RE: Change Order No. 1 - Bowman Creek Improvements — Project No. 118-017
Dear Mr. Kuhns:
The Board of Public Works, at its meeting held on November 27, 2018, approved the above
referenced Change Order for an increase of $765, plus an additional one -hundred fourteen
(114) days, bringing the current contract amount to $98,240 and the new project completion
date to November 18, 2018.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK JAMES A. MUELLER THERESE J. DORAU
��,z9au'rd t� L
CITY OF SOUTH BEND, INDIANA-',
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER awe»
DATE: 8/3/2018
PROJECT NO: 118-017
PROJECT NAME: Bowman Creek Improvements
CONTRACT DATE: 6/12/2018
CHANGE ORDER NO: 1
SUBJECT OF CHANGE ORDER: PCR #1-Double Swinq Gate PCR #2-Time Extension
The original contract sum
$ 97,475.00
Net change by previously authorized change orders
$ _ 0.00
The contract sum prior to this change order
$ 97,475.00
By this Change Order, the project amount is
X Increased
Decreased $ 765.00
The new contract sum including this change order
$ 98,240.00
This Change Order represents a total change of
0.78
Total change for entire project
0.78
Original contracted completion date/time
7/27/2018
Extension of date/time by previous change orders
0 da s
Date/time extension by this change order
114 days
New completion date/time
11/18/2018
CONTRACTOR
ED FOR AP
Contractor Signature
CONS'TR ON MANAGER
ToP. K�,144S
CITY OF SOUTH BEND
Printed Name and Title
BOARD OF PUBLIC WORDS
Approved Date; ... I
pp
Sel a Construction Co. inc.
Company Name
* ^.
Gary A. Gilt, President
2833 S 11 th St
Address
14 1Y d
Niles„ MI 49120
City, State, Zip
Elizabeth A. Maradik, Member
Therese J. orau„ "ember
James A. Mueller, Member
8"r�,w'
Selge Construction Co., Inc.
2833 S. 111h Street - Niles, Michigan 49120
P:269.684,0842 F:269.684.0846
" kW:oA
November 7, 2018
City of South Bend
Div. of Engineering
Attn: Mr. Scott Kreeger, P.E.
227 W Jefferson Blvd, STE. 1316
South Bend, IN 46601
RE: BOWMAN CREEK IMPROVEMENTS PROJECT
SOUTH BEND PROJECT NO. 118-017
REQUEST FOR TIME EXTENSION
Scott,
As you are aware, this project had a completion date of July 27, 2018. Due to the lengthy
fabrication and galvanizing time frames, we were not able to take receipt of these custom
fabricated grates and gates until the end of October 2018 at which time we proceeded with the
installation of this work. We brought this to the City's attention during our preconstruction
meeting on July 19th, 2018 and depicted it in our project schedule that we submitted during the
meeting. I have attached the original project schedule that we submitted along with a letter
from our vendor stating the length of time needed to fabricate and galvanize the grates and
gates. Below is listed the sequence of events for this project. They are as follows:
Descrl tion
1) Bid
2) Award
3) PO — Evans Metals
4) Notice to Proceed
5) Original Completion
6) Submittal and Field Drawings
7) Submittal Review Returned
8) Fabrication —start
9) Grates / Gates shipped to Galvanizer
10) Grates Delivered
11) Gates Delivered
12) Work Commenced
Date
._ 5/22/2018
6/12/2018
7/10/2018
7/19/2018
7/27/2018
8/21/2018
8/23/2018
8/24/2018
10/05/2018
10/26/2018
11/01/2018
11/05/2018
CEMEI0MOO ROOM'
July 10, 2018
Selge Construction Co., Inc.
2833 S. 1P Street
Niles, MI 49120
Attn. Bob Kuhns
Re: Bowman Creek Improvements
PO BK071018
Thank you for your recent order. Our current production schedule is approximately 8 —12
weeks. Please contact our office with questions.
L".
Bruce W. Rienks
Sr. Project Manger
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date November 16, 2018
Name Scott Kreeger
Department Public Works
Division/Bureau Engineering
BPW Date November 27, 2018 Phone Extension 9245
')FkidA" ��;pIW��CY�WiW.i;�RPMIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIVIIIIIIIIIIIIIMGM/AUAO.WNINp, + u. .....i... ��t��� � NiJ.MWVIWd9NNV'V'WWW��^^^����"`^^^NYhA^�H/H/H/HMIMNIMIIIIIIIINr//�FMI�'M�'M�'M�'M�'M��NANIiDbUINI� v JIIIfSIdkdVPY(d;Po
.�...................... mm...........
Re uired Prior to Submittal _...�.......... _._......��.�w_� �..____.�� .� al to Board
0
Legal E] Attorney Name: Clara McDaniels
Controller E] Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing
_......... ..........
the
Lj Agreement Amendment
Professional Services
❑ Bid Opening
❑ Quote Opening
® Change Order No. 1
❑ Ease/Encroach.
Other:
�r riate Item Type �-
El Contract
Resolution
for All Submissions
] Proposal
❑ Bid Award ❑ Req. to Advertise
❑ Quote Award
C/O & PCA No. ❑ PCA
❑ Traffic Control:
Required Information
Addendum
❑ Title Sheet
II Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
.. ..._.. v.. u . ...poi od For Chang e Order ,On
Amount of E] Increase $y
Decrease $
Previous Amount $