To: Redevelopment Commission
From: David Relos, Economic Development Planner
Subject: Disbursement Agreement & Revised Development Agreement
Rushton Building, 501 W. Washington
Date: July 12, 2012
On October 25, 2011, the Commission entered into an MOU with South Bend Heritage
Foundation, for the rehabilitation of the historic Rushton Building, at the northwest corner of
W. Washington and William St. Because the Rushton was built with common kitchen and
dining areas, and has stood vacant since 2002, extensive remodeling of the building is
required. The building will be converted into a 23 unit, low to moderate income senior
housing complex.
Total development costs are estimated to be $3.4 million. Funding for the project will come
from $2.8 million Low Income Housing Tax Credits and $277,700 Historic Tax Credits. To
fully fund the project, $322,300 in West Washington Chapin Development Area TIF was
approved.
On March 27, 2012, the Commission approved a Development Agreement, which
delineated each party's responsibilities. Commission improvements will allow off street
parking for residents and visitors, necessary site utility upgrades, sidewalks and curbs,
landscaping and lighting, exterior tuck pointing and cleaning, and new thermo windows.
On May 31, 2012, the Commission approved Resolution No. 3035 and an Addendum to the
Master Agency Agreement, for the Board of Public Works to oversee the Commission's
participation.
To take full advantage of the tax credits needed to make this project successful, the total
cost of $3.4 million must be used. The attached Disbursement Agreement allows SBHF to
incur all costs of the project, and thereby earn full tax credit eligibility. Commission funds
will be governed by the Disbursement Agreement, which allows funds to be deposited in an
escrow account, and disbursed only with Commission approval, ensuring the use is as
previously agreed to in the Development Agreement.
What We Do Today Makes A Difference!
A revised Development Agreement is needed to incorporate the Disbursement Agreement,
specifically Item 4 on the third page, which adds Exhibit G to the Development Agreement.
Staff requests approval of the Disbursement Agreement and revised Development
Agreement, allowing full tax credit eligibility for this project, and thereby making it as
successful as possible.
Memo To RC re Rushton Disbursement Agreement.doc what we Do Today Makes A
Difference!
DEVELOPMENT AGREEMENT (Revised)
Between the City of South Bend Redevelopment Commission
and South Bend Heritage Foundation, Inc.
THIS Agreement, dated the day of , 2012, is made and
entered into between the SOUTH BEND REDEVELOPMENT COMMISSION (the
"Commission ") and SOUTH BEND HERITAGE FOUNDATION, INC. ( "SBHF "), a nonprofit
corporation organized and duly existing under the laws of Indiana (the South Bend
Redevelopment Commission and SBHF being sometimes referred to herein individually as a
"Party" and collectively as the "Parties ").
WHEREAS, SBHF is party to an agreement whereby it has rights and expects to
acquire the real property commonly known as 501 W. Washington, South Bend, Indiana 46601,
and all improvements thereon, described in Exhibit A (the "Property "); and
WHEREAS, the donation by SBHF to the Commission of an Access Agreement
to the Property described in Exhibit A (the "Donated Property ") will be made for the sole
purpose of allowing the Commission to renovate and improve portions of the structure and
parking lot (the "Project ") for low income senior housing; and
WHEREAS, a wholly owned subsidiary of SBHF is the general partner of
Historic Rushton LP ( "Partnership "), which will own and operate the project; and
WHEREAS, SBHF and the Partnership intend to remodel and upgrade the
Property from an existing vacant apartment facility, into a twenty -three (23) unit low income
senior housing complex and make a significant private capital investment in order to improve its
interior and exterior appearance and functionality; and
WHEREAS, SBHF's proposed investment in redevelopment of the structure
furthers the goals of the West Washington Chapin Development Area Development Plan, and
WHEREAS, the Commission considers the Project a benefit to the health and
welfare of all of the community's residents, and
WHEREAS, the Commission has identified a public purpose in SBHF's physical
redevelopment of the building and use as a low income senior housing complex; and
WHEREAS, the Commission wishes to participate as a development partner with
SBHF by undertaking certain renovations which would not otherwise be privately funded, and in
so doing, the Commission hopes to enhance the viability and vibrancy of the Project.
NOW, THEREFORE, the Parties hereby agree and represent as follows:
I . The Recitals are incorporated into the operative provisions of this
Agreement as if fully set out herein.
2. SBHF will convey an Access Agreement in the Donated Property to the
Commission in a form which is satisfactory to SBHF and the Commission (the "Access ").
SBHF will not warrant title to the Donated Property nor provide title insurance, provided,
however, the Commission may refrain from accepting the Access to the Property if, in its sole
discretion, SBHF is unable to convey an acceptable Access to the Donated Property.
The term of the Access shall be for a period of one (1) year from the date the
Access is executed, but the Commission shall have an option at its discretion to renew the
Access for two (2) consecutive six (6) month periods by providing SBHF notice of the
Commission's intent to renew fifteen (15) days prior to the expiration of the original one (1) year
term or any subsequent six (6) month renewal. In any event, the Access shall expire two (2)
years from the date of the Access unless the parties agree, in writing, to an extension.
A professional architect or architectural firm ( "Architect ") acceptable to the
Commission, will assess the renovation needs of the Donated Property, draft plans and develop
cost estimates for the renovation. The renovation plans and cost estimates will be presented by
the Architect to the Commission and SBHF for approval. Once approved, the Architect, under
contract with the Commission, will work with the City of South Bend Board of Public Works,
through an interagency agreement with the Commission, to refine the bid specifications, publicly
advertise and bid the Project, and oversee construction activity.
The source of funding for the project is the West Washington Chapin
Development Area Tax Increment Financing fund ( "TIF "). The Commission's approved total
Project budget is Three Hundred Twenty -Two Thousand Three Hundred and 00 /100 Dollars
($322,300.00), subject to appropriation by the Commission ( "Project Costs "). Project Costs in
excess of this amount may not be expended without further approval by the Commission. A
preliminary outline of the scope of work on the Project to be contracted through public bid is
attached hereto as Exhibit C. Conceptual plans of the interior renovation are attached hereto as
Exhibit D, with that portion of activity to be undertaken by the Commission so noted. The
construction schedule for the Project is attached hereto as Exhibit E.
3. The Donated Property will be under the control and maintained by the
Commission during the term of the Access. All expenses relating to the control and operation of
the Donated Property, and any adjacent portions of the Property owned by SBHF, including
utility charges, shall be apportioned such that SBHF shall be deemed to have been obligated for
all expenses relating to the period prior to the date of the Access and the Commission shall be
obligated for all expenses relating to the Donated Property for the term of the Access. SBHF
agrees to take reasonable steps of security during the term of the Access for the Donated
Property to secure and protect the Donated Property and improvements and personal property
thereon from damages and losses, and to not allow any liens or encumbrances of any kind to
attach to the Donated Property. The Commission, also, agrees to work with SBHF to assure that
reasonable and mutually accepted liability and casualty insurance protection is in place in
relation to the Donated Property and the improvements thereon so as to reasonably protect their
respective interests.
The Project is scheduled to be completed by December 31, 2013 ("Completion Date "). If
SBHF fails to substantially complete its renovation to the Property by the Completion Date, the
Commission may terminate the Access and SBHF will pay to the Commission all documented
expenses incurred for the Donated Property, less any expenses reimbursed by the title insurance
policy, if partial rehabilitation is due to any title defects or newly discovered encumbrances.
SBHF will invest approximately $3.1 million in non - Commission funds to renovate the Property
as a low income senior housing complex, and shall provide ongoing operational and building
maintenance expenses ( "Operational Obligations" or "Operations ") as set forth in Exhibit F.
4. SBHF and the Commission will execute a Disbursement Agreement in the
form attached hereto as Exhibit G.
5. This Agreement shall be binding upon the parties hereto and their
respective successors and assigns.
6. The Parties agree to take such actions, including the execution and
delivery of documents and instruments, as may be necessary or appropriate to carry out the terms
and intent of this Agreement and to aid and assist each other in carrying out the terms and intent.
7. No recourse under or upon any obligation, covenant, or agreement of this
Agreement or for any claim based thereon or otherwise in respect thereof shall be had against the
appointed or elected public officials of the City or the Commission or their respective officers,
agents, and employees, in any amount subject to the terms and conditions herein, and no liability,
right or claim at law or in equity shall attach to or shall be incurred by the public officials of the
City, the Commission or their respective officers, agents, and employees and all such claims are
hereby expressly waived and released as a condition of and as a consideration for the execution
of this Agreement by the Commission, provided such elected officials, officers, agents, and
employees are acting pursuant to lawful authority and are uniformly enforcing and /or
administering the laws, ordinances, practices and procedures of the City and the Commission.
No recourse under or upon any obligation covenant or agreement of this Agreement or for any
claim based thereon or otherwise in respect thereof shall be had against the officers, agents, or
employees of SBHF in any amount subject to the terms and conditions herein.
7. If any portion of this Agreement, or its application to any person, entity, or
property, is held invalid or unenforceable, the application or validity of any other portion of this
Agreement shall not be affected.
8. The Parties shall each bear their own costs and expenses with respect to
this Agreement and the other matters contemplated hereby, including, without limitation, the fees
and expenses of their respective legal counsel.
9. This Agreement shall be construed in accordance with the laws of the
State of Indiana.
10. This Agreement may be executed in more than one counterpart which,
when executed, shall together constitute one agreement.
IN WITNESS WHEREOF, the Parties have duly executed this Agreement as of
the date first above written.
South Bend Heritage Foundation, Inc.
By:
Its:
ATTEST:
By:
Its:
South Bend Redevelopment Commission
By:
Its:
ATTEST:
By:
Its:
EXHIBIT A
Property
LEGAL Building
PARCEL I: A strip of land 3 feet wide and 94 feet long, being a part of BOL No. 24 of the First
Plat of Out Lots of the Town, now City of South Bend, platted by the State Bank of Indiana, and
described as follows, viz: Beginning on the West line of North William Street, at a point 100 feet
North of the North line of West Washington Street, being the present Southeast corner of said
Out Lot; thence running North 3 feet; thence West 94 feet to a private alley, 6 feet wide; thence
South 3 feet; thence East 94 feet to the place of beginning.
PARCEL II: A part of BOL No. 24 of the First Plat of Out Lots of the Town, now City of South
Bend, platted by the State Bank of Indiana, which part is bounded by a line running as Follows,
viz: Beginning at the Southeast corner of BOL No. 24 being at the Northwest corner of
Washington and William Streets in said City; thence running West on the North line of
Washington Street 50 feet; thence North 100 feet; thence East 50 feet to the West line of William
Street; thence South on the West line of William Street 100 feet to the place of beginning.
Legal Parking lots
The west half of the east half of lot numbered 22 in the State Banks first addition to the City of
South Bend, except the following: Beginning on the south line of Colfax Avenue, 53.13 feet west
of the east line of bank out lot 22 (west line of William street); thence south parallel with 53.13
feet west of east line of said bank out lot 22 a distance of 199 feet to the north line of public
alley; thence west along the north line of said public alley, a distance of 1.77 feet; thence east
along south line of said Colfax avenue a distance of 2.32 feet to the place of beginning.
Commonly known as 508 W. Colfax, South Bend, Indiana Key No 71018- 1023 -0970
The East half of the west half of bank out lot numbered 22 of the first plat of out lots of the town,
now City of South Bend, platted by the State Bank of Indiana. Commonly know as 512 W.
Colfax, South Bend, Indiana Key No 71018 -1023 -0969
EXHIBIT C
Scope of Work
The scope of work for the Rushton Building is extensive. The interior of the building will be
completely demolished to core components and rebuilt (approx 17,767 sq. ft.). For example,
floor framing will be repaired and replaced, a new central stairway constructed, new blocking,
beams and framing will be installed as well as all trims (reuse existing when able), flooring,
walls and cabinets. HVAC, electric and plumbing will be completely new systems. All units will
receive new appliances. A Kroppe fire system will be installed for fire suppression. A new
central elevator will be installed requiring footers and mechanical pit in the basement. On the
exterior, a new roof will be installed, the existing brink facade will be tuck pointed, limestone
repaired /replaced and new brick veneer applied where needed. All windows will be repaired and
or replaced.
A parking lot will also be constructed close to the building on two existing vacant lots. An
existing structure on one of the lots will be utilized for covered parking. The lot will be
constructed per the existing zoning ordinance. All set -back, lighting, landscaping and spacing
requirements will be followed accordingly.
As part of the tax credit award, certain environmentally - friendly or "green certified" products
and procedures will also be utilized.
EXHIBIT D
Conceptual Plan
Upon completion, the Historic Rushton Senior Apartments Building will contain 23 units (15 one
BR, 3 two BR and 5 Studio) two units will be constructed per the American Disability Act and
will house handicap persons accordingly. The building will also house a community room,
laundry facility and leasing office. A central elevator will provide easy access for residents to
reach their apartments (see attached building plans). Convenient short-term parking is available
on street and a large parking lot will be available to residents adjacent to the site. A small
covered parking facility is also planned.
EXHIBIT E
Construction Schedule
Begin Construction: October 2012
October 2012 - January 2013: Interior Demolition, install new roof, secure existing windows and
doors, preliminary electric installation.
January 2013 -June 2013: HVAC, electric, plumbing, interior carpentry, primary interior finishes,
new windows, parking lot construction. Pre -lease marketing begins
July 2013- October 2013: Exterior finishes, final interior finishes, complete all interior carpentry.
All construction completed.
October 2013 - February 2014: Finalize all marketing, resident occupancy certifications and
stabilization, building fully occupied and operational.
EXHIBIT F
Operational Obligations
Rushton residents must be 55 years of age and over and meet certain income guidelines. All
entrances to the building will be secured and a resident controlled security system will be utilized
and monitored by management. Building maintenance will be provided by South Bend Heritage
Foundation, and a part-time leasing agent will be housed in the building. As scheduling allows,
social activities for residents will be offered, as part of South Bend Heritage's Resident Life
Coordinator Initiative. Public transportation is directly available to Rushton residents.
Located in the West Washington National Register Historic District, The Rushton will serve as a
signature historic housing development for the transition area between downtown South Bend
and the West Washington neighborhood.
Community and Economic Development Impact:
At least $1,973,009 for construction payroll and building materials;
Rehabilitate a long- standing historic property that would otherwise remain vacant or be
demolished at a cost to the City;
Inject roughly $3,493,977 of private equity into our community;
Create a new base of seniors living near downtown South Bend that will purchase goods and
services;
Provide high quality, affordable housing for seniors near medical facilities, recreational and
cultural amenities.