HomeMy WebLinkAboutNo. 3026 approving/authorizing the execution of an amendment to the addendum to the master agency agreement (Olive Road Right-of-Way Acquisition - Supplement #3)0 RESOLUTION NO. 3026
RESOLUTION OF THE SOUTH BEND REDEVELOPMENT COMMISSION
APPROVING AND AUTHORIZING THE EXECUTION OF AN AMENDMENT
TO THE ADDENDUM TO THE MASTER AGENCY AGREEMENT
(Olive Road Right -Of -Way Acquisition - Supplement #3)
WHEREAS, effective January 1, 2012, the South Bend Department of
Redevelopment, acting by and through its Redevelopment Commission (the
"Commission ") and the South Bend Board of Public Works (the "BPW ") entered into a
Master Agency Agreement which authorized the BPW to act as agent for and on behalf
of the Commission for certain projects during 2012; and
WHEREAS, effective January 1, 2012, the Commission and the BPW entered
into a Master Agency Agreement which authorized the BPW to act as agent for and on
® behalf of the Commission for the limited purpose of contracting for and managing the
completion of existing Projects; and
WHEREAS, pursuant to the Master Agency Agreement, the Commission added
the Olive Road Right -Of -Way Acquisition to the Master Agency Agreement by way of
an Addendum on February 19, 2010; and
WHEREAS, the Commission amended the Addendum with Supplement #1 by
way of Resolution 3024 on April 24, 2012; and
WHEREAS, the Commission amended the Addendum with Supplement #2 by
way of Resolution 3025 on April 24, 2012; and
WHEREAS, the Commission desires to amend the Addendum by way of this
Amendment.
0 NOW, THEREFORE, BE IT RESOLVED by the South Bend Redevelopment
Commission as follows:
,,. Section 1. The Commission hereby approves the Amendment to the
Addendum to the Master Agency Agreement (Olive Road Right -Of -Way Acquisition -
Supplement #3) and hereby authorizes its execution in substantially the form attached
hereto with such changes as the Commission may deem necessary or appropriate upon
the advice of counsel, said execution thereof to be conclusive evidence of the
Commission's approval of such changes. The Clerk is hereby directed to file a copy of
this Amendment to the Addendum with the BPW.
Section 2. This Resolution shall be in full force and effect after its adoption
by the Commission.
Section 3. Commission staff members are authorized to execute on behalf of
the Commission any documents necessary to carry out the intent of this resolution.
ADOPTED at a meeting of the South Bend Redevelopment Commission held on
April 24, 2012, at 4:00 p.m., in Room 1308, County -City Building, South Bend, Indiana
46601.
ATTEST:
� Z 4�4�
Donald Alford, Sr., cretary
South Bend Redevelopment Commission
CITY OF SOUTH BEND,
DEPARTMENT OF
REDEVELOPMEN
Marcia I. Jone , President
South Bend Redevelopment Commission
AMENDMENT TO THE ADDENDUM TO THE
MASTER AGENCY AGREEMENT
(Olive Road Right -Of -Way Acquisition - Supplement #3)
3026 -11
This Amendment to the Addendum to the Master Agency Agreement (this
"Amendment "), made and entered into as of the 8th day of May, 2012, by and between
the South Bend Department of Redevelopment, acting by and through its Redevelopment
Commission (the "Commission ") and the City of South Bend, Indiana, a municipal
corporation duly organized and existing pursuant to the laws of the State of Indiana,
acting by and through its Board of Public Works (the "BPW ") for purposes of the
Commission designating the BPW to act as the Commission's agent to undertake the
Olive Road Right -Of -Way Acquisition - Supplement #3 (the "Project ").
WHEREAS, effective January 1, 2012, the Commission and the BPW entered
into a Master Agency Agreement which authorized the BPW to act as agent for and on
behalf of the Commission for certain projects during 2012; and
WHEREAS, effective January 1, 2012, the Commission and the BPW entered
into a Master Agency Agreement which authorized the BPW to act as agent for and on
behalf of the Commission for the limited purpose of contracting for and managing the
completion of existing Projects; and
WHEREAS, pursuant to the Master Agency Agreement, the Commission added
the Olive Road Right -Of- -Way Acquisition to the Master Agency Agreement by way of
an Addendum on February 19, 2010
WHEREAS, the Commission amended the Addendum with Supplement #1 by
way of Resolution 3024 on April 24, 2012; and
the Commission amended the Addendum with Supplement #2 b
WHEREAS, PP Y
Cway of Resolution 3025 on April 24, 2012; and
WHEREAS, the Commission desires to amend the Addendum by way of this
Amendment.
NOW, THEREFORE, in consideration of the mutual covenants and promises
contained herein, and for other good and valuable consideration, the receipt of which is
hereby acknowledged, the BPW and the Commission agree as follows:
1. The Commission hereby empowers and appoints the BPW, pursuant to the
Master Agency Agreement, to act as the Commission's agent for the limited purpose of
contracting for and managing the completion of the Project, the scope of said Project
being originally described in "Exhibit A ", amended by Supplement #1 as described in
"Exhibit B ", amended by Supplement #2 as described in "Exhibit C ", and now amended
• as described in "Exhibit D ", attached hereto and made a part hereof.
2. All of the terms and conditions of the Master Agency Agreement shall
control this appointment and this Addendum shall be attached to the Master Agency
Agreement.
3. Commission staff members are authorized to execute on behalf of the
Commission any documents necessary to carry out the intent of this resolution.
IN WITNESS WHEREOF, the undersigned execute this Addendum to Master
Agency Agreement to be effective as of the date first written above.
(Signature Page Follows)
C7
to
ATTEST:
South Bend Redevelopment Commission
ATTEST:
Linda Martin, Clerk
CITY OF SOUTH BEND,
DEPARTMENT OF
REDEVELOPMENT
South Bend Redevelopment Commission
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
Gary Gilot, President
Don Inks, Member
Kathryn Roos, Member
u
F.xhihit "A"
OLIVE ROAD RIGHT -OF -WAY ACQUISITION
See attached Acquisition Information prepared by DLZ, Inc.
and approved by the Board of Public Works on February 22, 2010
:7
C7
c
ADDENDUM TO
MASTER AGENCY AGREEMENT
(Olive Road Right -Of -Way Acquisition)
This Addendum to Master Agency Agreement (this "Addendum"), made and
entered into as of the 22nd day of February, 2010, by and between the South Bend
Department of Redevelopment, acting by and through its Redevelopment Commission
(the "Commission ") and the City of South Bend, Indiana, a municipal corporation duly
organized and existing pursuant to the laws of the State of Indiana, acting by and through
its Board of Public Works (the "BPW ") for purposes of the Commission designating the
BPW to act as the Commission's agent to undertake the Olive Road Right -Of -Way
Acquisition (the "Project ")
WHEREAS, effective January 1, 2010, the Commission and the BPW entered
into a Master Agency Agreement which authorized the BPW to act as agent for and on
behalf of the Commission for certain projects during 2010; and
WHEREAS, pursuant to the Master Agency Agreement, the Commission desires
to add the Olive Road Right -Of -Way Acquisition to the Master Agency Agreement by
way of this Addendum.
NOW, THEREFORE, in consideration of the mutual covenants and promises
contained herein, and for other good and valuable consideration, the receipt of which is
hereby acknowledged, the BPW and the Commission agree as follows:
The Commission hereby empowers and appoints the BPW, pursuant to the
Master Agency Agreement, to act as the Commission's agent for the limited purpose of
contracting for and managing the completion of the Project, the scope of said Project
(W being more specifically described in "Exhibit A ", attached hereto and made a part hereof.
c:
2. All of the terms and conditions of the Master Agency Agreement shall
control this appointment and this Addendum shall be attached to the Master Agency
Agreement.
3. Don Inks or Jeff Gibney is authorized to execute on behalf of the
Commission any documents necessary to carry out the intent of this resolution.
IN WITNESS WHEREOF, the undersigned execute this Addendum to Master
Agency Agreement to be effective as of the date first written above.
ATTEST:
Nancy N. Kii , Secre y
South Bend Redevelopment Commission
ATTEST:
i da Martin, C rk
CITY OF SOUTH BEND,
DEPARTMENT OF
REDEVELOPMENT
Garcia 1. Jone rest ent
South Bend Redevelopment Commission
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
/t h-t��
Gary Gilot, President
,-
Car ittrell, Member.
n Inks, Member
A
Exhibit "A"
The Olive Road Right -Of -Way Acquisition Project consists of the acquisition of
parts of sixteen (16) parcels in the corridor between Lincoln Way West and Nimtz
Parkway /Old Cleveland Road. The property acquisition is mainly located on the
east side of Olive Road with one parcel acquisition located on the northwest corner
of Olive and Lincoln Way West.
Sec attached Right -Of -Way Tracking Sheet for specific information about the
appraised value of each parcel A map of the target acquisition area identifying each
parcel has also been included with this Exhibit.
C
A
I
1
1
it
I
�1 g
1 Ij
1
I
c I I i M (NON 3DIUb3S 1VX1
.�I y
0
IL a
za
�a
I m�
Ig '.
� K
_Z
mW
O� O
9 O�
� O
v
I `
A
D
O
v
lc
- - -� -_ _- - _- _ --- - -- S
iI I I
1 9 -�I-
toy �I3 \Zl/ N N1 7 u I_�_
to I .I l
g x � � j_
_ ILL I -- _ �R373'di7T _ � — — — — — — \N M u
rL to
�m
o�
O ° p
W
- - - -_. aW � (9908 _— _— — - - - -- _ _� - - - - — — I T ---- - - - - - -- N o Z
O �
----- -. - - -- -- �._ —. -- ------ _— _�_ - -- z VI J
- I
CL
� _ _ ____ __�� ---- - - - - -- �
�o
�i _____
r ___
- - - - --�— _
— — UO
a�
— M�ISVI'.'----- - - - --1 WW
— —
N !s I g o
MQ
ES
o �
4 ;
a
I Q5 .r
m J I 5 Me 30M3S TVD01
C+1
C7
s=
o ° E
o
•
Exhibit "B"
OLIVE ROAD RIGHT -OF -WAY ACQUISITION - SUPPLEMENT #1
See attached Letter Agreement for Professional Engineering from DLZ, Inc. dated
February 2, 2012
t
0
C
F.xhihit "C"
OLIVE ROAD RIGHT -OF -WAY ACQUISITION - SUPPLEMENT #2
See attached Budget Schedule for project prepared by DLZ, Inc.
dated December 21, 2011
Engineer's Estimate
$109,975.00
Budget Request
$125,000.00
n
LUTHERAN SCHOOL - SOCCER FIELDS
I STATEMENT OF PROBABLE CONSTRUCTION COSTS
December 21, 2011
Base Bid
iY
CONSTRUCTION ENGINEERING 1 LS $ 21000.00 $ 2,000.00
MOBILIZATION AND DEMOBILIZATION
1
LS
$ 4,900.00
$ 4,900,_
3,050
CYS
$ 7.00
$ 21,350.00
COMMON EXCAVATION
MOL
$
ITOPSOIL
920
CYS
1� 5 00
S 4.600.00
SYS
$
BASIN SEEDING
2.50
$ 12,087.50
It I YElw
107
TON
$' 0
GEOTEXTILE
1.50
$ 427.50
73'
LPT
$ _ -.
. -
MOD. MANHOLE, TYPE K4
vi'I I
2.000 00
$ 8,000.00
PIPE END SECTION, 24,
1
EACH
$ 500.00
H.x. -
$ 5001
CONTINGENCY
1
I.S
S 5.200.00
$ 5.'�u�w�
IF
2011 Base Bid TOTAL
S 109,975.00
M:\PR0A0761\2664\Phase 1 \civil \eng\[Cost Estimate (Lutheran School) 8 -30 -201 I. Is1COST ESTIMATE
r-�
Exhibit "D"
OLIVE ROAD RIGHT -OF -WAY ACQUISITION - SUPPLEMENT #3
See attached Letter Agreement for Professional Engineering from DLZ, Inc. dated
February 8, 2012
U
�J
'Illr� ;F
rr•.
DLZ
ENGINEERS • ARCHITECTS • SCIENTISTS
PLANNERS • SURVEYORS
February 8, 2012
Mr. Bill Schalliol
City of South Bend
227 West Jefferson Boulevard
South Bend, Indiana 46601
Re: Supplemental Agreement No. 1
Olive Road /Pine Road
DLZ Account No. 0761 - 2664 -90
Dear Mr. Schalliol:
Please find enclosed three copies of Supplemental Agreement No. 1 for the above - mentioned project. The
original agreement dated April 9, 2007, included complete design of an Olive Road /Pine Road Connector
(Phase 2). Per your request, we have identified separate scope and fee for 30% design plans and right of way
(W engineering for Phase 2.
We hope that this Supplemental Agreement meets with your approval and acceptance. We will be happy to
meet with you at your convenience to discuss the Supplemental Agreement in detail.
DLZ appreciates this opportunity to provide continued service to the City of South Bend on this important
proj ect.
Very truly yours,
DLZ INDIANA, LLC
ary K. Fisk, P. .
Vice President
cc: BLG, JCZ, BMS, File
: \PROA 0761\2664 \docs\agreementSA #1 \SA Transmittal.doc
2211 East Jefferson Blvd. • South Bend, Indiana 46615 r (574) 236 -4400 • FAX (574) 236 -4471
With Offices Throughout The Midwest
www.dlz.com
SUPPLEMENTAL AGREEMENT NO. 1
This Supplemental Agreement No. 1 is made and entered into this day of
, 2012, by and between the CITY OF SOUTH BEND, INDIANA, acting by and
through the BOARD OF PUBLIC WORKS, hereinafter referred to as the "OWNER ", and
DLZ INDIANA, LLC, 2211 East Jefferson Boulevard, South Bend, Indiana 46615,
hereinafter referred to as the "ENGINEER ".
WITNESSETH
WHEREAS, the OWNER and ENGINEER did, on April 9, 2007 enter into an
agreement for preparation of construction documents for preparation of construction
documents for the widening and reconstruction of Olive Road from U.S. 20 to 300 feet
south of Nimtz Parkway (Phase 1), and the construction of an Olive Road /Pine Road
Connector (Phase 2), and
WHEREAS, the OWNER has requested certain additional services and
changes not included in the original contract or supplemental agreement,
specifically the design of 30% plans of an Olive Road /Pine Road connector for the
purposes of establishing the roadway right of way.
NOW THEREFORE, the OWNER and the ENGINEER desire to amend the above
referenced Design Contract as follows:
Add Section F. to Appendix "A" as follows:
F. Phase 2 30% Design Plans and Right of Way Engineering, as
described herein, shall consist of the following:
1. Design of Olive Road /Pine Road Connector, for Alignment Planning
(30% Design, from 2,100 feet north of the Edison Road /Pine Road
intersection to the US 20 10live Road intersection, approximately
3,700 feet in length. The design shall include a three -lane roadway
with new concrete pavement, integral curb, and a storm sewer
system. The design speed of Olive Road /Pine Road Connector will
be 40 mph.
2. When authorized by the OWNER, the ENGINEER shall:
a. Order title insurance for each parcel from which there will be a
taking.
b. Prepare a plat and legal description for each parcel of right of
way to be acquired, both permanent and temporary.
II. Add Section G. to Appendix "A" as follows:
G. Right of Way Management shall consist of the following:
1 of 6
Supplemental Agreement No. 1
1. Includes the administration of subconsultant agreements and
coordination of title work, appraisal problem analysis, appraisals,
review appraisals, just compensation certification, buying and
required approvals from the Client, INDOT and FHWA. Mortgage
releases will be obtained where value is greater than $10,000.00.
Coordination does not include property management, or relocation,
if required.
2. ENGINEER shall obtain partial mortgage re /ease(s) and /or additional
lien re /ease(s) when directed by OWNER to provide clear title to each
parcel.
3. ENGINEER shall provide as needed notarization services for
acceptance of offers and execution of conveyance documents by
property owners.
4. ENGINEER shall attempt to resolve right of way issues and
coordinate Administrative Settlements, upon approval and direction
by OWNER, if necessary.
5. Pursuant to successful acquisition of executed conveyance
documents and lien release documents, if applicable, ENGINEER
shall submit pay request memorandums, copies of executed
agreements and conveyance documents and taxpayer number
identification request forms to OWNER for review and processing of
payment for compensation of right of way acquisition.
6. ENGINEER shall coordinate with OWNER for distribution of checks
and verification of receipt of checks by property owners.
III. Modify Sections C & D to Appendix "C" as follows:
C. The Plans for Phase 1 will be ready for letting in approximately March
2013, based on a notice to proceed with Phase 1 by February 28, 2007,
contingent upon right -of -way acquisition and OWNER / INDOT review
periods of 30 days or less.
D. The Plans for Phase 2 will be ready for letting in approximately March
2014, based on a notice to proceed with Phase 2 by June 2007,
contingent upon right -of -way acquisition and OWNER / INDOT review
periods of 30 days or less.
IV. Add Section E to Appendix "C as follows:
E. Phase 2 30% Design Plans and Right of Way Engineering
1. Design of Olive Road /Pine Road Connector 30% Plans within 60
calendar days after receipt of Notice to Proceed for this phase.
2. Plats and Legal Descriptions for Phase 2 within 30 calendar days of
receipt from the OWNER of approval of the right of way limits.
2 of 6
Supplemental Agreement No. 1
V. Sections A.1 & 2 of Appendix "D" is modified as follows-
A. Amount of Payment
1. The ENGINEER shall receive as payment for the work performed under
this Agreement the total fee not to exceed of $1,149,650 $1,132,205.00
unless a modification of agreement is approved in writing by the OWNER.
2. The ENGINEER will be paid for the work performed under Appendix "A" of
this Agreement on a Lump Sum basis in accordance with the following
schedule, except as noted in the items below:
3of6
Supplemental Agreement No. 1
Description - Phase 1 Design and Right of Way Engineering
Amount
a.
Field Survey, Including Location Control Route Survey Plat
$115,000.00
b.
Roadway Design and Plans, Phase 1
$220,000.00
C.
15% Concept Design of Pine Road Connector intersection w/ US 20
$3,000.00
d.
Lighting Design and Plans, Phase 1
$19,000.00
e.
Utility Coordination
$5,000.00
f.
Erosion Control Plans and Notice of Intent Letter
$4,000.00
g.
INDOT Cut Road Permit & Coordination, Hourly Rate
$2,500.00
h.
Title Insurance and Updates, as required 17 Parcels
$5,525.00
i.
R/W En ineerin 17 Parcels @ $2,250 Each
$38,250.00
J.
R/W Coordination, Hourly Rate
$19,195.00
k.
R/W Staking, Hourly Rate, as required (32 Parcels @ $650 Each)
$20,800.00
I.
R/W Dedication Plat
$12,000.00
m.
Public Information Meeting, Hourly Rate
$2,585.00
Subtotal, Phase 1 Design and Right of Way Engineering 1
$466,855.00
3of6
Supplemental Agreement No. 1
Description - Phase 1 Right of Way Buying, Bidding and Construction
Amount
q1.
Phase Services
$62,000.00
n.
Appraising, Right of Way Management & Buying Services (1st & 2nd Ap)raisals) (34
$224,000.00
q3•
Appraisals @ $2,000 Each, 17 Buying Parcels @ $3,000 Each, Right of Way
$29,000.00
r1.
Management — 17 Each)
$10,000.00
o.
Bid Phase Services, Hourly Rate
$3,000.00
p.
Pre - Construction Conference, Hourly Rate
$1,500.00
q.
Construction Phase Office Services, Hourly Rate
$6,000.00
Subtotal, Phase 1 Right of Way Buying, Bidding and Construction
$234,500.00
Phase Services
3of6
Supplemental Agreement No. 1
Description — Phase 2 30% Design Plans and Right of Way
Engineering
Amount
q1.
Roadway 30% Design and Plans, Phase 2
$62,000.00
q2•
Title Insurance and Updates, as required 10 Parcels @ $325 Each
$3,250.00
q3•
R/W Engineering (10 Parcels @ $2,900 Each)
$29,000.00
r1.
Pick -up Field Survey
$10,000.00
Subtotal, Phase 2 30% Design and Right of Way Engineering
$104,250.00
3of6
Supplemental Agreement No. 1
II 1 Total, Phase 1 and Phase 2 1 $1,132,205.00 II
VI. Amendment:
This contract amendment decreases the current contract fee of $1,149,650.00 by
$17,445.00 to $1,132,205.00. All other terms and conditions as set forth in the original
contract dated April 9, 2007 shall remain in full force and effect, except as herein
modified.
The undersigned attests, subject to the penalties for perjury, that he is the contract
party, or that he is the representative, agent, member or officer of the ENGINEER that
he has not, nor has any other member, employee, representative, agent or officer of the
firm, company, corporation or partnership represented by him, directly or indirectly, to
the best of his knowledge, entered into or offered to enter into any combination,
collusion of agreement to receive or pay, and that he has not received or paid, any sum
of money or other consideration for the execution of this Contract other than that which
appears upon the face of the Contract.
4 of 6
Supplemental Agreement No
Description - Phase 2: Finish Design Plans
Amount
r.
Pick -up Field Survey
$10,000.00
S.
Roadway Design and Plans, Final Phase 2 - Finalize from 30% plans
$145,000.00
t.
Traffic Signal Warrant Analysis and Traffic Counts
$2,800.00
U.
Traffic Signal Design (1 @ $7,500)
$7,500.00
V.
Li htin g Design and Plans, Phase 2
$16,400.00
W.
Utility Coordination
$5,000.00
X.
Erosion Control Plans and Notice of Intent Letter
$4,000.00
y
INDOT Cut Road Permit & Coordination, Hourly Rate
$2,500.00
ab.
R/W Coordination, Hourly Rate
$8,400.00
ac.
R/W Staking, Hourly Rate, as required (10 Parcels @ $650 Each)
$6,500.00
ad.
R/W Dedication Plat
$12,000.00
ae.
Public Information Meeting, Hourly Rate
$5,000.00
Subtotal, Phase 2 Finish Design
$225,100.00
II 1 Total, Phase 1 and Phase 2 1 $1,132,205.00 II
VI. Amendment:
This contract amendment decreases the current contract fee of $1,149,650.00 by
$17,445.00 to $1,132,205.00. All other terms and conditions as set forth in the original
contract dated April 9, 2007 shall remain in full force and effect, except as herein
modified.
The undersigned attests, subject to the penalties for perjury, that he is the contract
party, or that he is the representative, agent, member or officer of the ENGINEER that
he has not, nor has any other member, employee, representative, agent or officer of the
firm, company, corporation or partnership represented by him, directly or indirectly, to
the best of his knowledge, entered into or offered to enter into any combination,
collusion of agreement to receive or pay, and that he has not received or paid, any sum
of money or other consideration for the execution of this Contract other than that which
appears upon the face of the Contract.
4 of 6
Supplemental Agreement No
Description - Phase 2 Buying, Bidding and Construction Phase
Services
Amount
af.
Appraising, Right of Way Management and Buying Services (1st & 2nd Appraisals)
(14 Appraisals @ $2,000 Each, 7 Buying Parcels @ $3,000 Each, Right of Way
Management — 7 Each ) "
$91,000.00
ag.
Bid Phase Services, Hourly Rate
$3,000.00
ah.
Pre - Construction Conference, Hourly Rate
$1,500.00
ai.
Construction Phase Office Services, Hourly Rate
$6,000.00
Subtotal, Phase 2 Bidding and Construction Phase Services
$101,500.00
II 1 Total, Phase 1 and Phase 2 1 $1,132,205.00 II
VI. Amendment:
This contract amendment decreases the current contract fee of $1,149,650.00 by
$17,445.00 to $1,132,205.00. All other terms and conditions as set forth in the original
contract dated April 9, 2007 shall remain in full force and effect, except as herein
modified.
The undersigned attests, subject to the penalties for perjury, that he is the contract
party, or that he is the representative, agent, member or officer of the ENGINEER that
he has not, nor has any other member, employee, representative, agent or officer of the
firm, company, corporation or partnership represented by him, directly or indirectly, to
the best of his knowledge, entered into or offered to enter into any combination,
collusion of agreement to receive or pay, and that he has not received or paid, any sum
of money or other consideration for the execution of this Contract other than that which
appears upon the face of the Contract.
4 of 6
Supplemental Agreement No
IN TESTIMONY WHEREOF, the parties hereto have executed this Supplemental
Agreement No. 1.
ENGINEER:
DLZ INDIANA, LLC
K. 'Fisk, P E.
Vice President
ATTEST:
Brian M. Smith, P.E.
Highway Department Manager
OWNER:
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
Gary A. Gilot, P.E.
By:
Donald E. Inks
By:
Kathryn Roos
ATTEST:
Approved as to Legality and Form:
Attorney for City of South Bend
5of6
Supplemental Agreement No. 1
STATE OF INDIANA
ACKNOWLEDGMENT
COUNTY OF ST. JOSEPH SS.
Before me, the undersigned Notary Public in and for said County personally appeared
Gary K. Fisk, Vice President and Brian M. Smith, Highway Department Manager of DLZ
Indiana, LLC, 2211 E. Jefferson Blvd., South Bend, IN 46615, and ea h acknowledged
the execution of the foregoing agreement on thi0z -h day of
2012 and each acknowledged and stated that he is the party authorized by the said firm
to execute the foregoing agreement.
Witness my hand and seal the said last named date.
My Commission Expires:
March 6, 2016
Connie J. Hume, Iqotary Public
County of Residence: St. Joseph
STATE OF INDIANA
ACKNOWLEDGMENT
COUNTY OF
SS:
Before me, the undersigned Notary Public in and for said County personally appeared
Gary A. Gilot, Kathryn Roos and Donald E. Inks of the City of South Bend Board of
Public Works and acknowledged the execution of the foregoing agreement on this
day of 12012.
Witness my hand and seal the said last named date.
My Commission Expires:
County of Residence:
M: IPROJ \0761\2664\docs\agreementIlA #1 \Supplemental Agreement I.docx
6of6
Notary Public
Supplemental Agreement No. 1