HomeMy WebLinkAboutAward Quotation and Terminate Previous Contract - 2018 Tree and Stump Removal Project No 118-048A - K&R Tree Service"Ovvl#
INTER -OFFICE ME,MORANDiU
DEPARTMENT OF PUBLIC WORK
ITACT DIVISION OF ENGINEERING
TO: Linda M. Martin, Clerk
Board of Public Works
FROM: Tara Weigand, Project Engineer "'XJ
SUBJECT: Award Project No. 11 8-048A
2018 Tree and Stump Removal
DATE: July 16, 2018
On June 12, 2018, - the Board of Public Works awarded the above project to the low quoter
Kachur Tree Service, LLC, However, following the award of contract the Contractor indicated to
the City that he wished to reject their bid and signature from the contract. In response, a Notice
of Termination was sent to Kachur Tree Service, LLC.
Following the contract termination, the next lowest quoter, K & R Tree Service was contacted.
They indicated that they would honor the quote they submitted for this project, which was opened
and read at the May 8, 2018 Board of Public Works meeting.
As a result, I recommend award of a contract for 2018 Tree and Stump Removal to the next
lowest responsive / responsible quoter, K & R Tree Service in the amount of $ 15,625.00.
Sufficient funds have been has appropriated from MVH, 202-0619-431.31-06.
Please call with your questions (5998).
Enc. Notice of Termination
1200 CoUN'I*Y- : ,rN,BUII.I)ING
227 W. JETTEASON I3t:)uIFi FARD
S(u,n I BI1 ND, IN DrANA 46601-1830
CrI"Y 01 Sou '1 r Bl1 IND M."TI? 131J'r "I(;1k,,G, Kwolt
DEPARTMENT OF LAW
STEM LkN1 E S'I'LsF= L,E
C()ICI'I )1' rXI'It: N C:(?[,1I ST71.
July 10, 2018
Mire Kachur
Kachur Tree Service, I...LC
316 Fulkerson Road
Niles, MI 49120
Re: Notice ofTermination
Project 118-048A -- Trce and. Stump Removal
Dear Mr. Kachur:
PrIONF 574/235-924I
FAx 574/235-7670
'I`F' 574/235-5567
A1.I1,I)ISAN M. D1?R(),SI.
CITY -ZVI OItNEY
Thank you for your phone call today to discuss the July 6, 2018 Notice of Default sent by the City.
During our discussion today, you indicated that you wish were withdrawing your quote for City
Project 118-048A — Tree and. Stump Removal and would not sign the Board of Public Works, City
of South Bend, Indiana Public Works Contract dated June 12, 2018. In confirmation of your
intentions, you sent an email to my attention, dated. July 10, 2018, wherein you stated that:
"Kachur Tree Service, LLC rejects our: bid and signature frorm the contract. Kachur "free Service,
LLC allows you to go to the next bidder and hire out someone else to complete the work."
Therefore, the City of South Bend, Indiana, pursuant to section XI. 2, of the Agreement is
exercising its option to terminate the Agreement with. Kachur Tree Service, LLC.
.'1° . U Sincerely,
1 . d f Pu.hliI Workq
lara McDaniels
+�"" ' ' Assistant City Attorney
cc: Tara Weigand
Toy Villa
Kara Boyles
ELLIO T A. ANDERSON ASHLEY NHLLS COLLORN St NDiC A KEN I' DY
CLARA MCDANIELS THOivIAS E. PANOWICL Dt' NIEL LE CAMPBELL WEISS
1316 COUN'ry-0'ry BUILDING,
227 W. JEFFERSON BOULEVARD
SOUTH RI -ND. INDIANA 46601-18.30
CITY Or SOuT11 BEND PETE BUTT[G I EG, MAYOR
BOARD OFTUBLIC' WORKS
July 24, 2018
Leah Kucher Siderits
Kachur Tree Service, LLC
316 Fulkerson Road
Niles, MI 49120
P110Nt1; 574/235-9251
FAX 5742359171
RE: RESCIND Quotation Award - 2018 Tree and Stump Removal — Project No. 118-
048A
Dear Ms. Kuchur Siderits:
The Board of Public Works, at its meeting held on July 24, 2018, approved your request to
rescind the award of the above referenced quotation to you and terminate the contract.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
GARN, A. GiLo'r SUZANNA M. FRITZBER(i ELIZABL--rii A. MARADIK J AM Es A. M t) F,11,0Ti-a,RESE J. ADO AU
1316 COUNTY-Cii-Y Fig ILUNG
227 W. .1 F'] 1; ERSON BOULEVARD
sotrrll 11�N]
I 1INDIANA46601-1930
CiTY OF SOUTH BEND PETE� BUTTWIE(j, MAYOR
BOARD OF PUBLIC WORKS
July 24, 2018
Kevin Kenney
K&R Tree Service
1724 S. Grant Street
South Bend, IN 46613
PHONE 574/ 235-9251
FAX 574/ 235-9171
RE: Quotation Award — 2018 'Free and Stump Removal — Project No. 11 8-048A
Dear Mr, Kenney:
The Board of Public Works at its meeting held on July 24, 2018, terminated the contract with
Kachur Tree Services LLC and awarded the above referenced quotation to you in the amount
of $15,625.
Please forward the following documents in one submittal by August 7. 201.8 to my attention
for Board of Public Works approval:
1) One (1) original of the Contract (enclosed); and
2) Certificate of Insurance naming the City of South Bend as an additional insured.
If you have any further questions regarding this matter,, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
GARY A. Git,o-r SUZANNA M. FRn,zt3r:RG ELIZAM-rn A. MARADIK JAMEs A. MUELLER Ti I E RESE J. DoR AU
CITY OF SOUTH BEND, INDIANA
CONTRACTOR'S QUOTE FOR PUBLIC WORK
1865
*ROJECTNAME: Tree and Stump. Removal
PROJECT NO. 118-048A
QUOTES DUE _May8, 2018
Date.
s7q
City/State/Zip: A4 LV( . AWNumber:
a Telephone
Agent of Bidder (if Applicable): Val,- —10&,e- 5e-,v-L) rL6
Pursuant to notices given, the undersigned offers to furnish labor andlor material necessary to complete the
public works project of:
I (-e-e- 'S n or, r cl-, b4
the City of South Bend, Indiana, in accordance with plans and specifications prepared by:
The Citv of South Bend, Deoartment of Public Works
and dated Ma Zo tl for the sum of
(Enter Sum of Total Quote shown on Propos)l
ter the Total Quote as shown on the Proposal)
(Numerical)
If alternative quotes apply, the undersigned submits a proposal for each in accordance with the notice. Any
addendums attached will be specifically referenced at the applicable page.
If additional units of material: included in the contract are needed, the cost of units must be the same as that shown
in the original contract if accepted by the City of South Bend. If the quote is to be awarded on a unit basis, the
itemization of the units shall be shown on a separate attachment.
The above quote is accepted this
Subject to the following conditions:
Pill
James A. Mueller, Member
By
(signat
ke 01 N S.
(Printed Narne of Person-9gninq)
day of
-,IA A4,44-
"—ruzarina'10. Pritzb6g, Member
Th ,eke J. Dorau, Member
-,-Mtest: Linda M. MArlin, Clerk
20 / V
Version 1013112017 Page - 8 Public Works Quote
BOARD OF PUBLIC WORKS
CITY OF SOUTH BEND, INDIANA
PUBLIC WORKS CONTRACT
THIS AGREEMENT, made and entered into this 24th Day of July, 2018, by and between, K &
R Tree Service, 1724 S. Grant Street, South Bend, IN 46613, HEREINAFTER called the
Contractor, and the Board of Public Works herein called the "Board"
WITNESSETH: That the Contractor covenants and agrees to make the following improvement,
as fully set out in the Request for Quotations, Standard Specifications, Special Provisions, Plans,
and Bid Proposals, all of which are set forth as a part of this Contract, for:
PROJECT NO. 118-048A
DESCRIPTION: 2018 TREE AND STUMP REMOVAL
COMPLETION DATE: SEE SPECIFICATIONS
AMOUNT: $155625
FUNDING: MVH
The unit prices for this improvement were those prices as received and accepted by the Board on
the 8th Day of May, 2018.
The Contractor further agrees to notify the Engineer when this improvement is completed. This
notification shall be in the form of a Completion Affidavit, signed by the Contractor. Upon final
acceptance of the improvement by the Engineer, the Contractors final estimate will be presented
to the Board for final Payment with one (1) copy of the Completion Affidavit and one (1) copy of
a Waiver of Lien.
BOARD OF PUI�Lj ORKS
Gary. ilot, President Elizabeth A. Maradik, Member
uz M. fritzterg, Jagies A. Mueller, Member
Member
Therese J. Dorau, Member /A/ttest: Linda M. `Martin,
Clerk
K&R TREE SERVICE
Printed Name
Signature
CERTIFICATION (To be completed if Contractor is a Corporation)
I, , certify that I am Secretary of the Corporation named as
Contractor herein; that who signed this Agreement on behalf of the Contractor
was then of said Corporation; that said agreement was duly signed for and in
behalf of said Corporation by authority of its governing body, and is within the scope of its
corporate powers.
Secretary
Corporate
Seal
Date
Name
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
July 16, 2018
Tara Weigand
Department
Division/Bureau
Public Works
Engineering
BPW Date July 24, 2018 Phone Extension 5998
PriorRequired to Submittal to Board
Legal Z Attorney Name: Clara McDaniels
Controller ❑ Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing z
Michael Schmidt
F1
Agreement Amendment
Ll Contract Ll Proposal H Addendum
❑ Professional Services
0
Resolution
❑
Bid Opening
F1
Bid Award ❑ Req. to Advertise Title Sheet
El
Quote Opening
Z
Quote Award
❑
Change Order No.
R C/O & PCA No, ❑ PCA
❑ Ease/Encroach.
F1 Traffic Control:
Other:
Company or Vendor Name K & R Tree Service
0 Yes Z No E] If Yes, Approved by
New Vendor Purchasing
MBEANBE Contractor
MBENVBE Contractor Requested
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
ZME
LJ No L] Yes Name of Company
2018 Tree and Stump Removal
118-04 8A
MVH
202-0619-431.31-06
$15,625.00
Remove trees and stumps for sidewalk replacement at various
locations in South Bend � ,9 , � `7`,-,"
E] Required Contractor's Certification Form's Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
Required For Chan e Orders Only
Amount of F] increase $
El Decrease $
Previous Amount
Current Percent of Change:
New Amount
Total Percent of Change:
Copy
Original
Fj Kara Boyles, City Engineer
F-1 Marcia Qualls, Streets
Tara Weigand,