HomeMy WebLinkAboutNo. 2864 approving/authorizing the execution of an amendment to the addendum to the Master Agency Agreement (Two Way Traffic Plan - Lafayette & William - Supplement #1)RESOLUTION NO. 2864
RESOLUTION OF THE SOUTH BEND REDEVELOPMENT COMMISSION
APPROVING AND AUTHORIZING THE EXECUTION OF AN AMENDMENT
TO THE ADDENDUM TO THE MASTER AGENCY AGREEMENT
(Two Way Traffic Plan - Lafayette and William - Supplement #1)
2864 -11
WHEREAS, effective January 1, 2011, the South Bend Department of
Redevelopment, acting by and through its Redevelopment Commission (the
"Commission ") and the South Bend Board of Public Works (the "BPW ") entered into a
Master Agency Agreement which authorized the BPW to act as agent for and on behalf
of the Commission for certain projects during 2011; and
WHEREAS, effective January 1, 2011, the Commission and the BPW entered
into a Master Agency Agreement which authorized the BPW to act as agent for and on
behalf of the Commission for the limited purpose of contracting for and managing the
%� completion of existing Projects; and
WHEREAS, pursuant to the Master Agency Agreement, the Commission added
the Two Way Traffic Plan - Lafayette and William to the Master Agency Agreement by
way of an Addendum on February 5, 2010; and
WHEREAS, the Commission desires to amend the Addendum by way of this
Amendment.
NOW, THEREFORE, BE IT RESOLVED by the South Bend Redevelopment
Commission as follows:
Section 1. The Commission hereby approves the Amendment to the
Addendum to the Master Agency Agreement (Two Way Traffic Plan - Lafayette and
IcWilliam - Supplement #1) and hereby authorizes its execution in substantially the form
attached hereto with such changes as the Commission may deem necessary or appropriate
upon the advice of counsel, said execution thereof to be conclusive evidence of the
Commission's approval of such changes. The Clerk is hereby directed to file a copy of
this Amendment to the Addendum with the BPW.
Section 2. This Resolution shall be in full force and effect after its adoption
by the Commission.
Section 3. Commission staff members are authorized to execute on behalf of
the Commission any documents necessary to carry out the intent of this resolution.
ADOPTED at a meeting of the South Bend Redevelopment Commission held on
April 12, 2011, at.4:00 p.m., in Room 1308, County -City Building, South Bend, Indiana
46601.
CITY OF SOUTH BEND,
APWN DEPARTMENT OF
REDEVELOPMENT
Marcia I ones, President
South Bencf Redevelopment Commission
ATTEST:
Nancy N. King Secretary
South Bend Redevelopment Commission
A
AMENDMENT TO THE ADDENDUM TO THE
MASTER AGENCY AGREEMENT
(Two Way Traffic Plan - Lafayette and William - Supplement #1)
2864 -11
This Amendment to the Addendum to the Master Agency Agreement (this
"Amendment "), made and entered into as of the 25th day of April, 2011, by and between
the South Bend Department of Redevelopment, acting by and through its Redevelopment
Commission (the "Commission ") and the City of South Bend, Indiana, a municipal
corporation duly organized and existing pursuant to the laws of the State of Indiana,
acting by and through its Board of Public Works (the "BPW ") for purposes of the
Commission designating the BPW to act as the Commission's agent to undertake the
Two Way Traffic Plan - Lafayette and William - Supplement #1 (the "Project ").
WHEREAS, effective January 1, 2011, the Commission and the BPW entered
%� into a Master Agency Agreement which authorized the BPW to act as agent for and on
behalf of the Commission for certain projects during 2011; and
WHEREAS, effective January 1, 2011, the Commission and the BPW entered
into a Master Agency Agreement which authorized the BPW to act as agent for and on
behalf of the Commission for the limited purpose of contracting for and managing the
completion of existing Projects; and
WHEREAS, pursuant to the Master Agency Agreement, the Commission added
the Two Way Traffic Plan - Lafayette and William to the Master Agency Agreement by
way of an Addendum on February 5, 2010
WHEREAS, the Commission desires to amend the Addendum by way of this
Amendment.
C9
NOW, THEREFORE, in consideration of the mutual covenants and promises
contained herein, and for other good and valuable consideration, the receipt of which is
hereby acknowledged, the BPW and the Commission agree as follows:
The Commission hereby empowers and appoints the BPW, pursuant to the
Master Agency Agreement, to act as the Commission's agent for the limited purpose of
contracting for and managing the completion of the Project, the scope of said Project
being originally described in "Exhibit A ", and now amended as described in "Exhibit B ",
attached hereto and made a part hereof.
2. All of the terms and conditions of the Master Agency Agreement shall
control this appointment and this Addendum shall be attached to the Master Agency
Agreement.
3. Commission staff members are authorized to execute on behalf of the
Commission any documents necessary to carry out the intent of this resolution.
IN WITNESS WHEREOF, the undersigned execute this Addendum to Master
Agency Agreement to be effective as of the date first written above.
(Signature Page Follows)
11
cw CITY OF SOUTH BEND,
DEPARTMENT OF
REDEVELOPMENT
ATTEST:
South Bend Redevelopment Commission
LM
ATTEST:
Linda Martin, Clerk
u
South Bend Redevelopment Commission
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
Gary Gilot, President
Carl Littrell, Member
Don Inks, Member
Exhibit "A"
Two Way Traffic Plan - Lafayette and William
See attached Proposal from Wightman Petrie dated December 7, 2009
D4
7L,q_
December i, 2009
City of South Bend
Community and Economic Development
1200 County -City Building
South Bend, IN 46601
Attn: Bill Schalliol
RE: PROPOSAL FOR CORRIDOR ANALYSIS OF WILLIAM STREET &
LAFAYETTE BOULEVARD TWO -WAY CONVERSION
Dear Bill:
Thank you for contacting Wightman Petrie, Inc. (WPI) regarding the traffic evaluation and
striping plans for the William Street and Lafayette Boulevard Two Way Traffic Study Area. With
the completion of the conceptual streetscape improvements in the study area, the corridor
analysis should now be prepared before the City implements two -way traffic on both William
Street, and Lafayette Boulevard
Keeping that in mind, we are very pleased to provide you with the following proposal for your
consideration:
PROJECT UNDERSTANDING
WP understands the City of South Bend would like to convert both William Street and Lafayette
Boulevard from one -way streets to two -way streets. In order to insure this is done properly, the
City desires a corridor analysis be performed to determine the best configuration of the new
roadways. This analysis would need to include traffic modeling of the two corridors along with
an evaluation of the existing infrastructure, including existing signal equipment.
As part of the final report, recommendations will need to be made as to the recommended traffic
control at the intersections within the study area (i.e. traffic signal, 4 -way stop, etc.), along with a
striping plan for the two roadways. The City also desires an estimate of the cost to implement
the plan. A preliminary estimate will also need to be prepared to serve as a place holder in the
City's annual budget.
V'�/1;HTfl ETRI E
SURVEYING ENGINEERING ENVIRONMENTAL LANDSCAPE ARCHITECTURE
City of South Bend
William and Lafayette Two -Way Conversion
December 7, 2009
Page 2 of 5
SCOPE OF SERVICES
TASK 1- PROJECT MANAGEMENT
This task will include overall project management for the tasks listed below. In addition, three
meetings with the City are included to discuss the project as needed and to discuss the results
of the study.
TASK 2 - TOPOGRAPHIC SURVEY
A. FIELD SURVEY (LAFAYETTE BLVD. LIMITS)
A limited topographic survey will be performed in the area. The survey will be limited to the
geometric locations at intersections where GIS data is not clear:
• South limit - South Street and Lafayette Blvd. intersection.
• North limit - Madison Street and Lafayette Blvd. intersection.
• Extreme limits - Existing travel portion of roadway
• Location of manholes as needed
B. TOPOGRAPHIC FIELD SURVEY (WILLIAM STREET LIMITS)
A limited topographic survey will be performed in the area. The survey will be limited to the
geometric locations at intersections where GIS data is not clear:
• South limit - The dead end of William Street at Coveleski Stadium.
• North limit - William Street and Madison Street intersection.
• Extreme limits - Existing travel portion of roadway
• Location of manholes as needed
Property lines will be based upon City /County GIS Data.
In addition to the above, limited topographic information for intersections where the existing
grade may be a concern will also be collected to determine the existing pavement cross slopes.
These areas will need to be identified by the City and WP staff prior to starting the survey
component of the project.
TASK 3 - DATA COLLECTION
This task will consist of the necessary data collection to perform the required analyses to
complete the corridor study. The data collection items anticipated and included in this fee
proposal are as follows:
1. 12 -hour (6 am to 6 pm) intersection turning movement counts for all intersections within
the proposed corridor study area. 12 -hour counts will be necessary to perform the
requested traffic signal warrant analyses at the study area intersections. The general
study area includes a total of 17 intersections, and is generally as described below:
• William Street from Western Ave. to Lincolnway
• Lafayette Blvd. from South St. to one block north of Lincolnway
City of South Bend
William and Lafayette Two -Way Conversion
December 7, 2009
Page 3 of 5
2. Obtain and review existing signal timing data for signalized intersections. This
information will need to be provided by the City and /or INDOT.
3. Existing geometrics of the study area, including number of lanes, auxiliary lanes, turn
restrictions, on- street parking, etc.
TASK 4 — TRIP GENERATION, TRIP REDISTRIBUTION & TRAFFIC ASSIGNMENT
This task will consist of projecting the anticipated redistribution of traffic as a result of changing
William Street and Lafayette Blvd. from one -way streets to two -way streets. For this analysis,
we propose to utilize the previously prepared DLZ study for Main St. /St. Joseph St. /Michigan St.
two -way traffic conversion to the extent feasible.
It will be important that the City Engineering office participate in reviewing the redistribution
analysis prior to completing the detailed analysis of the intersections within the study area.
The redistributed traffic information will then be utilized to model traffic projections at the
individual intersections to project individual turning movements at each intersection within the
study area. This information will be used in several of the analysis items in Task 5.
For the purposes of this study, a horizon year of 2025 and an appropriate growth rate will be
developed to be utilized for the projected future traffic. This matches the methodology and
horizon year used in the previous DLZ study.
In addition to the above redistribution, it will be important to incorporate the redevelopment of
the future site located north of Coveleski Park. This task will involve projecting new traffic
to /from this site and distributing it within the study area. It will be important for the City to aide in
a determination of what development will occur on this site. The traffic projected from this site
will be added to the future (2025) scenario.
TASK 5- ANALYSIS
This task will involve the analysis of two scenarios as follows:
1. Existing traffic conditions after the two -way conversion
2. Future (2025) traffic conditions with two -way conversion
Note that no analysis is being proposed for the existing condition of the one -way pair. This
analysis could be completed at the City's request, but is not included in the scope of this study.
The analysis will be performed at all intersections within the study area for the AM and PM peak
periods as determined by the traffic count data. For the analysis, a model will be developed
using the Syncho 7 software. The following is a list of analyses that will be performed at each
intersection within the study area:
1. Capacity analysis, including level -of- service and delay calculations
2. Queuing analysis at all approaches to the intersections
3. Evaluation and warrant analyses to determine the most suitable traffic control (i.e. traffic
signal, 4 -way stop, 2 -way stop)
City of South Bend
William and Lafayette Two -Way Conversion
December 7, 2009
460'� Page 4 of 5
4. Progression analysis along each corridor
5. Modifications to existing signal equipment if a signal will be recommended
TASK 6 — REPORT
This task will involve draft and final versions of the corridor study report. The report will outline
the conclusions reached as a result of the analyses and make geometric and traffic control
recommendations for each intersection within the study area, including signal upgrades
necessary as a result of the conversion. The report will also include a conceptual corridor
striping plan for both William Street and Lafayette Blvd.
The draft report will be submitted to the City for initial review. After comments are received, the
report will be revised to address comments and a final draft will be prepared.
TASK 7 — PRELIMINARY CONSTRUCTION COST ESTIMATE
The first task will include a preliminary estimate of the construction costs associated with
converting both Williams St. and Lafayette Blvd. for the City to utilize for budgetary purposes.
The preliminary cost estimate will be updated after the City has reviewed the report and has
agreed to the recommended improvements.
FEES
The total lump sum fee to provide the tasks outlined in the Scope of Services is as follows:
8 700.00
Task 1 — Project Management
$
Task 2 — Topographic Survey
$ 6,000.00
Task 3 — Data Collection
$26,760.00
Task 4 — Trip Redistribution & Traffic Assignment
$23,360.00
Task 5 — Analysis
$36,120.00
Task 6 — Report
$23,700.00
Task 7 — Preliminary Construction Cost Estimates
$ 2.720.00
Total Professional Services Lump Sum Fee: $127,360.00
EXCLUSIONS
Be advised that the services and fees quoted above do not include the following activities or
services:
1. Engineering Design of Any Recommended Improvements*
2. Reimbursable Fees
*These services can be provided by Wightman Petrie and would be subject to a new and
separate agreement.
rM
City of South Bend
William and Lafayette Two -Way Conversion
December 7, 2009
Page 5 of 5
Should you have any questions, please do not hesitate to contact me at 574 - 232 -4388. Thank
you for the opportunity to be of service.
Sincerely,
David M. Rafinski
Vice President
1AProposals\City of South Bend\Streetscape Desgn\Wlliam and Lafayette - 12-7 -
09.docx
Accepted By: _ Date:
Printed name an�" •'
Business name:
Billing address:
Billinglaccount manager:
Phone No.: Fax No.: E -mail:
rW
"M