Loading...
HomeMy WebLinkAbout5A6 Budget Request (Olive GAC Plant Construction) Redevelopment Commission Agenda Item DATE: September 24, 2019 FROM: Kara Boyles, City Engineer SUBJECT: Budget Increase Request – Olive GAC WTP Which TIF? (circle one) River West; River East; South Side; Douglas Road; West Washington PURPOSE OF REQUEST: Budget increase of $500K for construction of the Olive WTP Improvements for a total of $1,536,000. Specifics: The Board of Public Works recently opened bids for the Olive WTP Improvements. Bowen Engineering Corporation submitted the only bid for $1,796,470, which is approximately $500K over the engineer’s estimate. Engineering has worked with the bidder to value engineer numerous elements of work, reducing the contract cost by ~$500K, bringing the new contract amount closer to $1.2M. Please consider this budget request for an additional $500K in order to award this project to Bowen Engineering Corporation. This project is a critical project for providing clean drinking water to the City’s central pressure zone. It is also beneficial to keep this project moving forward in order to schedule shut down of the plant for construction within lower demand periods of water usage over the winter months. History: This project involves the rehabilitation of Olive GAC plant. The project includes upgrades to chlorination and the fluoride system. The natural gas heating unit is also to be replaced. This request for funding will help the South Bend Water Works complete a portion of their 6-Year Partial Capital Improvement and Replacement Plan. This project was listed as a critical project, and identified in the Indiana Utility Regulatory Commission (IURC) testimony as projects to be funded with TIF in 2018. _________________________Pres/V-Pres ATTEST: __________________Secretary Date: ____________________ APPROVED Not Approved SOUTH BEND REDEVELOPMENT COMMISSION Page | 2 INTERNAL USE ONLY: Project Code: ___________________18J009____________________________; Total Amount new/change (inc/dec) in budget: __$500K___________; Break down: Costs: Engineering Amt: ______$310K_____________; Other Prof Serv Amt_________________; Acquisition of Land/Bldg (circle one) Amt: ___________; Street Const Amt ________________; Building Imp Amt___$1,226,000______; Sewers Amt________; Other (specify) Amt: ________________ ___________________________________________. Going to BPW for Contracting? Y/N Is this item ready to encumber now? _yes___ Existing PO#__________ Inc/Dec $_____________