September 24, 2019
Scott Randle
American Structurepoint, Inc.
r 4a �c(1 ,i�stt trcttlE Agin eoti,i
RE: Change Order No. 1 - Safe Routes to School: LaSalle Intermediate and Marquette
Primary —Project No. 116-040
Dear Mr. Randle:
The Board of Public Works, at its meeting held on September 24, 2019, approved the above
referenced Change Order for an increase of six (6) additional days, bringing the current
contract completion date to August 22, 2019.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
GARY A. GILOT GENEVIEVE E. MILLER ELIZABETH A. MARADIK LAURA L. O'SULLIVAN THERESE J. DORAU
<< DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
r�aa
116-040 'WOR*a" � �� � ,a;a �� ��� G �� ,��� � ���,anM r�W� 1
Project Number: Project Name: Change Order #:
DATE INITIATED: 9/16/19 BPW DATE:9/24/19
Brief Summary of Change Order; (Construction Change, Alternative, Substitution, Differing Instructions, Out of Scope, Etc.).
Time Extension of 6 days due to utility delays by AEP.
Attachments: (List documents support change — required)
INDOT Change Order Form
Amount of ❑ Increase / ❑ Decrease: $ NSA
Categories (Pick One):
Previously approved Change Order(s): $ N/A ❑ Scope of Work
............................. — ......... ®----® ❑ Differing Site Conditions, Changed Conditions
Current Percent of Change: NSA % ❑ Conflicted Specifications and Drawings
New 1,589, 000 ❑ Failed Materials
Total Amount: $_ ❑ Error
❑ Omission
Total Percent of Change: 0.00
❑ Final Quantity Adjustment
17-11
Funding Secured From° _. ..
(filled out by PM)
RECOMMENDED BY.
Project Inspector (Print Name) (Signature) (Date)
REVIEWED BY:
Construction Manager ( (nt Name) (Signature) (Date)
APPROVED BY:
Engineering Project Manager (Print Name) (Signatu (Date)
APPROVED Y:
City Engineer (Print Name) (Signs v ) (Date)
Contract No:R -39514 Change Order No.: 001
INDIANA Department of Transportation Page: 1
Construction Change Order and Time Extension Summary
Contract Information Contract No.: R -39514 Letting Date:10/11/2018
District:LAPORTE DISTRICT AE:Forgey, Ryan PE/S:Randle, Scott Status:Draft
Change Order Information Change Order No.: 001 EWA: N or Force Acct: N
Date Generated: 00/00/0000 Date Approved: 00/00/0000
Reason Code: CHANGED COND, Utility Related
Description: Time Extension
Original Contract Amount $ 1,589,000.00
Current Change Order Amount $ 0.00 Percent: 0.000 %
Total Previous Approved Changes $ 0.00 Percent: 0.000 %
Total Change To -Date $ 0.00 Percent: 0.000 %
Modified Contract Amount $ 1,589,000.00
Time Extension Information
Date Initiated 00/00/0000 Date Completed 00/00/0000
Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SP Date 00/00/0000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Time Element Description:
Current Time Extension SS Days 0 SP Days 6 SP Days Value $ 0.00
Previous Time Approved SS Days by AE: DCE:_ SCE: DDCM:-__
SS Days.__,_._ SP Days Value $
Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SS Date 00/00/0000 or SP Days 0
Contract No:R -39514
INDIANA Department of Transportation
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority
($ per Change Order)
(Days per Contract)
Verbal Approval Required?
Total Change To-Date>5%?
Scope/Design Recommendation
Required?
Change Order No.: 001
Page: 2
AE: DCE: SCE: " DDCM:
(-LE$250K-)(-LE$750K-)(--LE$2M--)(--GT$2M--)
( 50 SS days) ( 100 SS days) ( 200 SS Days) ( GT 200 SS days)
Y / N If Y, by Date Issued,----
Y / N If Y, Copy to Program Budget Manager, rv,
Y / N If Y, Referred to Project Manager(PM)
Date to PM
Approval Authority Concurs with PM? Y / N If Y, Concurrence by
If N,Resolution: Approved
Date Returned
Resolvedby_......-...........-_.._.._.. ........
._
LPA Signatures Required? Y / N If Y, Date to LPA _
FHWA Signatures Required? Y / N If Y, Date to FHWA
* Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer wy mm mmm _ w wwwwww Date
Comments:
Date
Disapproved
Date
Date Returned
Date Returned
Contract No:R -39514
Change Order No:001
INDIANA
Department of Transportation
Date:08/21 /2019
Contract: R -39514
Project: State: 160007600LC4
Change Order Nbr: 001
Change Order Description: Time Extension
Reason Code: CHANGED COND, Utility Related
CI„N IPON P11 v _ . «....,.. 'Commenter Amount..
�� "" Il�f Vlr�m f �ri II�InIt II Ptttt. Price CO Cilfy Change
Milestone Time Adjustment
MileStone Nbr: 02
Page: 3
Total Value for Change Order 001 = $ 0.00
Milestone Description: INTERMEDIATE COMPLETION DATE
Original Completion dt: 08/16/2019 Adi comp) dt 08/22/2019 Adi No. of Days 6
Explanation: Before the start of the project AEP had several power poles along Hamilton between Olive and Brookfield. and along
Keller between Olive and Johnson, which needed to be relocated and removed. Reith Riley started removing concrete
on April 1. 2019 and had to start in the middle of the project were power poles were not in conflict. Rieth Riley was able
to remove and pour concrete in as many intersections as possible before the power poles would be an issue. AEP was
on -site June 19 20 t 9 to start removing and relocating the power poles along Hamilton and Keller AEP crews were
onsite for only 10 days before being called off on antherjob, their work was not complete. While AEP was on -site they
completed placing the new poles along Hamilton but not relocating their cables or removing the old poles along Hamilton
and Keller. Since the power poles were still in place Rieth Riley could not remove or pour any concrete at those
intersections due to utilities, which caused Reith Riley several days of delays. AEP was back onsite Aug 5 2019 and was
able to remove the power poles along Keller between Olive and Johnson on Aug 9, 2019 Once the poles were removed
Rieth Riley complete removal and concrete work at those intersections. Due to AEP delay in removing those poles along
Keller. Reith Riley had delays, and is requesting an additional 6 days be added to the contracts intermediate completion
date due to utility delays. I have reviewed Rieth Rileys request for those 6 days and spoke with the City of South Bend
regarding the time extension request. Upon talking with the City we agree on allowing the contractor 6 extra days be
added to the intermediate completion date due to utilities. The contract has an intermediate completion date of August
16, 2019. By adding those additional 6 days that would make the new intermediate competition date be Aug 22 2019. 1
have attached Rieth Riley letter requesting the time extension.
Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended.
General or Standard Change Order Explanation
Before the start of the project AEP had several power poles along Hamilton between Olive and Brookfield, and along Keller between Olive and
Johnson, which needed to be relocated and removed. Reith Riley started removing concrete an April 1. 2019 and had to start in the middle of the
project were power poles were not in conflict Rieth Riley was able to remove and pour concrete in as many intersections as possible before the
power poles would be an issue, AEP was on -site June 19, 2019 to start removing and relocating the power poles along Hamilton and Keller. AEP
crews were onsite for only 10 days before being called off on antherjob. their work was not complete. While AEP was on- site they completed
placing the new poles along Hamilton but not relocating their cables or removing the old poles along Hamilton and Keller Since the power poles
were still in place Rieth Riley could not remove or pour any concrete at those intersections due to utilities, which caused Reith Riley several days
of delays. AEP was back onsite Aug 5 2019 and was able to remove the power poles along Keller between Olive and Johnson on Aug 9, 2019.
Once the poles were removed Rieth Riley complete removal and concrete work at those intersections. Due to AEP delay in removing those poles
along Keller, Reith Riley had delays, and is requesting an additional 6 days be added to the contracts intermediate completion date due to utility
delays. I have reviewed Rieth Rileys request for those 6 days and spoke with the City of South Bend regarding the time extension request. Upon
talking with the City we agree on allowing the contractor 6 extra days be added to the intermediate completion date due to utilities. The contract
has an intermediate completion date of August 16, 2019. By adding those additional 6 days that would make the new intermediate competition
date be Aug 22 2019. 1 have attached Rieth Riley letter requesting the time extension.
Change Order Explanation for Specific Line Item
It is the intent of the parties that this change order is full and complete compensation for the work describe above
Notification and consent to this change order is hereby acknowledged
Contractor: Rieth Ril
Da
tt=: 8/21 /19
Construction Co., Inc.
"Signed
Contract No:R -39514 INDIANA
Change Order No:001 Department of Transportation
NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system,
Date:08/21/2019
Page: 4
Contract No:R -39514 INDIANA
Change Order No:001 Department of Transportation
................................ I .....................................................................................
4)z,
q PPROVED FOR LOCAL PUBLIC AGENCY
. ........ . ....
(SIGNAT RE)
(TITLE)
(SIGNATURE) (TITLE)
A
t
SUBMITTED FOR CONSIDERATION
P Ej Sf�
kt
(DATE)
Of
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORTATION
4�ro"'va--1,L"e,,V'e"l' -"""N,'a"m''-e" "o, f"Ap-p-r-o',v-e-r- ",_—ate-
Date:08/21/2019
Page: 5
100% Quality
April 24, 2018
Scott Randle
INDOT Project Supervisor
American Structurepoint
Project: INDOT R-39514-A
/ JAh
100% Employee Owned
Lasalle Safe Routes to School
Intermediate Completion Time Extension Request
Dear Mr. Randle,
Over 100 Years
Rieth Riley is requesting an intermediate completion time extension to the INDOT R-39514-A, Lasalle
Safe Routes to School project. The time extension is due to utility delays by AEP and extra work added
along Bergan Street to the contract.
In the beginning of the project we encountered several AEP power poles which were to be removed and
or relocated before the project started. These power poles had not been and still have not been
relocated or moved as of today. These utilities delayed us approximately 3 days in the beginning during
our removal phase of the project. Also, during construction of the sidewalk and curb ramps for the
project, the power poles were in our way as we tried to complete our work. We were ordered to leave
out small pockets of concrete adjacent to the power poles so AEP could move them more easily. In the
last few weeks of the project it was determined that the poles would most likely not be relocated by the
intermediate completion date and the City decided we should go back to these areas without concrete
and rework them the best we could. This extra work caused us another 3 days of coordination and work
around, and the power poles are yet to be relocated to this day.
Lastly, there was some additional sidewalk work along Bergan Street requested to be performed. This
extra sidewalk work, which was requested towards the end of the project, caused for an additional day
of work.
For the reasons listed above, we are requesting an additional 7 days of time extension to the
intermediate completion date. If you have any questions, do not hesitate to contact us.
Respectfully,
RIETH-RILEY CONSTRUCTION CO., INC.
Ruben Alvarado, P.E.
Project Manager
P.O. Box 1775 • 25200 S. R. 23 • South Bend, IN 46634
Phone: (574) 288-8321 • www.rieth-riley.com
CONTRACT NO. ( R-39514-A
DATE OF SUBMISSION August 15, 2019
PROJECT DESCRIPTION Lasalle SRTS
(route / intersection / bridge no(s).)
CHANGE ORDER REQUEST SUMMARY Intermediate Completion Date Time Extension due to utility delay and extra
DESCRIPTION work
PROPOSED SOLUTION SUMMARY Time extension for 7 days
i
NOTE, Upon request from Engineer, enter detailed description on page 2
ONSET DATE OF CHANGE August 15, 2019 � CHANGE ORDER TYPE � 104 02 Changed Conditions
COST COST INCREASE / (DECREASE): $ $ 0.00
The cost adjustment shall include lump sum and estimated totaled unit -priced item costs. Attach a separate sheet of unit price items
including item description, unit of measurement, estimated quantity and unit price.
CHECK APPROPRIATE BOXES PER APPROPRIATE BASIS OF COST CHANGE:
❑ 109.03 Altered Quantities ❑ 109.05(a) Agreed Price ❑ 109.05(b) Force Account ❑ 109.05.02 Delay Costs
PROPOSED COST CHANGE INCLUDES: ® Labor ® Material M Equipment ® Lease Agreement ❑
Subcontractor
Addition 7 day
TIME ADJUSTMENT INCREASE / (DECREASE): (work days) time extension
CHECK APPROPRIATE BOXES PER APPROPRIATE BASIS OF TIME CHANGE:
-Z 108.08(a) Excusable, Non-Compensable ❑ 108.08(b) Excusable, Compensable
NOTE: If Compensable, attach details based on 109.05.1(a) Allowable Delay Costs.
SUPPLEMENTAL INFORMATION
Additional information may be entered by the contractor,
CHANGE ORDER ORIGINATION:
DOCUMENTS AFFECTED:
❑ Contract Specifications (ref. doc name/no.)
❑ Contract Plans (ref. doc name/no.)
❑ INDOT / LPA ® Contractor
CHANGE ORDER AFFECTS DBE PARTICIPATION: ❑ yes Z no (if yes, attach details)
Vi, 101,3P7
CHANGE ORDER REQUEST FORM
CONTRACT NO. R-39514-A
i
i
UPON WRITTEN REQUEST FROM THE ENGINEER,VI ADDITIONAL DETAIL
f
DATE RECEIVED REQUEST FOR August 15, 2019 SUBMITTAL DATE OF August 16, 2019
ADDITIONAL DETAIL ADDITIONAL DETAIL
DETAILED DESCRIPTION / JUSTIFICATION:
(Include location(s), actions of contractor, owner, and other stakeholders, key events and related cause(s), discoveries,
discussions, meetings, and effect on the contract if no action is taken. Also include references to key documents attached
or available to support this change order request.)
Refer to attached letter and meeting agenda notes
PROPOSED SOLUTION — ADDITIONAL DETAILS:
(Include proposed scope of work, means & methods, materials, equipment, utility relocation required, subcontracted
scope and the effect on the contract schedule. Also include references to attached documents including, but not limited
to, sketches, calculations, photos, material information, and submittals and meeting minutes.)
Refer to attached letter
SIGNATURES
Contractor:
Name: (print) Ruben Alvarado
k ✓�.��a
(signature) _ _ Date: 8/15/19
Project Engineer/ upervisor: (signature is to acknowledge receipt of the document and does not signify agreement of the change order)
Name: (print) ' _......... m
(signature)��
.are± Date:
NOTE: The Contractor and PE/S should retain a signed copy of this documentfor record.
CONTRACT NO. R-39514-A
ATTACHMENT: UNIT PRICE ITEMS DETAIL
Attach or paste a unit price item detail.
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 9/10/19 Department Public Works
Name Kyle Silveus..�.�.�........._,,,,, �............................-..�...�.�.�...�.�.�.._.�._.._�........�..._ .�..._....____....
Division/Bureau Engineering
BPW Date 9/24/2019 Phone Extension 9083
N
_Be uired Prior to Submittal to Board
Legal ® Attorney Name: Clara McDaniels
Controller Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ❑ Michael Schmidt
Check the AMRpriate Item Type — Required for All Submissions
g � 0 Proposal M Addendum
Agreement Contract
[� Professional Services [:] Resolution
Bid Opening E] Bid Award Req. to Advertise ❑ Title Sheet
j Quote Opening El Quote Award
Change Order No. 1 0 C/O & PCA No. ❑ PCA
F] Ease/Encroach. ❑ Traffic Control:
El Other:
Roquired Information
Company or Vendor Name
Indiana Dewrtment of Transportation
New Vendor
❑Yes H No If Yes,wA�a rove Purchasing _...
MBE/WBE Contractor
❑ MBE W B E
MBE/WBE Contractor Requested
❑ No [] YesNameoCom an
�r
Safe Routes to School near LaSalle Intermediate and Marquette
Project Name
Primary
Project Number
ENG: 116-040 DES No: 1600076
Funding Source
LOIT Ma'ot r Projects
Account No.
257.0608.431.42.96
Amount
$1,589,000
Terms of Contract
.�........... ...... ............... � �6 - -
80% Federal- 20% Local
Purpose/Description
This change order is a time extension of 6 days only due to utility
delays by AEP. When this change order is approved, it is to be
sent to Scott Randle at American Structurepoint at
srandlestructurepoint.com
Disoersal After
Copy
Original
®
❑ Kyle Silveus
aitlin Stevens, MACOG
❑
❑
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 9/10/19 Department Public Works
Name Kyle Silveus Division/Bureau Engineering
BPW Date 9/24/2019 Phone Extension 9083
rnum'udu'r,�rr�. �'�r' '.�nuimrnx, muomuioi.m ..... muuuuuuuuuuuuumwuuuuvirvunm�u.... u,N r�
_� N� hired Prior to "Submittal to Board_ m _�
Legal ® Attorney Name: Clara McDaniels
Controller ❑ Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ❑ Michael Schmidt
H Agreement
Professional Services
Bid Opening
❑ Quote Opening
® Change Order No. 1
Ease/Encroach.
Other:
LJ Contract
❑ Resolution
❑ Bid Award
❑ Quote Award
E' C/O & PCA No.
E Traffic Control:
Proposal
Addendum
Company or Vendor Name
Indiana Department of Transportation
New Vendor
[ Yes Noo ifYes, Aved by Purchasing
MBE/WBE Contractor
MBE^m�mmm
/W
MBEBE Contractor Requested � an
s l� '�
q No ❑Ye. Nameof Com.,�..near
Safe Routes to School arquette
LaSalle Intermediate and M
Project Name
Prima
Project Number
ENG: 116-040 DES No: 1600076
FundingSource
LOIT Mafor .... _.���_ _w ....�...._...���� _..._�.���.�......._.
,_m Protects
Account No.
257.0608.431.42.96�.............
Amount
.....� ....... .....
$1,589,000 m.����.�.� ..�w ....... ....
Terms of Contract
�0�/ 20% Local
Purpose/Description
This change olyder s time extension of 6 days only due to utility
delays by AEP. When this change order is approved, it is to be
sent to Scott Randle at American Structurepoint at
srandle@structurepoint.com
L Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
„�, �'�
Amount of _._,,
Increase $ 6 Additionals
Da
E] Decrease
$
Previous Amount
....
��_...��... .....-. ...._�............... . .....
1,89,000
Current Percent of Change:
�.....
0
New Amount
$ $1,589,000�..
Total Percent of Change:
o.�.........ww ..,,.... m......
0 /o