HomeMy WebLinkAboutChange Order No 1 - Century Center Convention Hall A-B New Entry Project No 115-017A - Brown and Brown General Contractors1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOI ITH BEND. INDIANA 46601-1 830
1865
February 12, 2019
Eric Brown
Brown and Brown General Contractors, Inc.
124 E. Elkhart Street
Wakarusa, IN 46573
PHONE 574/235-9251
FAX 574/235-9171
RE: Change Order No. 1 - Century Center Convention Hall A-B New Entry — Project No.
115-017A
Dear Mr. Brown:
The Board of Public Works, at its meeting held on February 12, 2019, approved the above
referenced Change Order for an increase of $12,862, plus an additional seventy (70) days,
bringing the current contract amount to $88,414 and the new project completion date to March
15, 2019.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
,41
Linda M. Martin, Clerk
Enclosure
GARY A. GILOT SUZANNA A FRITZBERG ELIZABETH A. MARADIK LAURA O'SULLIVAN THERESE J. DORAU
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO:
SUBJECT OF CHANGE ORDER:
1/18/2019
115-017A
..Century Center Convention Hall A-B New__Entry
10/9/2018
PCR #1-Chan a in materials and availabili
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
CO
Contrac or SIgnature
6r
i-
Printed Name 'and Title
Brown & Brown General Contractors, Inc.
Company Name
124 S Elkhart St.
Address
Wakarusa IN, 46573
City, State, Zip
$ 75,552.00
$ 0.00
$ 75,552.00
X Increased
Decreased
$ 12,862.00
$ 88,414.00
17.02 %
17.02 %
1 /4/2019
0 days
70 days
3/15/2019
RE r�eOMM EN—DE9N—DEQ
EQ8 AePROVAL
COI+ aT
ION MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC O IDS
pproved Date.c'f
Gary A. Gilo , President
St zann , M. Fritzbe g, Member
Elizabeth A. aradik, Member
4a'Sullivan,
J. Dorau, Merry r
Member
-'-" R711Y4t "1 R7:7�
Arown and Rsown
CIEMER AL CONTRAICTORS. INC.
124 S. ELKHART ST.
P.O. BOX 487
WAKARUSA, INDIANA 46573.0487
PHONE: (574) 862.2171 FAX: (574) 862.3930
January 3, 2019
Joe Nucciarone
Alliance Architects
929 Lincolnway East, Suite 200
South Bend, IN 46601
Re: Century Center Convention Hall
Joe,
Our µprice for the Construction Change Directive 1-3 is as follows. Once
these items are approved, a completion date can be given after delivery dates are
confirmed. I have already authorized the change for the casework because of the
long lead time, that material should be ready for installation 1-11-19.
CCD #1
1. Add for aluminum window change $ 328.00
2. Add for casework change 3,520.00
3. Add for door No. 1 change 99.00
4. Add corner guards 323.00
CCD #2
1. Add for floor covering changes in
room B-205 $8,262.00
CCD #3
1. Add two (2) access panels $330.00
2. Relocate electrical boxes NC
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 02/04/2019
. . . ..................... Department Public Works
Name Roger Nawrot
. ..............
Division/Bureau Engineering
........................ -
BPW Date 02/12/2019
Phone Extension 5920
Legal
Attorney Name:
Controller
Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing El
. ...................
Check the Appropri
. .......Type- -Re uired for A Submissions
ate —I
Agreement
IE]
Contract Proposal El Addendum
Professional Services
[_1
Resolution
E]
Bid Opening
E]
Bid Award Req. to Advertise El Title Sheet
E]
Quote Opening
El
Quote Award
Change Order No. 1
F-1
C/O & PCA No, E], PCA
Ease/Encroach,
F-1
Traffic Control:
E]
Other:
Required Information
Company or Vendor Name
Brown & Brown General Contractors, Inc.
El Yes [:] No mm If Yes, Approved by
New Vendor
Purchasing
MBEIWBE Contractor
MBE [:] WBE
MBEIWBE Contractor Requested ._D_No
. . .........................
[:] Yes Name of Corn an
..... ................ . . ........ ..
Project Name
entu
Cry Center Convention Hall A-B Entry
....... .................
Project Number
115-01 7A
Funding Source
...... . ... ........ _. ..........
Hotel -Motel
Account No.
..........................
7304.42010.000.0099
Amount
$75,552.00
Terms of Contract
.. . ........... . .........
Purpose/Description
Approval of C.0 #1
F-1 Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E- ��!Jfy, Iran, etc.
........... .... . — . J . ........
. .........Re faired For Change Orders Only
Amount of Increase $12,862.00 .............
El Decrease
Previous Amount $75,552.00
. . .............. . . ....................
Current Percent of Change: 17.02%
........................
New Amount 88,414.00
Total Percent of Chan e: 17.02% ............. . ......