April 23, 2019
Tim Morey
Ziolkowski Construction, Inc.
4050 Ralph Jones Drive
South Bend, IN 46628
PHONE 574/235-9251
FAx 574/235-9171
RE: Change Order No. 11 — Erskine Clubhouse Renovation — Project No. 116-108
Dear Mr. Morey:
The Board of Public Works, at its meeting held on April 23, 2019, approved the above
referenced Change Order for an additional sixty-three (63) days, bringing the current contract
completion date to May 24, 2019.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
GARY A. GILOT GENEVIEVE E. MILLER ELIZABETH A. MARADIK LAURA L. O'SULLIVAN THERESE J. DORAU
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO:
SUBJECT OF CHANGE ORDER
4/15/2019 0:00:00
116-108
Erskine Clubhouse Renovation
9/27/2018
11
PCR #11-Request for Contract Time Extension
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
ownd;z"M
1° -
Contractor Signature
Printed Name and,Title
Ziolkowski Construction, Inc.
Company Name
Address
City, State, Zip
�
$
0.00
$
0.
Increased
.........
Decreased
$
0.00
$
0.00
0.00 %
20.35 %
.......
3/15/2019 0:00:00
.... ._
0 days
63 days
5/17/2019
D
CONSTRUCTION MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC OR S
Approved Date: '), xe
ary A. Gf0t, President
Genevieve E. Miller, Member
Elizabeth A. Maradik, Member
Therese J. Dorau„ Mimber
ler, Member
ZIOLKOWSKI
, Construction, Onc.
< General Construction & Design/Sulld
ufuullkflinu 'pmoumryjlRoaklliions p" tlVur�, N74
April 15, 2019
City of South Bend
Department of Public Works
Attn: Alicia Czarneeld
300 W. Jefferson Blvd., Suite # 200
South Bend, IN 46601
Reference: Erskine Clubhouse
Request for Contract Time Extension
Alicia,
Ziolkowski Construction is requesting for a contract time extension for the Erskine Clubhouse
project. We are requesting 63 additional calendar days due to the following changes and delays.
Additional demo (unforeseen).
Lead and Asbestos work needing done.
Unforeseen Septic Tank removal.
0 Kitchen/Bar added.
0 Restroom Extension added.
Unforeseen fuel oil tanks needing removed.
Rework existing kitchen feeders (existing panel was not to code).
Add Additional exterior windows to Pro Shop.
Additional Plaster wall and ceiling repairs.
Additional wood flooring repairs.
Additional IT Data work.
Revised lighting layout.
Added floor mop sink in closet.
• Revised spiral duct work (re-routing).
If you should have any questions, please call.
Respectfully submitted,
Ziolkowski Construction, Inca
Tim Morey
Project Manager
CC: Toy Villa, Kyle Silveus, Tim Koziel
TM/lun
't 't ! a11,a�;� Jones Dhve pWO Bgnd,.1141 4662 t Phone (� 74) 'Pw td I "1 t'ax q a��� �4„o"N of
Committed to professionalism and excellence for the benefit of our clients, employees, and shareholders
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date
Name
4/16/19
Silveus
Department Engineering .................m..........__
BPW Date 4/23/19 Phone Extension 9083
.. 1. WW,W'MM�'@'MIMIMIMI�M.9VWWWWWWWWWWWWWVIVIVN'VWIA�PtlIVIVPoWIVWW'i�Wl MIDI NIIIIIIIINIINIIIIIIIIIIINIIINIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIW"J�IP.X�NMNI�W'AWPMf�MYY@f IDIDID1�flAY,GM�k,�iW�I�WMNI�IIWNRIp:�n!M�MI�F�40f9�
..........................�.......—.......—.... ....... .......... ........ �,..................mm...........................
Rquir�d .Prior to ITSubmittal to Board
Legal ❑ Attorney Name Clara McDaniels
Controller ❑ Controller review is required for all Contracts $5,000.00 or more anc
greater than one year in length per the City Purchasing Policy
Purchasing Michael Schmidt
Check the
Agreement
Professional Services
Bid Opening
EJ Quote Opening
® Change Order No. 11
El Ease/Encroach.
0 Other:
iro riate Item T e -
[:1 Contract
E] Resolution
❑ Bid Award
❑ Quote Award
❑C/O &PCANo.
_
❑ Traffic Control
for All Submissions
I Proposal Addendum
❑ Req. to Advertise ❑ Title Sheet
ired Information
❑ PCA
Company or Vendor Name Ziolkowski Construction Inc.
New Vendor [] Yes E No ❑ If Yes, Approved by Purchasing
MBE/WBE Contractor [ ] MBE FWBE
MBEM/BE Contractor Requested ❑ No ❑ Yes Name of Company
Project Name Erskine 116-10Clubhouse Renovation
ProjectNumber 8..............................�..�.m.............................................. ..._...._
Funding Source
Account No.
Amount N/A
Terms of Contract
Purpose/Description Time Extension for Misc. Unforeseen Conditions — 63 Calendar
Days Moves Substantial Completion to 5/24/19
❑ Required Contractor's Certification Form Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-)/eify, Iran, etc.
Required For Change Orders Only _.
Amount of ❑ Increase N/A
❑ Decrease $
Previous Amount
Current Percent of Change, N/A aaa �a
New Amount
Total Percent of Change:
Dispersal After Approval
Copy Original
® ❑ Kyle Silveus
® ❑ Patrick Sherman....................................�.....�.�..........�.