HomeMy WebLinkAboutResponses to Council Questions - Budget Hearing 2
2020 BUDGET HEARING – WRITTEN RESPONSES TO COUNCIL QUESTIONS
Budget Hearing #2: August 7, 2019
Department of Public Works
Unanswered Council Questions
Why did Traffic Calming increase but Light Up South Bend and Curbs and Sidewalks stay flat?
There has been a tremendous demand for traffic calming in neighborhoods throughout the City, and the engineering division
has a backlog of projects that they do not have funding for. Although the capital funding for Light Up SB has remained at the
2019 level, the operating budget for streetlight tariffs has increased each year to meet the demands of the additional lights.
The City operating costs for 2019 is $133,000 per month compared to $124,000 per month in 2018. The funding request for
the 2020 C&S program is the same as 2019, however, the City will be reconstructing Bendix from Lathrop to the Toll Road,
Olive from SR23 to Tucker, and Ironwood, Rockne, and Corby intersection. Each of these projects has a significant amount of
new sidewalk in 2020.
How many streetlights total in the City? City maintained – 3,015
AEP maintained – 9,518
How did we get a mixed (City/AEP) system? We believe that it’s due to allowing design preference in the different
neighborhoods and areas. We do not have a definitive answer, but most of the decorative lights are City owned and
maintained.
How do Council members ensure that they know how to help residents report out streetlights? Residents should contact
311 to report streetlight outages. There is information on the City webpage on how to report to 311. There is also a link to
an AEP Outage Report form that they may use if it’s an AEP light that they wish to report. The City webpage also gives tips to
help identify whether the light is City-owned or AEP-owned.
Do we take it for granted that AEP is repairing the streetlights when they need to? Yes.
What is the timing of the County’s Douglas Road widening project? Construction/Letting is December of 2020.
Is there a way to get funding for the lift station relocation? Not at present.
What are we doing about potholes in business alleys? Grading and/or patching. Call 311 to report any specific areas that
need patched.
Can you give us the total capital projects supported by TIF and the ending TIF balances? This question is best answered by
DCI.
Can you give us the total capital projects supported by Fund 642 and the ending balance?
$6,250,000 with $114,691 as the ending balance
Downtown cross streets - $1.5 million. At what point will we move away from downtown? As part of the master planning for
the Downtown Conversion of Main Street and MLK back in 2014-15, cross-streets were contemplated and discussed with
the public as the next phase.
Water meter replacement. $800,000 Is the cost being incurred by the City?
This cost is built into the water rates and charges. The City purchases meters through the water budget, from revenue
generated by monthly rates and charges to users. When a meter is damaged (for instance because building is without heat)
or lost, the customer is responsible for replacement costs. Any routine failure or normal replacement is covered within the
monthly rates and charges.
Can you clarify the participation metric for yard waste?
The metrics come from Naviline. The percentage of utility customers (est. 39,000) that are being charged for yard waste. In
2018 it was 51% and so far in 2019 we are at 61%.
Where is the trash transfer station located?
Green Tech Transfer Station (Republic) 2500 Green Tech Drive, BETW Ewing & Eckman behind Ball Park, South Bend, IN.
The mayor himself acknowledged in his State of the City Address this year that we are not on a sustainable roads cycle. For
the administration to then budget $1MM less for roads in 2020 than in 2019 is in direct contradiction to the mayor’s own
statement AND the citywide survey which indicated that roads and infrastructure is a top priority.
Road funding is a top priority for the City, and the allocation of the annual amount is $550,000 less than what was budgeted
in the 2019 operating budget. In addition, the Council appropriated an additional $500,000 in supplemental road funding in
2019. However, this is not inclusive of all of the road funding going into South Bend streets in 2020. The other component of
road funding comes through Federal Aid Grants. The City has successfully requested funding for 3 LPA projects that will
start in 2020; Bendix Avenue Replacement from Lathrop to the Indiana Toll Road, Corby/Ironwood/Rockne Intersection
Improvement, and the Olive Street Replacement from SR23 to Tucker Drive. The total estimated cost for the 3 additional
projects is $12,000,000.
Eric said 1/15th of the water meters are replaced every year because they have about a 15 year lifespan. What is the lifespan
of a road and why don’t we take a similar approach?
The lifespan of a road varies depending on the wearing surface(i.e. asphalt or concrete) and on other considerations such as
drainage, soil conditions, subbase conditions, type and amount of traffic… On average, a general assumption is 15-25 years
for an asphalt road and 20-40 years for a concrete road. The City has funds designated for road maintenance and
replacement from two funds: Motor Vehicle Highway and Local Road & Street. These are primarily funded by gas tax and
vehicle registrations. The City does not control the amount of funding that comes into these funds, so we use the allocation
as best we can to meet the most urgent road demands in the City.
The public works budget is raising the wages for two positions that, in Eric’s words have been open for “quite some time.” If
we have been operating sufficiently without those positions for that long, do we really need to fill them let alone raise the
salary? We are being presented with a total budget that spends $10MM less than last year but still has a $10MM deficit. We
can’t keep spending down reserves and the best way to control spending is to look at our salaries and wages which again the
mayor mentioned that we are on a soft hiring freeze?
Both positions are necessary for normal operations of the water distribution system. The position that has been open since
December of 2018 is the Distribution System Operations Manager. We are requesting to change the title and wages due to
the high level of responsibility. This is the position in the City that is responsible for maintaining all of the City’s Water lines,
valves, hydrants, meters, service requests, backflow testing, water line locates, and service line repair program. The
Distribution Operations Manager (Director) is critical to sustainable administrative, managerial/supervisor roles within the
Utility and it’s unionized workforce. This is a 24/7 responsible position. The distribution manager is located at the Olive Road
well field, at a remote site not connected to the Water Treatment plants or the Customer Service and billing staff. All the
more reason why we need the position. We currently have other staff members trying to fulfill some of these duties while we
look for a candidate. It is not a great arrangement. The union staff has been restless. They want their needs met. There is no
way we would want this to continue on. One of the reasons for the position not being filled is low wages for the level of
responsibilities for this position. This is a very demanding position which requires 100’s of after hour emergency calls. Water
is necessary to life, health and safety of the City. We have to have a responsible person ensuring the daily 24/7 needs are
being met.
The second position being adjusted is due to a recent retirement. The Distribution Records Drafter title is a dated
description of the skills and demands of this position. This is due to a 25+ year employee being in this position, and not
sufficiently upgrading the job title, duties, and salary to reflect the needs of the organization 25+ years later. There are many
fewer positions in the water division than there were even 10 years ago, and as a result many positions have taken on greater
responsibilities. The person in position is one of two that handled new tap permits for connections to the water system,
document these on water maps, and provide inventory and purchasing controls for the distribution system needs, in addition
to other duties and responsibilities.
Yard waste nowhere near pays for itself. Can we move yard waste to every other week pickup? What would that save? We
could calculate the savings from eliminating 2 positions and some modest savings on gas costs. However, it is more difficult
to estimate the extra burden on the crew that does extra pick-ups, the trash crew or the crew picking up illegal dumping
because the waste will end up somewhere in the system. If we go to every other week, we believe that the yard waste extra
pick-ups will increase significantly. We do not charge for the extra pick-ups, but we would need to add staff back to handle
this increase unless we also eliminate the extra pick-ups.
I don’t understand how we are using SSDA TIF funds for the Prairie Ave. water main which is well outside the SSDA. Some
clarification on that would be great. The new Prairie Avenue water main will close a crucial loop in the City’s distribution
system. In this area, the loop will provide reliability and redundancy to the south pressure zone which serves the SSDA TIF
area, and which is fed by the South Well Field located in the SSDA.
Questions from the Public
Why do temp speed humps cost more than permanent? A recent quote for temporary speed humps was higher than the cost
of permanent speed humps; however, the temporary speed humps will be able to be removed and replaced in multiple
locations for temporary demonstrations as needed.
Why are they removing the bathroom in Walker Field Park? What is the plan for bathrooms in neighborhood parks? This
question is more appropriately directed towards VPA.
Cost vs. benefit of taking side streets back to brick roads? We looked at the benefits vs. costs for rebricking a portion of
LaSalle(because some of the bricks were still intact) and the benefit/cost ratio for the asphalt street was much greater than
the b/c for redoing the brick. Typically the capital cost for installing a brick street is 5-10 times more than resurfacing with
asphalt.
Why are there so many areas where we spend down? (red ink) There are times that we purposely spend cash reserves to
meet operational, maintenance, or capital demands. All funds will retain positive balances.
Is Olive Street designed for trucks with steel coils? Yes, Olive is a truck route.
Curbs - paved right over the curbs; there is no curb, hence there is no water drainage, is there going to be remediation?
Please provide specifics. Tell residents to call 311 with drainage concerns.
Filtration - her water smells like pool water?
Chlorine is added to drinking water to meet safe drinking water standards, and to make sure it is safe when it arrives to
people’s homes. The amount added to drinking water is much less than what is maintained in pools, but some people may be
more sensitive to the chlorine smell than others. For any water quality concern, including concern about a chlorine smell, we
encourage residents to contact our Water Quality staff at 574-235-9670. We can arrange a visit, and also discuss ways that
the situation may be improved.
What % of sewers are cleaned now? Approximately 11%. We have a five year rotation for cleaning the sewer lines in most
need.
Pilot program - scan roads for potholes; what happened with these? Need additional clarification on the question.
Has there been an increase in minority contractors? This question is best directed to the Office of Diversity & Inclusion.
How many bonds are on the horizon? Other than potential equipment lease bonds, Public Works does not have any bonds
anticipated for 2020.
Renovation of bathrooms
Opioid crisis means a lot of people doing drugs in parks, would be nice to have sharps containers in bathrooms
Will there be charging stations for phones? These questions are best answered by VPA Department.
Sustainability - 50 buildings in the city, study all the City roofs - can we improve insulation, have solar panels, green roofs, etc.
The Sustainability Office does not have an engineering or capital budget, but each time a department requests a roof project,
it is evaluated for sustainability opportunities. These opportunities must typically be funded outside the capital request for
the roof – namely through grants or via private projects, and very few grants have been available for sustainability upgrades
to municipal buildings.
However, there are three city facilities with operable solar arrays (Century Center, SBFD Station 4, and SBFD Station 9), and
two in the works (SBFD Central Fire and Howard Park). There is one City facility with a green roof (Potawatomi Greenhouse
entrance).
Breakdown of professional services - who is getting these projects? This is public information that can be retrieved from the
City’s website: http://docs.southbendin.gov/weblink/Browse.aspx?dbid=0&startid=96984&row=1&cr=1. Each fiscal year
has a folder for Agreements/Contracts/Proposals.
Backflows that would help with flooding - where are we on this? If this is asking about the basement backflow valve
prevention program, The City continues to offer this program at a 50% reimbursement to residents. Kieran Fahey is the
contact for this project.
What projects have had cost overruns that were underfunded? This is also public information that can be retrieved from the
City’s website: http://docs.southbendin.gov/weblink/Browse.aspx?dbid=0&startid=96984&row=1&cr=1. Each fiscal year
has a folder for Change Orders.
In light of the decision to cut the stormwater funding, the amount of the stormwater funding is too small, why are we
spending on Boomer instead of stormwater? Stormwater funding was not cut for 2020. Internal accounting policies require a
25% cash reserve. Stormwater funds were not used to pay for Boomer.
The guardrail in North Shore triangle is still down. Will it be reinstalled? When? Guardrails must be repaired/installed by
certified personnel, and we do not have any on staff. Repair/replacement will have to be contracted out.
Has money been allocated to address the impact of ND and Holy Cross activities on the hill? How much? This is a question for
ND and/or Holy Cross. The City continues to work with them on a resolution. Any work will likely be done in conjunction
with the Coal Line trail project that will be crossing this property and creating a boundary between the hill and the
residential property.
Has money been allocated to complete all LFA recommendations in 2020?
See recommendations below in italic and the response to each of the recommendations in the LFA study:
1. Evaluate the current design criteria for determining sewer capacity and stormwater storage.
City is implementing a new standard for this requiring new designs meet a 25-year, 24 hour event. This is up from a ten-year,
six hour event.
2. Continue to offer residents the Basement Valve Program
The City continues to offer this program. Since the event there were 21 applications for the BVP from the NST. All applications
received were approved. Six applicants abandoned their applications, despite being approved. 15 (of the 21) completed the
program at a total cost of $36,458. The city reimbursed 50% of that amount, $18,229.
3. Place particular emphasis on the neighborhoods featured in this report for sewer cleaning cctv’ing etc.
In the near aftermath of the event, between March and July of 2018 the Sewer Department videoed, and where necessary,
cleaned almost 30,000 feet (>5.5 miles) of sanitary and storm sewer in the NST. Undertaking this required four staff members.
4. Research the possibility of a notification system along multiple media platforms to provide residents with notification and
information during flood events.
With assistance and expert guidance from the US Army Corps of Engineers and the US Geological society this project has
commenced and is in a data gathering and modelling phase. The tool will be known as a “flood inundation mapper” and is
expected to be completed in the summer of 2020. Work completed so far included the installation of a river depth gauge. The
gauge is connected to the internet and is freely available to the public. It is accessible online at the following address and shows
the river height in feet:
https://waterdata.usgs.gov/in/nwis/uv/?site_no=04101225&PARAmeter_cd=00065,00060,62614,00010. I would also like
to point out that if you go to the website you can click on the WaterAlert link underneath the graph:
https://water.usgs.gov/wateralert/subscribe2/?site_no=04101225&parm=00065. This will allow you to sign up to receive
email or text alerts when the river gage reaches a certain height. This can give individuals advance notice of potential flooding
events.
5. In certain circumstances FEMA provides grant assistance for the purchase of homes that are within particular flood zones. The
City should research these FEMA requirements and ascertain their applicability to South Bend.
City did not research this. This FEMA program would mean the razing of homes; so it is important that this only be further
studied if there is a residential interest in doing so, and the city has not received notice of such interest.
6. Evaluate the 12-inch throttle pipe in the Riverside Drive (South of Bartlett) area to see if it could be increased to allow more
flow to leave the area quicker. The effect on the downstream system should be evaluated along with the actual impact on the
Riverside area.
This has and is still being studied. Two possibilities have been identified and are being considered in the City’s long-term sewer
plans.
7. Further research to determine that the 10-inch sewer along Angela is appropriately sized for the sanitary flow it conveys (due
to the larger pipes flowing into the 10-inch pipe).
Assessment of locally gathered sewer data did not indicate a bottleneck at this specific location.
8. Discuss options to control runoff with the private landowner(s) of the 40-acres that is contributing stormwater runoff to the
area north of Angela near Iroquois and Marquette.
The city has been in discussion with this property owner, the University of Notre Dame. An update from the University as to
their plans will be the most appropriate action. The University has been in discussions with a private utility (AEP) regarding
improvements that they, AEP, may be making there. City staff hasn’t been privy to those discussions. For that reason, an
update from the University regarding their privately held property would be most appropriate. The land is privately owned
and is not within the city.
9. Install backflow prevention measures on the stormwater outlets to the St. Joseph River within the Northshore Triangle.
Currently being designed by Abonmarche. Construction likely to be spring/summer 2020.