HomeMy WebLinkAboutChange Order No 2 - VPA Restroom Remodeling Project No 118-043R - Michiana Contracting Incam
1316 COUNTY -CITY BUILDING llu
PHONE 574/ 235-9251
227 W. JEFFERSON BOULEVARD
l a int
% FAX 574/ 235-9171
SOI IT" BEND_ INDIANA 46601-1930
CITY OF SOUTH BEND PETE BUTTIGIEG, MAYOR
BOARD OF PUBLIC WORKS
September 10, 2019
Scott Kirkpatrick
Michiana Contracting, Inc.
7843 Lilac Road, PO Box 929
Plymouth, IN 46563
RE: Change Order No. 2 - Venues, Parks, and Arts Restroom Remodeling — Project No,
118-043R
Dear Mr. Kirkpatrick:
The Board of Public Works, at its meeting held on September 10, 2019, approved the above
referenced Change Order for an increase of nineteen (19) days, bringing the current contract
completion date to September 18, 2019.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
GARY A. GILOT GENEVIEVE E. MILLER ELIZABETH A. MARADIK LAURA L. O'SULLIVAN THERESE J. DORAU
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO:
SUBJECT OF CHANGE ORDER:
8/12/2019
118-043R
VPA Restroom Remodelin
1 /22/2019
2
PCR #2-Time extension
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
CONRTOR
Contractor Sig ,
3 N ajficX,
Printed Name and Title
Michiana Contracting Inc.
Company Name
7843 Lilac Rd. PO Box 929
Address
Plymouth, IN 46563
City, State, Zip
oi.y45N.I
1865
$ 490, 000.00
$ 35,250.82
$ 525,250.82
Increased
Decreased $ 0.00
$ 525„250.82
0.00 %
7.19 %
8/30/2019
0 days
19 days
9/18/2019
CONSTRUCTION MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLC W RKS
Approved Date: i d �v
Gary A. Gilot, President
Genevi ve E. Miller, Member
w�e rar &A,
DEPARTMENT OF PUBLIC WORKS
*" DIVISION OF ENGINEERING
kdipti
Project Number: 118-043R
Project Name: PA Restroom Remodeiing Change Order #: 2
DATE INITIATED: 8/12/19•
BPW DATE: 9/10/19
Brief Summary of Change Order; (Construction Change, Alternative, Substitution, Differing Instructions, Out of Scope, Etc.).
Time extension request due to unforeseen conditions.
Attachments: (List documents support change — required)
Formal request from contractor.
PCR#002.
Amount of ❑ Increase / ❑ Decrease:;
�1
Categories (Pick One):
Previously approved Change Order(s): $ Mt.t ❑ Scope of Work
--.............
-. 8 Differing Site Conditions, Changed Conditions
Current Percent of Change;
. . . . . . — % ❑ Conflicted Specifications and Drawings
El Failed Materials
New Total Amount: $
❑ Error
.wwwww
❑ Omission
Total Percent of Change: _��
% ❑ Final Quantity Adjustment
Funding Secured From: Axrle.s Zpy&Z
(filled out by PM)
RECOMMENDED BY:
Greg McGowan
Project Inspector (Print Name)
(Signature)
(Date)
REVIEWED BY:
n'
9
Construction Manager (Print Name)
(Signature)
(Date)
APPROVED BY:
r r eeL"v-)
r
Q q-19
Project anager (Print Name)
(Signature)
(Date)
APPROVED BY:
u
City Engineer (Print' Name,y
g
(Smgnatd e)
(Deice) d d
0
Mailing Address
P.O. Box 929
Plymouth, IN 46563
8/28/19
City of South Bend
Mr. Greg McGowen
227 W. Jefferson Blvd.
South Bend, IN 46601
RE: Project No. 118-043R Venues, Parks and Arts Restroom Remodeling Contract Time
Extension Due to Design Issues
Mr. McGowen,
As you are aware, Michiana Contracting has encountered numerous issues throughout this
project that have caused delays. Below is a brief summary of these delays.
Pinhook Park: Plumbing issues were discovered in March following DA Dodd's arrival at this
location. Following an on -site meeting it was determined that additional work was
requested which included:
• Demolition of the existing cast iron pipe (lead joints ) and carriers
• Furnish and install new carriers for the water closets in the new locations.
• Furnish excavation as required for the underground connections as required.
• Furnish and install new drain and vent piping in chase (WE intend to reuse existing water
piping where possible)
• Cut concrete floor were needed in chase and repour.
Pricing for this additional work was submitted on 4-1-19 and again on 6/7/19. A change order
for this work wasn't approved until 7/9/19. As a result, work at this location was delayed by 100
calendar days.
Kennedy Park: When DA Dodd arrived on site to check they turned the water on to check the
existing system. Upon doing so it was determined that the both the existing water and sewer
piping was failing. Following an on -site meeting it was determined that additional work was
requested which included:
• Disconnect existing chase piping and prepare piping for selective demolition. Run a camera down
the existing drainpipe and verify the condition prior to connecting new pipe.
• Furnish and install new sanitary piping (PVC) connect to existing as available.
• Furnish excavation for new underground sanitary piping connection.
MICHIANA CONTRACTING, INC. - PO Box 929 Plymouth, IN 46563 - Tel: 574-936-8613 Fax: 574-936-6201
.nnichiianacontracti g.,&R�wLi
• Furnish and install new aboveground sanitary waste and vent piping (PVC) connect to existing
venting as available.
• Furnish and install new domestic water piping (copper with mechanical press fitting) connect to
existing as available.
• Plumbing fixture modifications to be included in the base pricing with the exception of the
replacement of the "urinal" indicated as a "toilet to remain" to become a standard height toilet
in the women's restroom.
• Plumbing chase block wall will have to be tore down to make way for plumbing repairs and then
rebuilt
Pricing for this additional work was submitted on 6/7/19. A change order for this work wasn't
approved until 7/9/19. As a result, work at this location was delayed by 33 calendar days.
Boehn Park: The existing incoming water supply line was inadequate to properly operate the wall
mounted flush valve toilets specified on this contract. As a result, we were directed to switch to
tank type floor mounted toilets. This required additional concrete floor demolition and
replacement. This change resulted in a 14-calendar day delay.
While each of these issues created lengthy delays to our schedule, we did our best to re -arrange
our schedule to keep the project moving forward and minimize the overall delay to the project.
Since these delays were not caused or created by Michiana Contracting and are solely due to
design changes and additional work, we are respectfully requesting a contract time extension of
19 calendar days. This is significantly less days than our controlling items of work were impacted.
Your cooperation and understanding in this matter is appreciated. Please let me know if you
have any questions or need any additional information.
Respectfully,
s -t-k KW- 4j,4vi ce
Scott Kirkpatrick
President
Michiana Contracting
MICHIANA CONTRACTING, INC. - PO Box 929 Plymouth, IN 46563 - Tel: 574-936-8613 Fax: 574-936-6201
ww michianacgntraLc, cr p
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date September 3, 2019
�.,,,,,,�,�.����....A..�a....�...�.�...�............w Department Public
Name.............._..............................aScott ....Kree..er...__...... Works
BPW Date September 10 2019 Phone Extension 9245
le uirc Prior to Submittal to Board
BPW Attorney E] Attorney Name _ Clara McDaaniels
Dept. Attorney Attorney Name
Purchasing Michael Schmidt
Item"j:ype -- �q.tdred r All Submissions
H Professional Services Agreement e Contract
Open Market Contract
Amendment/Addendum
E]
Bid Opening
Bid Award
R
Quote Opening ❑j
Quote Award
❑
Proposal Opening
C/O & PCA No.
®
Chg. Order, No. 2
Traffic Control
E] Other:
qui ed Information
Company or Vendor Name Michiana Contracting, Inc.
New Vendor
MBE/WBE Contractor
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
" Proposal
El Special Purchase, QPA
[] Req. to Advertise
Reject Bids/Quotes
❑ PCA
Resolution
Ease./Encroach
❑ Title Sheet
0 Yes If Yes, Approved by Purchasing
® No
❑ MBE Completed E-Verify Form Attached El Yes
❑ WBE ❑ No
VPA Restroom Remodeling., ... . ............. ____ ..................... _ - -----
118-043R
.......... ......... .........
H.....r.... _.
471 1138-452.42-01
Parks Bond I
Time extension on Contract
For Chau e Crders Only
Amount of ❑ Increase.....
❑ Decrease ($ )
Previous Amount
$
Increase
Current Percent of Change:
Decrease (y %
New Amount
w
$ m.._...........................................................a,, .....�......�.�..�.�...�.
Increase
Total Percent of Change:
Decrease %
Time Extension Amount:
19 Davy
New Completion pleb Date: 9/
.mm._t ,,.. m,,... ....� .. 18/19
m ....._.. 6......_