1. REVIEW OF MINUTES
A. Agenda Review, Regular Meeting, and Claims Review Meeting of November 21,
November 27, and December 4, 2018
2. 2019 BOARD OF PUBLIC WORKS MEETING SCHEDULES
3. OPENING OF BIDS
A. Small Drainage Design and Repair – Project No. 118-063
1. Funding: LRSA/SSDA TIF (251.0608.431.42.96)
B. Sewer and Manhole Rehabilitation – Project No. 118-093
1. Funding: Utility Expense/Contractual Service (641.0621.792.63.35)
C. McKinley Avenue and Fremont Park Improvements – Project No. 118-072
1. Funding: LRSA/Utility Expense Contractual/VPA
(251.0608.431.42.96/201.1101.452.36.01)
D. Wastewater Treatment Plant Administration Building Masonry Improvements –
Project No. 118-087
1. Funding: Sewage Works Operations/Building Repairs & Maintenance
(641.0630.793.36.01)
E. Main and Colfax Parking Structure Repairs 2019 – Project No. 115-143A
1. Funding: Parking Garage Fund/RWDA TIF
(401.0401.415.36.01/324.1050.460.42.02)
F. Three Twenty at the Cascade – Site Utilities – Project No. 118-074D
1. Funding: REDA TIF (429.1050.460.42.03)
G. Sale of Abandoned Vehicles
4. OPENING OF QUOTATIONS
A. Fire Station No. 10 and 11 Equipment – Project No. 118-108
1. Funding: Equipment Purchases/Materials & Equipment (287.0902.422.43.10)
B. Colfax Water Works Building Repainting – Project No. 118-055
1. Funding: Water Works Building Repair & Maintenance (620.0640.657.36.01)
C. Organic Resources Facility Breakroom Addition
1. Funding: Organic Resources/Wastewater (TBD)
D. East Longfellow Ave. and North Riverside Dr. Traffic Calming – Project No.
118-113
1. Funding: LRSA (251.0608.431.42.96)
E. South Bend Civic Theater Alleyway Repaving – Project No. 118-110
1. Funding: Complete Streets (404.1001.460.42.30)
F. Morris Theater Mezzanine Handrails – Project No. 118-081R
1. Funding: Morris Performing Arts Center Capital (TBD)
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
MEETING
December 11, 2018 – 9:30 a.m.
Location: 1308 County-City Building
South Bend, Indiana 46601
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK THERESE J. DORAU JAMES A. MUELLER
Page 2
5. OPENING OF PROPOSALS
A. Police Vehicle Decal Design and Application
1. Funding: Police Department (202.0607.431.38.01/.02)
B. Engineering Services for Bendix Drive, Lathrop to Indiana Toll Road – Project
No. 114-065
1. Funding: LRSA/INDOT (251.0608.431.42.96)
6. AWARD BIDS AND APPROVE CONTRACTS
A. South Bend Fire Department Training Center Classroom Building – Project No.
117-127R
1. Company: Brown & Brown General Contractors, Inc.
2. Amount: $649,937; Base Bid plus Alternate Nos. 2 and 4
3. Funding: 2018 Fire Station No. 9 Capital (451.0901.422.42.02)
B. Fat Daddy’s Building Demolition – Project No. 118-066
1. Company: R & R Excavating, Inc.
2. Amount: $540,000; Base Bid plus Alternate Nos. 1 and 3
3. Funding: RWDA TIF (324.1050.460.39.82)
C. Wastewater Treatment Plant Electrical Improvements – Project No. 117-132
1. Company: Martell Electric, Inc.
2. Amount: $6,332,340; Base Bid plus Alternate Nos. 2, 3, and 4
3. Funding: Wastewater Capital/Contractual (642.0630.415.43.66;
641.0630.793.63.35)
D. Airport Annexation Area Sanitary Sewer Extension – Project No. 117-108
1. Company: HRP Construction, Inc.
2. Comments: Low Bidder Non-Responsive to Addendum
3. Amount: $766,957
4. Funding: Sewage Works Capital/RWDA TIF (642.0621.415.42.05)
E. Century Center Lower Level Restroom Remodel – Project No. 118-082A
1. Company: Brown and Brown General Contractors, Inc.
2. Amount: NTE $238,638
3. Funding: Liability Insurance (226.0419.672.43.02)
7. AWARD QUOTATIONS AND APPROVE CONTRACTS
A. Mishawaka Avenue Tree Replacement – Project No. 118-111
1. Company: Acorn Landscaping LLC
2. Amount: $21,839.50
3. Funding: Complete Streets Transportation (404.1001.460.42.30)
8. CHANGE ORDERS
A. Venues, Parks and Arts Maintenance Storage Building – Project No. 118-046R
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
MEETING
December 11, 2018 – 9:30 a.m.
Location: 1308 County-City Building
South Bend, Indiana 46601
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK THERESE J. DORAU JAMES A. MUELLER
Page 3
1. Company: The Robert Henry Corporation
2. Change Order No.: 3
3. Increase Amount: $38,936
4. Percent of Increase: 11.16%
5. Total Percent of Change: 17.48%
6. Revised Contract Amount: $387,890
7. Funding: Park Bond Series I (471.1138.452.42.01)
B. Howard Park Redevelopment and St. Louis Blvd. Improvements– Project No.
117-047B
1. Company: Larson-Danielson Construction
2. Change Order No.: 2
3. Decrease Amount: ($229,464)
4. Percent of Decrease: (1.22%)
5. Total Percent of Change: (5.70%)
6. Revised Contract Amount: $17,746,568
7. Funding: Park Bond, RETIF, Regional Cities & Cumulative Capital
(452.1101.452.02/.03; 429.1050.460.42.02; 201.1111.452.42.01;
407.1101.452.42.01)
C. Navarre Street Milling and Asphalt Overlay – Project No. 117-128
1. Company: Walsh & Kelly, Inc.
2. Change Order No.: 1
3. Increase Amount: $7,000
4. Percent of Increase: 16.47%
5. Revised Contract Amount: $49,503.50
6. Funding: LRSA (251.0608.431.36.10)
D. J.C. Lauber Site Improvements – Project No. 118-083B
1. Company: Rieth-Riley Construction Co., Inc.
a) Change Order No.: 1
(1) Increase Amount: $24,417
(2) Percent of Increase: 6.54%
(3) Revised Contract Amount: $397,945
(4) Funding: REDA TIF (429.1050.460.42.03)
b) Change Order No.: 2
(1) Increase Amount: $9,540
(2) Percent of Increase: 2.40%
(3) Total Percent of Change: 9.09%
(4) Revised Contract Amount: $407,485
(5) Funding: MVH (202.0607.431.36.01)
E. Lincoln Way East Corridor Improvements – Project No. 117-055A
1. Company: Walsh & Kelly, Inc.
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
MEETING
December 11, 2018 – 9:30 a.m.
Location: 1308 County-City Building
South Bend, Indiana 46601
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK THERESE J. DORAU JAMES A. MUELLER
Page 4
2. Change Order No.: 1
3. Increase Amount: $16,385
4. Percent of Increase: 3.57%
5. Revised Contract Amount: $475,385
6. Funding: Park Bond/RWDA TIF (452.1101.452.31.06; 471.1134.452.42.01)
F. Hibberd Plaza Improvements – Project No. 117-063R
1. Company: R. Yoder Construction, Inc.
2. Change Order No.: 2
3. Increase Amount: $28,123.73
4. Percent of Increase: 6.22%
5. Total Percent of Change: 7.85%
6. Revised Contract Amount: $479,998.27
7. Funding: RWDA TIF (324.1050.460.42.01)
G. Erskine Clubhouse Renovation – Project No. 116-108
1. Company: Ziolkowski Construction Co., Inc.
2. Change Order No.: 3
3. Increase Amount: $10,471
4. Percent of Increase: 1.14%
5. Total Percent of Change: 2.03%
6. Revised Contract Amount: $925,370
7. Funding: VPA Maintenance (201.1101.452.39.89)
9. CHANGE ORDERS AND PROJECT COMPLETION AFFIDAVITS
A. Ameritech Drive Pavement Improvements – Project No. 117-057A
1. Company: Walsh & Kelly, Inc.
2. Change Order No.: 1 (Final)
3. Decrease Amount: ($19,563.96)
4. Percent of Decrease: (5.03%)
5. Final Contract Amount: $369,436.04
6. Funding: RWDA TIF (324.1050.460.31.20)
B. Ziker Sample Street Building: Restroom Remodel – Project No. 117-123
1. Company: Premier 1 Construction, Inc.
2. Change Order No.: 1 (Final)
3. Decrease Amount: ($3,782)
4. Percent of Decrease: (15.92%)
5. Final Contract Amount: $19,978
6. Funding: RWDA TIF (324.1050.460.42.02)
C. 2016 Manhole and Sewer Lining – Project No. 116-026
1. Company: Insituform Technologies USA, LLC
2. Change Order No.: 5 (Final)
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
MEETING
December 11, 2018 – 9:30 a.m.
Location: 1308 County-City Building
South Bend, Indiana 46601
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK THERESE J. DORAU JAMES A. MUELLER
Page 5
3. Decrease Amount: ($162,538.70)
4. Percent of Decrease: (5.42%)
5. Total Percent of Change: 4.08%
6. Final Contract Amount: $2,837,196.20
7. Funding: Utility Expense/Contractual (641.0621.792.63.35)
10. PROJECT COMPLETION AFFIDAVITS
A. Lime Bike Parking Areas – Project No. 118-059R
1. Company: The Airmarking Co., Inc.
2. Final Contract Amount: $9,800
3. Funding: Complete Streets Transportation (404.1001.460.42.03)
B. Ironwood Drive Sidewalk, Edison Rd. to SR 23 – Project No. 117-033A
1. Company: Walsh & Kelly, Inc.
2. Final Contract Amount: $188,144.74
3. Funding: LRSA (251.0608.431.42.96)
C. Rum Village Dog Park Construction
1. Company: R. Yoder Construction
2. Final Contract Amount: $143,257.31
3. Funding: 2015 Park Bond (751.1101.452.39.89)
11. RESOLUTIONS
A. No. 64-2018 – A Resolution of the South Bend Indiana Board of Public Works on
Disposal of Unfit and/or Obsolete Property
1. Description: Various Computers and Electronics
B. No. 67-2018 - A Resolution of the South Bend Indiana Board of Public Works on
Disposal of Unfit and/or Obsolete Property
1. Description: Various Furniture, Fixtures, Machinery, Equipment and Building
Improvements
C. No. 68-2018 – A Resolution of the Board of Public Works of the City of South
Bend, Indiana, Approving the Acceptance of Transfers of Real Property
1. Description: Acceptance of Twenty-Six (26) Blighted Properties from Urban
Enterprise Association of South Bend, Inc.
12. AGREEMENTS/CONTRACTS/PROPOSALS/ADDENDA
A. QPA Purchase – Network Solutions, Inc.
1. Description: Refresh Seventy (70) Legacy Wireless Access Points used across
City Buildings for Wireless Connectivity
2. Amount: $54,864.50
3. Funding: IT Supplies and Professional Services (279.0672.415.21.05/31.06)
B. Service Agreement – Digital Defense Incorporated
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
MEETING
December 11, 2018 – 9:30 a.m.
Location: 1308 County-City Building
South Bend, Indiana 46601
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK THERESE J. DORAU JAMES A. MUELLER
Page 6
1. Description: Digital Defense Frontline Advanced Self-Directed Scanning
2. Amount: $33,504; Total for Three (3) Years; (Year 1: $12,900; Years 2 and 3:
$10,302)
3. Funding: IT Operating (279.0672.415.36.04)
C. QPA Software Licensing Agreement – Carahsoft Technology Corp.
1. Description: Licensing for ServiceNow IT Service Management
2. Amount: $48,202/Year for Three (3) Years, Plus $7,200 Training; Total
$151,808.04
3. Funding: IT Operating (279.0672.415.36.04)
D. Professional Services Agreement – Calfee Strategic Solutions, LLC dba Calfee
Zoning
1. Description: Administrative Process, Legal and Peer Review of South Bend
Zoning Ordinance Updates
2. Amount: $31,000
3. Funding: EDIT (408.1001.460.31.06)
E. Professional Services Agreement - EmNet
1. Description: 2018 CSO Reduction Projects
2. Amount: $279,001
3. Funding: Wastewater LTCP Engineering (641.0630.793.31.02)
F. Non-Exclusive License Agreement – Triangle Homeowners Association, Inc.
1. Description: Use of City of South Bend Burns Triangle Right-of-Way Area
for Homeowner Association Gatherings
G. Municipal Advisory Services – H.J. Umbaugh & Associates
1. Description: Financial Advisory Services for Long Term Control Plan Capital
Funding Plan
2. Amount: $25,000
3. Funding: Wastewater LTCP (641.0630.793.31.02)
H. QPA Purchase – Gametime, Inc.
1. Description: Purchase of Playground Equipment as part of 2019 Parks
Upgrade Program
2. Amount: $214,802.60
3. Funding: Park Bond Series I (471.1137.452.42.01)
I. Special Purchase – Emergency Radio Services
1. Description: One-Hundred, Ten (110) Portable Radio Chargers for Hardwire
Mount in Police Vehicles Compatible with Radios
2. Amount: $49,298.70
3. Funding: Grant
J. Memorandum of Understanding - MACOG
1. Description: Traffic Count Data Collection
2. Amount: $28,000
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
MEETING
December 11, 2018 – 9:30 a.m.
Location: 1308 County-City Building
South Bend, Indiana 46601
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK THERESE J. DORAU JAMES A. MUELLER
Page 7
3. Funding: LRSA (251.0608.431.31.06)
K. Access Permit – Indiana Michigan Power
1. Description: Access to Northeast Corner of Muessel Grove Park for Soil
Boring to Survey for Proposed Electric Transmission Line Route
L. Temporary Storm Sewer Access Agreement – Madison LLC
1. Description: Allow Commerce Center’s Temporary Parking Lot to connect to
Storm Sewer in Madison Street
M. Amendment No. 1 to Professional Services Agreement – Arcadis, U.S., Inc.
1. Description: Disinfection Pilot Testing and Cost Estimating for Stress Testing
Evaluation and LTCP
2. Amount: $11,630; New Total $160,420
3. Funding: Wastewater Engineering (641.0630.793.31.02)
N. Amendment No. 1 to Professional Services Agreement – Lochmueller Group, Inc.
1. Description: Addition of Utility and Railroad Coordination and Geotechnical
Services; Elimination of Unneeded APA Services
2. Amount: ($350); New Total $525,100
3. Funding: RWDA TIF (324.1050.460.31.02)
O. Professional Services Agreement – Incremental Development Alliance
1. Description: Near Northwest Neighborhood Plan
2. Amount: $25,000
3. Funding: EDIT (408.1001.460.31.06)
P. Professional Services Agreement – Opticos Design, Inc.
1. Description: Near Northwest Neighborhood Plan
2. Amount: $178,866
3. Funding: EDIT (408.1001.460.31.06)
Q. Escrow Agreement – Larson-Danielson Construction Co., Inc. and 1st Source
Bank, NA
1. Description: Escrow Agreement for Howard Park Redevelopment Project
R. Agreement – U.S. Department of the Army and Department of Interior
1. Description: Create Flood Inundation Mapper for South Bend
2. Amount: $71,000
3. Funding: Wastewater Engineering (641.0630.793.31.02)
13. STREET/ALLEY VACATIONS
A. Applicant: Matthew and Katherine Kent
1. Location: East/West Alley running from North/South Alley to 27th Street;
South of Pleasant Street and North of Northside Blvd.
2. Purpose: Sole Property Owners to create Urban Farm for use by Montessori
Center Preschool
3. Community Investment Comments
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
MEETING
December 11, 2018 – 9:30 a.m.
Location: 1308 County-City Building
South Bend, Indiana 46601
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK THERESE J. DORAU JAMES A. MUELLER
Page 8
14. TRAFFIC CONTROL DEVICES
A. New Installation - Handicapped Accessible Parking Space Sign
1. Locations:
a) 429 S. Edison Avenue
b) 1217 W. Indiana Avenue
2. All criteria has been met
15. CONSENT TO ANNEXATION AND WAIVER OF RIGHTS TO
REMONSTRATE
A. 25567 Shady Tree Court – Water and Sewer
B. 52471 Blue Winged Trail – Water and Sewer
C. 51541 Audubon Woods Drive – Water and Sewer
D. 26900 Marshall Drive North – Sewer
E. 53693 Terre Verde Hill Court – Water and Sewer
16. RATIFY BONDS
A. Occupancy Bonds
1. Lonewolf Enterprises, LLC, Released Effective February 7, 2019
2. Jon Freeman, Released Effective November 28, 2018
17. CLAIMS
18. PRIVILEGE OF THE FLOOR
19. ADJOURNMENT
NOTICE
FOR HEARING AND SIGHT IMPAIRED PERSONS
Auxiliary Aid or Other Services are Available upon Request at No Charge.