HomeMy WebLinkAboutChange Order No 3 - VPA Restroom Remodeling Proj No 118-043R - Michiana Contracting Inc.1316 CoUNTY-CITY BUILDING
PHONE $74/ i3$-9i$ I
227 W. JEFFERSON BOULEVARD '`-r� 1"r'i
FAX 574/ 235-9171
SOI ITH BEND_ INDIANA 46601-1830
CITY OF SOUTH BEND PETE BUTTIGIEG, MAYOR
BOARD OF PUBLIC WORKS
November 12, 2019
Mark Livinghouse
Michiana Contracting Inc.
7843 Lilac Road, PO Box 929
Plymouth, IN 46563
RE: Change Order No. 3 - VPA Restroom Remodeling — Project No. 118-043R
Dear Mr. Livinghouse:
The Board of Public Works, at its meeting held on November 12, 2019, approved the above
referenced Change Order for an increase of $4,058, plus an additional twenty-three (23) days,
bringing the current contract amount to $529,308.82, and revised contract completion date to
October 11, 2019.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
GARY A. GILOT GENEVIEVE E. MILLER ELIZABETH A. MARADIK LAURA L. O'SULLIVAN THERESE J. DORAU
yea H Mi h,
CITY OF SOUTH BEND, INDIANA a
;m34
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE: 8/26/2019
PROJECT NO: 118-043R
PROJECT NAME: VPA Restroom Remodelin
CONTRACT DATE: 1/22/2019
CHANGE ORDER NO: 3
SUBJECT OF CHANGE ORDER: PCR #3-Unforeseen repairs & delay
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
Contractor Signature
w
«^
Printed Name and Titfe
Michiana Contracting Inc.
Company Name
7843 Lilac Rd. PO Box 929
Address
.Plymouth, IN 46563
City, State, Zip
$ 490,000.00
$ 35,250.82
$ 525,250.82
X�Increased
Decreased $ 4,058.00
$ 529,308.82
0.77 %
8.02 %
8/30/2019
19 days
23 days
10/11/2019
r Y T M. M ���:, w s rN. JY1 M N •.. i
IM
•1UN MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
Approved Date: e
Gary A. Gilot, P 'sident
Genevi ve E. Miller, Member
I L I- a
Elizabeth A. Maradik, Member
-,.-„
There J. Dorau,,,Me' er
"'l�aura O'Sullivan, Member
a, DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
Project Number: 118-043R Project Name: VPA Restr worn Remodeling Change Order #: 3
DATE INITIATED: 10/15/19 BPW DATE:
Brief Summary of Change Order; (Construction Change, Alternative, Substitution, Differing Instructions, Out of Scope, Etc.).
Replace main shut-off valve at Vet's Memorial- $3,390
Miscellaneous unforeseen costs at Rum Village and Pinhook- $668
Unforeseen delays- Extend completion to 10/11/2019
Attachments: (List documents support change - required)
Contractor's cost explanations and time extension request.
Amount of BIncrease/ ❑Decrease: $ 4058
"""""' Categories (Pick One):
Previously approved Change Order(s): $ 35250.82 B Scope of Work
.- - El
Site Conditions, Changed Conditions
Current Percent of Change: 0'77 % ❑ Conflicted Specifications and Drawings
.. ❑Failed Materials
New Total Amount: $ 529, 308.82
❑ Error
❑ Omission
Total Percent of Change: 8.02
❑ Final Quantity Adjustment
Funding Secured From
(filled out by PM)
RECOMMENDED BY:
rr
Project Inspector (Print Name) iiegnature) (Date)
REVIEWED BY:
Construction Man ger (Print Name) (Signature) (Date)
APPROVED BY:
Engineering Project Manager (Print Name) (Signature) (Date)
APPROVED BY:
City Engineer (Print Name) (Signature) (Date)
From: Mark Livin house
To: QM9QU McGowan
Subject: Additional C/0"S
Date: Monday, July 1, 2019 2:40:43 PM
1. Pinhook Park: Pricing to install light switch that was moved from wall that was removed at door
way In woman's restroom. $368.00
2. Rum Village water line consultation
$300.00
Thanks
Mark Livinghouse
Michiana Contracting Inc.
PO Box 929
7843 Lilac Rd
Plymouth, IN 46563
Work a7A03646_B.
Fax
Mailing Address
P.O. Box 929
Plymouth, IN 46563
9/19/19
City of South Bend
Greg McGowen
227 W. Jefferson Blvd.
South Bend, IN 46601
RE: Project No. 118-043R Venues, Parks and Arts Restroom Remodeling Contract Time Extension
Due to design Issues at Veterans Memorial Park
Greg,
As you are aware, plumbing issues were encountered during the demolition of the block wall
at Veteran's Park August 27th. The original design called for wall hung toilets with flush values that which would
not work at this location. It was determined that these toilets needed to be changed to floor mount units.
In addition, the shut off valve in the pit was broken and could not be completely turned off. The plumbing work at
this location was put on hold for several weeks until a decision was reached on how to proceed.
Parts for the new water valve are on order, along with the parts needed to make toilet and flush valve changes.
We anticipate these parts arriving sometime next week.
The plumbers have been at a standstill since 8/28/19 and were able to start on some work 9/18/19 while
still waiting for parts for the pit shut off valve. As a result of these delays we are requesting a contract time
extension until 10/11/19. This will allow us the time needed to procure the parted needed and complete the
work.
On 9/18/19 it was discovered that the men's restroom has no floor drain which is required by code. If a new drain
is required to be installed, additional time will be needed.
Please let me know if you have any questions or need any additional information.
Mark Livinghouse
Project Manager
Michiana Contracting
MICHIANA CONTRACTING, INC. Shipping Address: 7843 Lilac Road Plymouth, IN 46563
Tel: 574-936-8613 Fax: 574-936-6201 www,w�iiiciiiati contractin co
Mailing Address
P.O. Box 929
Plymouth, IN 46563
9/19/19
City of South Bend
Greg McGowen
227 W. Jefferson Blvd,
South Bend,IN 46601
RE: Project No. 118-043R Venues, Parks and Arts Restroom Remodeling Change Order for pit water
Valve replacement. And pit clean out.
Materials:$1036.00
Labor 1700.00
10% MU 264.00
Total 3000.0
Pit clean out
$390.00
Total change order
$3,390.00
Mark Livinghouse
Project Manager
Michiana Contracting
MICHIANA CONTRACTING, INC. Shipping Address: 7843 Lilac Road Plymouth, IN 46563
Tel: 574-936-8613 Fax: 574-936-6201 a www.michianac ntr�acti corn
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date November 5, 2019
Department Public
Name Scott Kree er Works
BPW Date November 12 2019 Phone Extension 9245
Rpquired Prior to Submittal to Board
BPW Attorney ❑ Attorney Name
Dept. Attorney r-] Attorney Name
Purchasing
Check the Appr prlat Item Type Requ re l r All Submissions
D Professional Services Agreement Contract
❑ Open Market Contract
❑ Amendment/Addendum
Bid Opening
❑ Bid Award
E]
Quote Opening
❑ Quote Award
Proposal Opening
❑ C/O & PCA No.
Z
Chg. Order, No. 3
❑ Traffic Control
n Other:
Information
Company or Vendor Name Michiana Contracting, Inc.
New Vendor
MBE/WBE Contractor
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Proposal
Special Purchase, QPA
E] Req. to Advertise
Reject Bids/Quotes
H PCA
Resolution
Ease./Encroach
❑ Title Sheet
Yes If Yes, Approved by Purchasing
No
MBECompleted E-Verify Form Attached ❑ No
V'PA Restroom Remodeling
118-043R
....................
471-113 8-452.42-01
.......... _. ... .... ......
Parks Bond I
Avoroval of C.O. #3
For Change Orders Only
Amount of Increase $4,058.00
❑ Decrease $
Previous Amount
Current Percent of Change:
New Amount
Total Percent of Change:
Time Extension Amount:
Increase 0.77%
Decrease %
$ $529308.82
Increase_..................................8...02%
Decrease %
23 Das
New Completion Date: 10/11/2019