HomeMy WebLinkAboutChange Order No 20-PCA- WWTP Secondary Treatment Improvements Project No 114-053 - Thieneman Construction Inc1316 COUNTY -CITY BUILDING
227 W.JEFFERSON BOULEVARD
SOIJTH BEND. INDIANA 46601-1830
CITY OF ! BEND PETE BUTTIGIEG, MAY
BOARD PUBLIC 1
;�
November 27, 2018
Matt McCoy
Thieneman Construction, Inc.
17219 Foundation Parkway
Westfield, IN 46074
PHONE 574/235-9251
FAx 574/235-9171
RE: Change Order No. 20 (Final)/Project Completion Affidavit - Wastewater Treatment
Plant Secondary Treatment Improvements — Project No. 114-053
Dear Mr. McCoy:
The Board of Public Works, at its meeting held on November 27, 2018, approved the Final
Change Order for this project, for an increase of $323.07, plus an additional twelve (12) days.
The new Contract sum is $13,886,920.98, and the new project completion date is May 22,
2018.
In addition, the Project Completion Affidavit for this project was approved in the amount of
$13,886,920.98.
Copies of the Change Order and Project Completion Affidavit are enclosed for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
w
Linda M. Martin, Clerk
Enclosures
GARY A. G1LOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK JAMES A. MUELLER THERESE J. DoRAu
CITY OF SOUTH BEND .,
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE: 11 /14/2018
PROJECT NO: 114-053
PROJECT NAME: WWTP Secondary Treatment Improvements
CONTRACT DATE: 09/03/2015WContract Award, 10/05/2015 Notice to Proceed
CHANGE ORDER NO. 20
SUBJECT OF CHANGE ORDER: Various modifications to the contract. See attached.
All items completed substantially as planned.
See attached Comparison of Estimate for overruns and underruns,
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
CONTRACTOR
Contractor Signature-_ -........ ._ ....
A77—
G G�
rinted Name and Title
Thieneman Construction, Inc.
Company name
17219 Foundation Parkway
dre Adss .�.. .____._ -'-
Westfield, Indiana 46074
City, State, Zip
$
11, 885, 000.00
2,001,597.91
$
13 886,597 91
® Increased
❑ Decreased $
323.07
$ .............13,
886, 920.98
.............
0.003
+16.84 %
08/25/2017
258 daysmm ITITwww
1S...........
05/22/2018
RECOMMENDED.... ...... _..........
FOR APPROVAL
ACC�
onstruction Manager
CITY OF SOUTH BEND
BOARD OF PUBL C W RCS
Approved Date:"!;'`
ary A. Gilot, Resident
James A. Mueller, Member
erg, e, er
Elizabeth A. Maradik, Member
Therese J.. Dora ._,. u, _..._ em'� er.. '._- ....
. M
, ,,1i 1,9141114"
CITY OF SOUTH BEND, INDIANA Pei
BOARD OF PUBLIC WORKS
PROJECT COMPLETION AFFIDAVIT
Itl6S
r Treatment Plant Seconda Treatment Improvements
PROJECT NAME Wastewater �' reatmeI ... . ,
PROJECT NO. 114-053 FINAL 13,886,920.98 �....
COST _
CONTRACT 09/03/2015 MAINTENANCE AGREEMENT 5/22/2021
SIGNED ENDS
PROJECT Construct improvements at Aeration Basins, Final Clarifiers, Effluent Piping,
DESCRIPTION Flow Meters. Air MixinEr ui ment, and Gate Replacements at W WTP..
WITNESSETH:
The work under the above contract between the City of South Bend and the undersigned contractor having
been completed, the City of South Bend, its officials and agents are hereby released from all claims and
demands whatsoever arising under or by such contract, and that the contractor performed the work within the
scope of the Specifications and Sins ndards of the City of South Bend which were a part of the above Contract.
Executed this
r'da� 20
.......... !:�Li 44- ThienemanITConstruction, Inc.
Signature Company an Name
Printed _ ,..'t 17219 Foundation Parkway_
_1 WWWWW undati�
d Name �._..._....._. Company Address
Wes. �_..�........�...................... .
WITNESS City/State/Zip
e riders ned Notary Public in and for said country and state, personally appeared
Bt,dorc� me, the � "g
acknowledged his/her signature to the above Proj t l�lction Affidavit
on the ... °� an 201� _. P' ao1�c
�. P day o �',....._.
.r Nota SI ] ti,are M Commission Expires t Y _ Y pn
. � �w W
Y atM
Printed in
N me Count of Reside ce� ��
03
If the Contractor 1s a corporation, the following certificate will be executed.
Icar r i , , certify that I am Secretary of the Corporation executing this release; that
who signed this release on behalf of the contractor was then
' .lti � fr.. Aof said Corporation; that said release was duly signed for and on behalf of
s�pi1'1'p' ltthor
aa<,atity of its governing body, and is within the scope of corporate powers:
ecclar �Y's Signature re Corporate Seal
m. rN
Printed Name
DEPARTMENT OF PUBLIC WORKS APPROVAL
This project is acceptable for final approval and we recommend to the Board of Public Works that it be
ordained so.
Constructnnanagery Date:
BOARD OF PUBLIC W71 A
PPROVA Date: ... 2, 7Lf-
Gary A. t ltlr't, Presid nt Suzam�:a rt.. c ember James A. Mueller, Member
`t,Ncrk.
Elizabeth A. M- aradik, rau
Member Therese J. o, Member I tttda M, Mailin„
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF UTILITIES
TO: Members of the Board of Public Works
Eric Horvath, Director of Public Works
Clara McDaniels, Board of Public Works Attorney
FROM: Al Greek, Director of Utilities
Jacob M. Klosinski, Assistant City Engineer
SUBJECT: Agenda Request Form — Change Order No. 20 & Project Completion Affidavit
Project No. 114-053: Wastewater Treatment Plant Secondary Treatment
Improvements
DATE: November 19, 2018
rouiNNWi010
The Division of Utilities is requesting the Board of Public Works approval of Change Order No.
20 for Project No. 114-053 Wastewater Treatment Plant Secondary Treatment Improvements.
Refer to attached documents for supporting details for the subject work.
Change Order No. 20 addresses the following changes:
COP 123 — Revised Electrical Short Circuit Study
Credit for scratched Panel Door at Dewatering Well #3
NET INCREASE FOR CHANGE ORDER NO. 20 ITEMS
Original Contract Sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this change order, the project amount decreases by
The new contract sum including this change order is
This Change Order represents a total change of
Total change for the entire project
$ 1,323.07
($ 1,000.00)
$ 323.07
$11,885,000.00
$ 2,001,597.91
$13,886,597.91
$ 323.07
$13,886,920.98
+0.003%
+16.84%
Time Extensions resulting from Change Order No. 18:
Substantial Completion: 12 days
Final Completion: 0 days
Comments:
Final Adjustment to Substantial Completion covers all adjustments related to the revision
of the Short Circuit Study and delays related to the 2018 Flood Events.
The funding sources for Change Order No. 20 shall be directed from the Utilities, Wastewater
Capital Account (642-0630-415-43-66) as appropriate. If there are questions regarding the
subject change order, please contact Al Greek (Ext. 4210) at Division of Utilities or Jacob M.
Klosinski (Ext. 9496) at the Division of Engineering.
Letter of Transmittal
To: City of South Bend Date: November 14, 2018
3113 Riverside Drive
South Bend, IN 46628
Re: South Bend Secondary Treatment Improvements
Attention: Jacob Klosinski
We are sending you: O Enclosed ❑ Under separate cover via ❑ Mail ❑ Messenger, the following items:
❑ shop drawings ❑ prints ❑ data sheets ® Change Order
❑ specifications ❑ sketches ❑ brochures
Our action relative to items submitted for approval has been noted on the drawings.
COPIES PREPARED BY REFERENCE NO. DESCRIPTION
l City of South Bend Project Change Order
1 Arcadis Change Order No. 20 incl. COP 123
THESE ARE TRANSMITTED AS CHECKED BELOW:
❑ As requested ❑ Approved
❑ For your use ❑ Approved as Corrected
❑ For review & comment ❑ Revise and Resubmit
❑ For your information ❑ Not approved
Remarks:
ARCADIS U.S., Inc.
150 W. Market Street
Suite 728
Indianapolis, IN 46204
TEL: 317-231-6500
FAX: 317-231-6514
Vn 1p'�+�rw.
John C. Huston
Project Engineer
❑ Resubmit copies for approval
❑ Submit copies for distribution
❑ Return corrected prints
❑ Approved as Corrected/Resubmit
Copies: ARCADIS-IND File Copy
Arcadis Job #03029034.0000
EJ C,I)C
Change Order No. 20
Date of Issuance: November 14, 2018 Effective Date:
Owner: City of South Bend Owner's Contract No.: 114-053
Contractor: Thieneman Construction Contractor's Project No.:
Engineer: Arcadis US Engineer's Project No.: 03029034.0000
Project: Secondary Treatment Improvements Contract Name:
The Contract is modified as follows upon execution of this Change Order:
COP 123 Revised Short Circuit Study due to AEP Changing Transformer .......................... _........... $1,323.07
Scratched Pump Door Credit......................................................................................................_ ($1,000.00)
Project Time .... ......... ......... .................... ......... ........$0.00
Attachments: Contractor's Change Order Proposals
CHANGE IN CONTRACT PRICE
Original Contract Price:
$ 11 885 000.00
Increase from previously approved Change Orders:
$ 2,001,597.91
Contract Price prior to this Change Order:
$ 13,886,59791
Increase of this Change Order:
$ 323.07
Contract Price incorporating this Change Order
R
R M��ED:
By:
ITEngineer (if required)
Title:
Date:
CHANGE IN CONTRACT TIMES
Original Contract Times:
Substantial Completion: July 26 2017
Ready for Final Payment: Au ust 25 2017
Increase from previously approved Change Orders:
Substantial Completion: 258 days
Ready for Final Payment: 258 days
Contract Times prior to this Change Order:
Substantial Completion: Aril 10 2018
Ready for Final Payment: May 10 2018
Increase of this Change Order:
Substantial Completion: 12 days
Ready for Final Payment: 0 days
Contract Times with all approved Change Orders:
Substantial Completion: Aril 22 2018
Ready for Final Payment: May 22 2018
ACCEPTED
By: Y!ao. :. ... By:
Owner (Authorized Signature)mmm
Title �jrrj Fi✓6l�lQ Title
Date //- /I?- ZO/8u Date
'rudyge r 729 A0.04.0 6V
ACCEPTED,,
Contractor (Authorized Si ... ature)mm
Gem %ylANA..6-0.....
._ ... ............................
EJCDC® C-941, Change Order.
Prepared and published 2013 by the Engineers Joint Contract Documents Committee.
Page 1 of 1
CITY OF SOUTH BEND, INDIANA
WWTP SECONDARY TREATMENT IMPROVEMENTS
CITY PROJECT NO. 114-053
CHANGE ORDER PROPOSAL
Change Order Proposal No.: 114-053 13 3 Date 3/2//1,8
Submitted in Response to Proposal Request No.:
Contract Name and No 1 14-053 South Bend 'i�t'"4 1 l' econc;lal [!,:pmtrt �nC tt Iarc) Ile )IS
Contractor wl 1lip11pj11gn � �1!1s1 tM 1,�;on, �tq,.
Subject: Additional costs from Sweney to perform a revised short circuit test as requested due to
AEP using a different transformer than they had previously provided data for. Due to the tardiness
of this submission, I have eliminated any unnecessary markups. This missing PCO was discovered
recently during my audits of all PO's and Subcontracts.
The following changes to the Contract are proposed:
SCOPE OF WORK: (attach and list supporting information as required)
1. Item: TCI — See attached cost breakdown - $0.00
2. Item: Sweney — See attached cost breakdown - $1,323.00
JUSTIFICATION:
1. Item: Owner request
CHANGES IN CONTRACT PRICE AND CONTRACT TIMES:
We propose that the Contract Price and Contract Times be changed as follows:
For Contract Price, when requested by Engineer, attach detailed cost breakdowns for Contractor and
Subcontractors, Supplier quotations, and other information required.
For the Contract Times, state increase, decrease, or no change to Contract Times for .Substantial Completion,
readiness forfenal payment; and Milestones, ifany. /fincrease or decrease, state specific number ofdays for changes
to the Contract Times.
Contract Times (da S
Descri tion Amount Substantial Final
1. Item —Direct Costs $1,323 0 0
2. Item — Marku s. 5% Subs / 15% TCI $0 0 0
Total Thts Change Order Proposal ... �_.... — $1.,323 __.....�..e.a ._....__wa �m................�...................
Changes to Milestones if any: 0 days.
The adjustment proposed is the entire adjustment to the Contract to which the proposer believes it
is entitled as a result of the proposed change.
Change Order Proposal By:
Signature of Proposer: . _._.—
a
as
N
00
O
H
n
W
o
ry
Q
N
I
i
®
O
um
a
90
-Ca
0
avro
_j
F
�+
w
W9
A
a
d
`�
w
H
a
«1W
N k P ti
®
� "
A'
U
611�1
1.9 613In6q'W
d
0
b®®®®
o
o
®
w Z
0 C,
z
n
v V
�I
rc�
c�
`
I
w
oI
r
b,
U-
, 1Isec,
Phone;
CONTRACTORS & ENGINEERS (219)769-6007
Fax;
9111 Louisiana Street (219) 769-0565
Merrillville, Indiana 46410
May 11, 2017
Thienemen Construction
17219 Foundation Parkway
Westfield, IN
ATTN: Mr. Craig Steele
RE; REVISED STUDY
SOUTH BEND WWTP
Mr. Steele;
We are submitting for your use our proposal to furnish a revised short circuit study. This is due to AEP
using a different transformer than they provided data on.
Square "D" $ 1,100.00
PM 135.00
Profit _62.00
Total $ 1,297.00
If you have any questions or comments please feel free to contact me.
Sincerely yours,
Sweney Fit- t.ie Company, Inc.
I
'omas C. Niermeyer
1600 Northwlnd Parkway a Hobart, Indiana 46342 a 219.947.8800 ■ Ra% 219.9472300
9
May 11, 2017
Sweney
9111 Louisiana Street
Merrillville, IN 46410
: South Bend WWTP Study Adder
Sweney PO # TCNIS035
SQD Q2C # 37064586
Attention: Tom Niermeyer
Tom:
The total cost adder to revise the SQ D study to include the 750KVA transformer feed is $1,000.00
This revised amount includes new labels also.
Regards,
ta.
I
Brian Szczerbowski
Leiner Electric Company
•DI:7riGllBuruf• l:'l+•rhieir/.`�ep/dire;llunrn,atinn/hnr/+rrt.+•Lie,rKpr6lr+n(�rrrernf,tnl+riiwu•(,i'rrr•roars•;lular,brlrv/lJrrr+(.iilGv'rims•/ldhtleuntreenrirrrtioul'rorluru
ILIpPp17 C�" Ilr'iPr.i . Aulrutri,tl S7rp/rlir, • l_��ur„ rrrridl �:" Grdurrrnal Litbtirr•K
• Special Serldeesr 2-t llr,nr I:irlrrx"+rrp r1-lnroP Repair • (ri,rrrraw .:'rrrirr i:• You'd • ! lrn r .1}rnYu/r : isi;,urrr
190 9061c2000 tgiatw d Firm 'ks "p
„A "VNO' Y- Wit,
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date
Name
November 19. 2018
Jacob M. Klosinski
Department Utilities Wastewater
BPW Date November 27, 2018 Phone Extension (574)" 235 9496
i6MMYIP.2Ul'a"J�I "WWY�d' WMY91it�kP�"!Y'dWWWWW'�NM'i�'F'YdYb4�'ri��Yl Vl�.ild,�:. ._. ✓Ptak'. ':',�WWVWWIIIW dV+�Y�,�Y�Du�y!NFIY. � w+mmnvnr�— �my�„.. IVfY1(W�NVi3 v �iui�Pr9�oPi�,� �. ��1F�IWIMrtrvil' mmrwam �a�..m.:ft'L�NINININIIIIIII II����N':M�YW."A'ek bEr^uJ,✓�iYiN „kuVX
Required_ "'_ ... ....... , ._ .....� ._ ti ..e...._
Prior to Submittal to Board
Legal ®
Attorney Name Clara McDaniels
Controller ®
Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ®
*AI Greek Director of Utilities*
..m.......... ... _. _ _���_ ��_ .__ .... _ ---
Check the Appropriate Item Type — Required for All
❑ Agreement
❑
_Submissions
Contract Proposal Addendum����
El
Professional Services
Resolution
Bid Opening
El
Bid Award ❑ Req. to Advertise ❑ Title Sheet
Quote Opening
❑ Quote Award
Change Order No.
® C/O & PCA No. 20 Final ❑ PCA
�]
Ease/Encroach.
❑ Traffic Control
❑
Other: �
.............
m........ ___�_�....�__�. � �..._ _...._ _.._....�...
�._ m....�
Information
�� � Ruired_..� ��...._..._�. ..... �._ ..m ............. ��
Company or Vendor Name
Thieneman Construction Inc.
New Vendor
E] Yes ® No E If Yes, Approved by Purchasing
MBE/WBE Contractor
❑ MBE ❑ WBE
MBE/WBE Contractor Requested ❑ No ❑ Yes Name of Company
Project Name
Wastewater Treatment Pla
nt ant Secondary Treatment Improvements
Project Number
114-053
un ource
m g
_...._n.. �............ ..
......
2018 Wastewate r Capital Account. _...___................�..._._..... ___m.,.. ............
Account No.
642-0630-415-43-66
Amount
$ �.....�
Terms of Contract
Purpose/Description
The Division of Utilities recommends the approval of Chang Orden
No. 20 Final and the Project Completion Affidavit for the subject
ro'ect as noted in the attached Inter -Office Memordandum and
Change Order Documents.
❑ Required Contractor's Certification Form Attached (Non -
Collusion,_.. N _. Non -Debarment, E Verif Ir
Win, etc.
Required For Change Orders Onll
Amount of
Increase
mm. m W .
3 07
$ 32 ...._ . __ ,.. me.........._..._ _....
❑
Decrease $
Previous Amount
..........................���� ��.�....................��...........��r ��.........�........................���....,,..................._
3,886,597.
...........
Current Percent of Chan g e:
+91�_
„� �_� �...........�.... �
0.0
.003%
New Amount
,
$ 13,886,920.98
Total Percent of Change: +16.84%
Dispersal After Approval����
Copy Original
® ❑ Al Greek, Director of Utilities
® ❑ Jacob M. K I o s i n s k i, Assista t City ..�_ ,�� er
® ❑ Susan Zeeb, a Director of Fin EngineFinancial Services Wastewat
er