, tornado, and other necessary
insurance. Our workers are fully covered by Worker's Compensation Insurance. This proposal is
valid for 30 days from issue date.
ACCEPTANCE OF PROPOSAL
The above prices, specifications, and conditions are satisfactory and are hereby accepted. ChoiceLight,
Inc. is authorized to do the work as specified. Payment will be made as stated above.
The undersigned person executing this Proposal represents and certifies that he/she is a duly authorized
officer with authority to execute this Proposal and has the full legal rights, power and authority to enter
into this Proposal and to grant the rights and perform the obligation herein; that no third party consent or
approval is required to grant such right or perform such obligations hereunder.
Sign atur.tPDate:
K Inc.
Cot -ON
3/2019
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date
Name
12/9/19
Michael E. Sniadecki
Department Innovation & Tech
BPW Date 12/19/19 Phone Extension 6004
likWlllllllll�l�'�lAi u � ....mvs JVi NtlO� WIY .. ya'£�r F���'w�i�6M,ku/{xN/M�N��ihmIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII�;W�gFiY q,9A4PAp,IpU&p/➢UE"JION!!,'I'I�N'�'ll NINi�YN�M�kvYvY1�10tlIWUJWN;"ifY ���+����A6GibSJui,
�.,.,...., .,...... ........ ...,.o...,..........�,.,,.�.a...,.. �.....�............................—...,..�,..,.
required Prior to Submittal to Board
Legal ® Attorney Name Sandra Kennedy
Controller ® Controller review is required for all Contracts $5,000.00 or more anc
greater than one year in length per the City Purchasing Policy
Purchasing
Check the Appropriate Item Type
Agreement
® Professional Services
Bid Opening
El Quote Opening
[] Change Order No.
El Ease/Encroach.
E Other:
LJ Contract
❑ Resolution
❑' Bid Award
Quote Award
[� C/O & PCA No.
❑ Traffic Control
for All Submissions
j Proposal 0 Addendum
❑ Req. to Advertise ❑ Title Sheet
uired Information
Company or Vendor Name ChoiceLiht (formerly Metronet Zi
❑ PCA
New Vendor ❑ Yes Z No ❑ If Yes, Approved by Purchasing
MBE/WBE Contractor ❑ MBE ❑ WBE
MBE/WBE Contractor Requested ❑ No ❑ Yes Name of Company
City of South Bend -Metronet Buildout Phase 3
Project Name (Choice Light/Metronet Portion)
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Amount of ❑
Previous Amount
n/a
IT Professional Svc
279-067..........._
2-415-31-06 _
A one-time cost of $259,312,
Statement of Work
Add six COSB locations to the Metronet during phase 3 of this
project..
❑ Required Contractor's Certification Form Attached (Non -
Collusion, Non -Discrimination„ Non -Debarment, E-Verify; Iran, etc.
Required For Change Orders Only
Increase $
Decrease
..........
Current Percent of Change: %
New Amount $
� ,�. INTER -OFFICE MEMORANDUM
n
Information Technologies Department
, s r 227 W Jefferson Blvd (574) 245-6000
,CRkTCF,py
TO: Board of Public Works, Linda Martin
CC: Dan O'Connor
FROM: Michael E. Sniadecki, Director of Infrastructure
SUBJECT: City of South Bend -Metronet Buildout Phase 3
(ChoiceLight/Metronet Portion) 1 of 2
Connecting our facilities for reliability and performance
DATE: 12/9/19
Linda, Clara, Sandra, Ben, Daniel & Michael,
Please see the attached quotes and spreadsheet regarding the addition of six COSB locations to
the Metronet/Dark Fiber during Phase 3 of this project. The overall initiative is to connect just
about all city facilities to the Metronet/dark fiber within two years with an exception of Elbel Golf
Pro Shop & Maintenance Garage.
Currently, Metronet/Dark Fiber serves as the backbone to share IT services/network connectivity
throughout many of the city facilities. ChoiceLight (formerly Metronet Zing) provides significant
savings as well as better, faster, more reliable/redundant connectivity. The Office of Innovation
and Technology team reviewed the quote and give favorable recommendation.
Below are locations within phase 3 that have no network connection, very slow circuit, and/or lack
of redundancy:
1) Rum Village
2) Pinhook Park
3) Leeper Park
4) Potawatomi Pool
5) Kennedy Pool
6) Byers Softball Complex
Phase 3 of the Metronet/Dark Fiber Buildout will be a one-time cost of $259,312 (Total of
$298,411.14 including equipment in another agenda). We have $373,000 budgeted f/ 2019.
ChoiceLight is a "sole source" vendor. They are the only ones that can do this work.
Thank you,
Michael E. Sniadecki
Metronet Connectivity
Locations
Phase 3 Total
Rum Village
80,995.00
Pinhook Park
49,090.00
Leeper Park
14,600.00
Kennedy Pool
23,000.00
Potawatomi Pool
19,450.00
Byers Softball Complex
72,177.00
Total
$259,312.00