HomeMy WebLinkAboutAward Quotation - West Race Emergency Repairs Proj No 115-115 - HRP Construction IncINTEROFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Linda M. Martin, Clerk
Board of Public Works
FROM: Sue Ellen Doudrick, Assistant City Engineer
SUBJECT: Award Project No. 115-1 15
Project Name: West Race Emergency Repair
DATE: May 4, 2018
On May 3, 2018, the Board of Public Works opened and read quotes for the above project. I have
reviewed them and found them correct.
The bidders ranked as follows:
Bidder
Base Bid Amount
Alternate A
Alternate B
1. HRP
$72,800
$107,300
$11,300
Engineering would like to award the Base Bid ($72,800) and Alternate B ($11,300) for a project
total of $84,100, The project is to be funded from Hotel/Motel Tax - 7304.42010.000.0099.
Please call with your questions.
w o
CL co c3 0 0 co 6 (D CD� 0
cr a) 0 0 0 w m 0 C) 0 0 m
m C� E cq c� E cq r-z
LA 0) q 00 0
�n 14
m ro m �l
�n �n if) lll� An
m
m
:12-
m
a)
m
on
C,
C0
�
0
CD 1�1
C)
Q
c!
9
<
C,
C3 11
(Y�
0
0
C�
0
0
:!
U)
It
o9
LO
0
JALU
m
E
w
ED
LS
au
LU
LU
HI "I "
m
CL
w
ce
u
dl
lil
M
>
c
S
'o
,
0
0)
sn
am
>
Ln
0
E
LA
c
0
0
m
tw
=
0
uo
rn
co
a
Q
0
M
IM
0
r
0
0
E w
.2
r
'D
c
0
m
0
4�
0
z
E
E
ri
q)
:Ll
w
ct
-
1316 Cotwry-Crry BUILINNG
227 W. JEFFERSON BOULEVARD
SOUTH BFND. INDIANA 46601-1830
CITY OF Soun-i BEND PETE BuTTiG;,'M EG, MAY Bw.vviNrlNnyrm-� --,F.
May 8, 2018
Matthew Cain
HRP Construction Inc
5777 Cleveland Road
South Bend, IN 46624
PHONE 574/ 235-9251
FAX 574/ 235-9171
RE: Quotation Award — West Race Emergency Repair — Project No. 115-115
Dear Mr. Cain:
The Board of Public Works at its meeting hold on May 8, 2018, awarded the above referenced
quotation to you in the amount of $ 84,100 for the base bid plus alternate B.
Please forward the following documents in one submittal by May 22, 2018 to my attention
for Board of Public Works approval:
1.) One (1) original of the Contract (enclosed); and
2) Certificate of Insurance naming the City of South Bend as an additional insured.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Q., L
0 -
Linda M. Martin, Clerk
C: Sue Ellen Doudrick, Engineering
GARY A. GiLOT SUZANNA M. 1 RITZ13ER(3 EuZABEI,ii A. MARADIK JAMP's A. MUf31,1,1 R THERESE J. DORAU
BOARD OF PUBLIC WORKS
CITY OF SOUTH BEND, INDIANA
PUBLIC WORKS CONTRACT
THIS AGREEMENT, made and entered into this 8th Day of May, 2018, by and between, HRP
Construction Inc., 5777 Cleveland Road, South Bend, IN 46624, HEREINAFTER called the
Contractor, and the Board of Public Works herein called the "Board".
WITNESSETH: That the Contractor covenants and agrees to make the following improvement,
as fully set out in the Request for Quotations, Standard Specifications, Special Provisions, Plans,
and Bid Proposals, all of which are set forth as a part of this Contract, for:
PROJECT NO. 115-115
DESCRIPTION: WEST RACE EMERGENCY REPAIR
COMPLETION DATE: SEE SPECIFICATIONS
AMOUNT: $84,100; BASE BID PLUS ALTERNATE B
FUNDING: HOTEL/MOTEL TAX
The unit prices for this improvement were those prices as received and accepted by the Board on
the 3rd Day of May, 2018.
The Contractor further agrees to notify the Engineer when this improvement is completed. This
notification shall be in the form of a Completion Affidavit, signed by the Contractor. Upon final
acceptance of the improvement by the Engineer, the Contractors final estimate will be presented
to the Board for final Payment with one (1) copy of the Completion Affidavit and one (1) copy of
a Waiver of Lien.
BOARD OF PUBLIC—W S
Gary A. Gi ot, President f
Suzanna M. Fritzberg,
Therese J`"Dorau, Member
Clerk
HRP CONSTRUCTION INC
A. Maradik, Member Printed Name
Y
A. Mueller, Member Signature
Linda
CERTIFICATION (To be completed if Contractor is a Corporation)
I, , certify that I am Secretary of the Corporation named as
Contractor herein; that who signed this Agreement on behalf of the Contractor
was then of said Corporation; that said agreement was duly signed for and in
behalf of said Corporation by authority of its governing body, and is within the scope of its
corporate powers.
Secretary
Corporate
Seal
No -
Address
West Race Erriergency_qep ir
115-115
May 3,..2018 before 10:30 a.m.
(Must be completed for all quotes. Please type or print)
5/3/18 — Firm: HEAP CONSTRUCTION INC.
5777 Cleveland Road, P.O. Box 266
City/State/Zip: South Bend, TN 46624 Telephone Number:
Agent of Bidder (if Applicable):
Pursuant to notices given, the undersigned offers to furnish
public works project of:
West Race EmerQencv Renair
574 1 271-7800
iabor and/or material necessary to complete the
the City of South Bend, Indiana, in accordance with plans and specifications prepared by:
Thie City of South, Bend, Department of Public Works
and dated — 41201..B ] - for the sum of (enter the Total Quote as shown on the Proposal)
See Attached
(Enter Sum of Total Quote shown on Proposal)
(Numerical)
If alternative quotes apply, the undersigned submits a proposal for each in accordance with the notice. Any
addendiums attached will be specifically referenced at the applicable page.
If additional units of material included in the contract are needed, the cost of units must be the same as that shown
in the original contract if accepted by the City of South Bend. If the quote is to be awarded on a unit basis, the
itemization of the units shall be shown on a separate attachment.,,
By
(Signature)
Ma-tthew D. Cain, President
(Printed Marne of Person Signing)
The above quote is accepted this
Subject to the following conditions:
titRD OF PUB.11-11C W R
ry rGi 11�o7tl, P re s i d e n t
Elizabeth A. Maradik, Member
James A.
Mueller, Member
ACCEPTANCE
al
SLIzanna M. Fritzberg, Member
31 Vre, e J. too a�Member
4=�
- Attdt: Linda IV.M artiN, Clerk�
Version 10/3112017 Page - 8 Public Works Quote
also"
MWIFNEM
115-115
Mav 3. 2018 before 10:30 a.m.
Item
No.
Description
Quantity
Unit
Unit Price
Total Amount
I
Mobilization & Demobilization
1
LSUM
3600.00
1
$ 5, SOO. 00
2
Dewatering and Flow Diversion
1
LSUM
ef, 00-D D
$ 34,306-00
3,
Construction of Cast -in -Place
Reinforced Concrete Wall at
Intake
1
LSUM
-3 6, COD, 00
$ DDO .0 C'
Base Bid Total
$ 91co 0c)
rArf'"TIMP.-VAI
Item
No.
Description
Quantity
Unit
Unit Price
Total Amount
1
Mobilization & Demobilization
1
1-stim
's ow, Do
$ 6,000-00
2
Dewatering and How Diversion
1
1 SUM
;B00-00
3; �q'$Co"00
3
Construction of Precast Concrete
Wall at Intake
1
LSUM
Coo .00
$ & 00, D00. CDO
Alternate ATotal
$ 101300, 00
FATTIMIMM"',
Item
No.
Description
Quantity
Unit
Unit Price
Total Amount
1
Reset Precast Planks
I
_
LSUM
1(1,300-00
$ t 1, 06. 0 0
Alternate B Total
$ j(' cc). CD
Note: Bidder shall provide Bids for the Base BA, Alternate A, and Alternate B provided.
Firm: HRP CONSTRUCTION INC.
Address: 5777 Cleveland Road,
City/State/Zip: South Bend, IN 46624
P.O. Box 266
Telephone Number:
Fax Number:
t 574 )271-0524
Bye��-ef t(s� zi—t"atw:�
Matthew 0. Cain. President
(Printed Marne of Person Siqn4ig)
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 05/01/2018 Department Public Works
❑ Agreement Amendment
U Contract H Proposal U Addendum
❑ Professional Services
❑ Resolution
Bid Opening
❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
Quote Opening
® Quote Award
❑ Change Order No.
❑ C/O & PCA No. ❑ PCA
❑ Ease/Encroach.
❑ Traffic Control:
❑ Other:
Company or Vendor Name
�}
❑ Yes 'No ❑ If Yes, Approved by
New Vendor
Purchasing
MBEIWBE Contractor
❑ MBE ❑ WBE
MBEIWBE Contractor Requested
❑ No ❑ Yes Name of Company
Project Name
West Race Emergency Repairs
Project Number
115-115
Funding Source
Hotel -Motel
Account No.
7304.42010.000.0099
Amount -
f 914 I b 6
Terms of Contract
Unit Prices
Purpose/Description
West Race of St. Joe River -- remove and replace stop logs and
reset planks downstream of West Race Gate. Damage to some
of the existing stop logs and planks due to February 2018 flooding
❑ Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
Amount of ❑ Increase $
❑ Decrease $