Loading...
HomeMy WebLinkAboutChange Order No 2 - INDOT - SRTS Monroe Primary and Studebaker Elementary Proj No 116-039Contract No:R -39513 Change Order No.: 002 INDIANA Department of Transportation Page:1 Construction Change Order and Time Extension Summary Contract Information Contract No.: R -39613 Letting Date: 10/1212017 Distdct:LAPORTE DISTRICT AE:Forgey, Ryan PE/S:Miliion, Jeff Status -Draft Change Order Information Change Order No.: 002 EWA: Y or Farce Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: CHANGED COND, Constructabllity Related Description: Additional cost and time extension for root removal. Original Contract Amount $1,938,001.25 Current Change Order Amount $10,990.04 Percent: 0.567 % Total Previous Approved Changes $-12,649.50 Percent: -0.648 % Total Change To -Date $-1,559.46 Percent: -0.081 % Modified. Contract Amount $1,936,441.7'9 Time Extension Information Date Initiated 00/00/0000 Date Completed 00/00/0000 Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) Time Element Description: Current Time Extension SS Days 0 SP Days 14 SP Days Value $ 0.00 Previous Time Approved SS Days by AE:_ DCE: SCE: DDCM: SS Days SP Days Value $ Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -39513 Change Order No.: 002 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approved Information Required Approval Authority AE: DOE: SCE.,-* DDCM: " ($ per Change Order) (Days per Contract) Verbal Approval Required? Total Change To-Date>5°/a? Scope/Design Recommendation Required? (-LE$250K3{-LE$750K-) (--LE$2M--)(--GT$2 M--) ( 50 SS days) (100 SS days ) ( 200 SS Days ) ( GT 200 SS days) a/ N If Y, by �_ Date Issued l Y /&f Y, Copy to Program Budget Manager Y / N If Y, Referred to Project Manager(PM) Date to PM Approval Authority Concurs with PM? Y / N if Y, Concurrence by, Date Returned Date If N,Resolution: Approved Disapproved Resolved by Date LPA Signatures Required? N If Y, Date to LPA Date Returned FHWA Signatures Required? Y Gif Y, Date to FHWA,,- ^, , pate Returned * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer Comments: Date Contract No:R -39513 INDIANA Change Order No:002 Department of Transportation Date:07/27/2018 Page: 3 Contract: R -39513 Project: 1600075 - State;160007500LC4 Change Order Nbr: 002 Change Ordar Description: Additional cost and time extension for root removal. Reason Code: CHANGED COND, Constructability Related Oi.N PCN PLN Item Code unit Unit Prise CtJ Qty Comment Amount Change 0041 1600075 0040 105.06007 LS 10,990.040 1.000 G Amounl:$ 10,990.04 Item Description: ADDITIONAL Supplemental DescdptlonI., Cost for tool removal Supplemental Descdption2: Total Value for Change Order 002 = S 10,990.04 Milestone Time Adjustment Mileslons Nbc 01 Milestone Description. INTERMEDIATE COMPLETION DATE 1 Original Completion dt: 09/07/201 a Adj comp) dt 09/2112018 Ad) No. of Days 14 Explanation. The Intermediate Completion Date to complete all of the concrete work on this project needs to be extended 14 calendar days due to the delays caused by the extreme amount of root removal encountered on this project, mainly along Woodside, Oakside, and Eckman Sts. This 14 days Includes the time Involved removing the roots as wall as The time needed to Import and replace the borrow material to fill the voids left by the root removal. Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation This change order adds a new lump sum item to cover the cost Incurred by the contractor for the removal of the extreme number and size of the tree roots encountered on this project, mainly along Woodside, Oakslde, and Eckman Sts. This work Involves the actual root removal as well as the hauling away of this debris. This change order also Includes a time extension of 14 calendar days to the Intermediate Completion Date of 9107118. The time delays involve the extra work for the root removal along with the time It takes to import and replace the borrow material to till the voids left by this removal. Change Order Explanation for Specific Line Item H....... .. H a...... ...... a} •+Ha } a H a R H+Y H++f a a t R H a a aY tt H H.... .....1. H.. Ma.......... k It Is the intent of the parties that this change order Is full and complete compensation for the work describe above. Notltication and consent to this chancre order Is herebv acknowtedoed. Contractor Date: Signed By: ) ): a... N a. a.......... —*....++..............tat. a......... H....... H........A.......... t+,.. NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Contract No:A -39613 INDIANA Date:07/27/2018 Change Order No:002 �s:��e�.s.�m-✓r�xm�.�a�rr ,.rxaerswx:s:az.��rrreasrx.+zcct�mas+n-w� Department of Transportation Page: 4 •►ff.ff)..)M.M....0......N..il.i...iH!l..�•liH.............yfyl.Ml.lyyy HM.ly1!!.L}1.1y.!l.11y11yyl ....... APPROVED FOR LOCAL PUBLIC AGENCY o Lc 6R L!;l A,uz 1'ecl-t7— 9// 5l/,,;�o u (816NA FIE) (rTLE) (DATE) 7� (SIGNATURE) (TITLE) (DATE) FOR CON DERATION =*w'Tr IE'AI��Z. ,, ► ............... .Myf.l.h ................!y.......y.y..y M........ y+Hif.M.HM... ..f)!.•f Mfg. APPROVED FOR INDIANA DEPARTMENT OF TRANSPORTATION ApprovalLevel Name of Approver bate Status BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM Date August 6, 2018 Name Roger Nawrot Department Public Works Division/Bureau Engineering BPW Date August 14, 2018 Phone Extension 5932 Rpn uired Prior to Submittal to Board Legal 01 Attorney Name. - Controller F-1 Controller review is required for all Contracts $5,000.00 or more and greater than one year in length per the City Purchasing Policy Purchasing El U Agreement El Professional Services F-1 Bid Opening ❑ Quote Opening Change Order No. 2 El Ease/Encroach. F1 Other: Company or Vendor Name LJ Contract El Resolution F1 Bid Award' F] Quote Award F1 C/O & PCA No. F1 Traffic Control: New Vendor MBEN\1BE Contractor MBEN\1BE Contractor Requested Project Name Project Number Funding Source Account No. Amount Proposal El Req. to Advertise Elm I Indiana Department of Transportation Addendum ❑ Title Sheet 10 No If Yes, Approved by Purchasina IN M _BE 9 ­­WB E LJ No LJ Yes Name of CoMpapy SRTS Monroe Primary and Studebaker Elementary R-39513 116-039 Terms of Contract Federal 80% and City 20O/o Purpose/Description This change order if for additional excavation and disposal for the -removal of tree roots removed under the new sidewalk. Ll Required Contractor's Certification Forms Attached (Non - Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.) Rc�uird For Chan Orders �r�ly Previous Amount $ 1,925,451.75 Current Percent of Change: 0.567% New Amount $1,936,441,791 Total Percent of Di s ersal After A royal Copy Original F] F-1 R El