HomeMy WebLinkAboutChange Order No 2 - Olive Production Well No 6 Rehabilitation Project No 118-102 - Peerless Midwest1316 COUNTY -CITY BUILDING 227 W.JEFFERSON BOULEVARD SOUT" BEND. INDIANA 46601-1930 c, 186 UITY OF SOUTH BEND P BOARD OF PUBLICWORKS February 12, 2019 Frank Williams Peerless Midwest 55860 Russell Industrial Parkway Mishawaka, IN 46545 PRONE 574/235-9251 FAX 574/235-9171 RE: Change Order No. 2 - Olive Production Well No. 6 Rehabilitation — Project No. 118- 102 Dear Mr. Williams: The Board of Public Works, at its meeting held on February 12, 2019, approved the above referenced Change Order for an extension of six (6) days, bringing the new project completion date to February 5, 2019. Enclosed is a copy of the Change Order for your records. If you have any further questions regarding this matter, please call this office at (574) 235- 9251. Sincerely, Linda M. Martin, Clerk Enclosure GARY A. GILOT SUZANNA . FRITZBERG ELIZABETH A. MARADIK LAURA O'SULLIVAN THEPESE J. DORAU CITY OF SOUTH BEND DEPARTMENT OF PUBLIC WORKS PROJECT CHANGE ORDER DATE: 01 /29/19 PROJECT NO: 118-102........ PROJECT NAME: Olive Production Well #6_ Rehabilitation CONTRACT DATE: . ..�,.,� _.m....�_-...... 11/27118 CHANGE ORDER NO. 2 SUBJECT OF CHANGE ORDER: See attached rnw_� po fa" aurrtwna of cloanc ea. See attached Comparison of Estimate for overruns and underruns The original contract sum $ 50,930.00 Net change by previously authorized change orders $ 12,307.00 The contract sun prior to this change order $ _.�......... .. 63,237.00 By this Change Order, the project amount is El Increased Decreased $ The new contract sum including this change order $ This Change Order represents a total change of p Total change for entire project 0 % Original contracted completion date/time Extension of date/time by previous change orders Date/time bxtension by this change order New completion date/time CONTRACTOR Contractor Signature "l lac, $ r r ....... Printed Name and Title Peerless Midwest Company name _._... l 55860 Russel Industrial Parkway Address Mishawaka, IN, 46545 City, State, Zip Januarym30. 2019 Februm 5, "2019 l�el�r�rrary 5, 2019 RECOMMENDED FOR APPROVAL �_. _ ----- ..._ ....... Project Manager CITY OF SOUTH BEND BOARD OF PUBLIC 1 Approved Dater, 01?.��C) f� GaftyA.....�. =Iotcl�reent Therese J. Dorau, Member January 29, 2019 City of South Bend Dept. of Public Works Division of Engineering 227 W. Jefferson Blvd, Suite 1316 South Bend, IN 46601 Attn: Ms. Rebecca Plantz RE: Olive Production Well #6 Change Order Request #2 Dear Ms. Plantz: Due to the inclement weather in the area today, as well as what is forecasted for the next few days, we will be unable to perform the work outside associated with completing this project. We would ask that the final completion date be extended to Tuesday, February 51". As the project stands, the rehabilitation of the well and pump have been completed, the pumping equipment has been reinstalled, and all that is needed is a final field acceptance test and water quality sample. Please let me know if there are any further questions, or if we can be of any further assistance. Very Truly Yours, PEERLESS MIDWEST, INC. -ZA FrankT. Williams Project Manager 55860 Ru..assd lndasstirW PIIrw7., Mishawaka, N 46545 574.259050 pf one 574.2549650 fzax wwvv,µroeedessunfidw esa.co rn BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM Date Name February 4, 2019 Becca Plantz Department Public Works Division/Bureau Engineering BPW Date February 12, 2019 Phone Extension 5998 Required Prior to Submittal to Board Legal F-1 Attorney Name: Clara McDaniels Controller El Controller review is required for all Contracts $5,000.00 or more and greater than one year in length per the City Purchasing Policy Purchasing El Check the E] Agreement Amendment El Professional Services F-1 Bid Opening M Quote Opening Change Order No. 2 Ease/Encroach, M Other: Iro ; Ltatq.1tern Type :7 eAi El Contract [:] Resolution El Bid Award El Quote Award F-1 C/O & PCA No, F-1 Traffic Control: Company or Vendor Name New Vendor MBE/WBE Contractor MBE/WBE Contractor Requested Project Name Project Number Funding Source Account No. Amount for All Submissions ] Proposal E] Req. to Advertise Information El PCA Addendum El Title Sheet Peerless Midwest F] Yes 0 No E] if Yes, Approved by Purchasin _p MBE WBE ❑ No 0 Yes Name of Compa ny Olive Production Well #6 Rehabilitation 118-102 Water Works 0 & M 620-0640-602.31.06 Terms of Contract Lump Sum Purpose/Description Extending the completion date due to severe we on 1/30/18 and 1/31/18. ❑ .................... ...... ..... ­­­ . . . . ............... Required Contractor's Certification Forms Attached (Non - Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.) �Rqq fired For,C an e Orders,O I n! Amount of F] increase . . . . ....... . ................... 1:1 Decrease Previous Amount . ............. ..... Current Percent of Change* % New Amount Total Percent of Change: % Dispersal After App . . . ............. Copy Original F1 Becca Plantz — - - - ----------------- El El El