HomeMy WebLinkAbout2 Minutes 12-28-10 MeetingSOUTH BEND REDEVELOPMENT COMMISSION
SPECIAL MEETING
December 28, 2010
10:00 a.m.
Presiding: David A. Varner, Vice-President
1. ROLL CALL
Members Present:
Members Absent:
Legal Counsel:
227 West Jefferson Boulevard
South Bend, Indiana
Dr. David Varner, Vice President
Ms. Nancy King, Secretary
Mr. Greg Downes
Mr. Donald Alford
Ms. Marcia Jones, President
Ms. Stephanie Spivey
Mr. Lawrence Meteiver, Esq.
Redevelopment Staff: Mr. Don Inks, Director
Mrs. Jenny Hullinger, Recording Secretary
Mr. Bill Schalliol, Economic Development Specialist
Mr. David Relos, Economic Development Specialist
Ms. Debrah Jennings, Property Manager
Others Present: Ms. Rita Kopala
Ms. GlendaRae Hernandez
Ms. Mo Miller, Prism Science
Mr. Phillip Faccenda, Attorney
Mr. Richard Nussbaum, Attorney
Mr. Donald Schoenfeld
2. APPROVAL OF MINUTES
A. Approval of Minutes of the Regular Meeting of
Friday, December 17, 2010.
Upon a motion by Mr. Downes, seconded by Mr.
Alford and unanimously carried, the Commission
approved the Minutes of the Regular Meeting of
Friday, December 17, 2010.
3. APPROVAL OF CLAIMS
COMMISSION APPROVED THE MINUTES OF THE
REGULAR MEETING OF FRIDAY,
DECEMBER 17, 2010
There were no Claims for approval. No CLAIMS FoR APPROVAL
South Bend Redevelopment Commission
Regular Meeting -December 28, 2010
4. COMMUNICATIONS
There were no Communications.
5. OLD BUSINESS
There was no Old Business.
6. NEW BUSINESS
A. Public Hearing
(1) Public Hearing on Resolution No. 2833
amending the Development Plan for the
South Bend Central Development Area
and adding interests in one or more
parcels to the List of Parcels to be
Acquired.
Mr. Inks noted that Resolution No. 2833 adds
interest in two parcels to the List of Parcels
to be Acquired, those parcels being the two
parcels on which sit the parking garage that
is integral to the 1 s` Source/Marriott complex.
He noted that the Public Hearing file is
complete, containing a copy of Declaratory
Resolution No. 2812 amending the
Development Plan for the South Bend
Central Development Area, a copy of the
Area Plan Commission Resolution No. 213-
l0approving the Declaratory Resolution, a
copy of the Common Council Resolution
No. 4071-10 approving the Area Plan
Commission's resolution, a copy of the
Notice of Hearing, a copy of Resolution
No. 2833, and affidavits from the Tri-County
News and the South Bend Tribune that the
Notice of Hearing was published in those
newspapers on December 17, 2010. The
mail was checked prior to the meeting and
there were no written remonstrances received
related to Resolution No. 2833.
THERE WERE NO COMMUNICATIONS
THERE WAS NO OLD BUSINESS
2
South Bend Redevelopment Commission
Regular Meeting -December 28, 2010
6. NEW BUSINESS (CONT.)
A. Public Hearing
(1) continued...
Mr. Inks noted that acquisition of the 1 S`
Source/Marriott parking garage will retain l sc
Source and its corporate offices in the
downtown. They employ 595 people in
South Bend. It would also retain an upscale
hotel at the site. The hotel currently employs
100 people. There are also several tenants in
the building that would be positively
impacted by this project. We estimate that as
many as 300 additional jobs would be
retained in those tenant offices. The building
itself will receive $14M of new investment.
Mr. Varner opened the Public Hearing for
whoever wished to speak regarding
Resolution No. 2833. There was no one who
wished to speak. Mr. Varner closed the
Public Hearing for whatever action the
Commission wished to take.
(2) Consideration of Resolution No. 2833.
Upon a motion by Mr. Downes, seconded by
Ms. King and unanimously carried, the
Commission approved Resolution no. 2833
amending the Development Plan for the
South Bend Central Development Area and
adding interests in one or more parcels to the
List of Parcels to be Acquired.
B. South Bend Central Development Area
(1) Staff report on acquisition of property in
the South Bend Central Development
Area. (ls` Source/Host Parking Garage)
PUBLIC HEARING ON RESOLUTION NO.2833
COMMISSION APPROVED RESOLUTION NO. 2833
AMENDING THE DEVELOPMENT PLAN FOR THE
SOUTH BF;ND CENTRAL DEVELOPMENT AREA
AND ADDING INTERESTS IN ONE OR MORE
PARCELS '1'O THE LIST OF PARCELS TO BE
ACQUIRED
3
South Bend Redevelopment Commission
Regular Meeting -December 28, 2010
6. NEW BUSINESS (CONT.)
B. South Bend Central Development Area
(1) continued...
Mr. Nussbaum noted that on December 3, the
Commission heard a lengthy explanation
regarding the Memorandum of
Understanding (MOU) related to this project.
None of these documents in any way
modifies that agreement. The documents
supplement and help to implement that
agreement.
Mr. Nussbaum noted that the Garage
Purchase Agreement confirms the authority
of the parties to enter into the agreement. It
sets out what documents are to be exchanged
at closing. The closing is scheduled to take
place later this day. And it provides for an
allocation of costs at closing. The city is not
paying any closing costs. All $6.SM that the
city is putting into the project will be put into
various escrow accounts to be used for
improvements.
Mr. Nussbaum noted that the Third
Amendment to the Operation, Maintenance
and Easement Agreement (OME) seeks to
keep in place the current agreement with
regard to the operation of the parking garage.
Part of the MOU was that although the city
will own the garage, both ls` Source and Host
will be the entities that will operate it and
incur all the expenses with regard to the
operations.
Mr. Nussbaum noted that there are three
Escrow Agreements: an Atrium Escrow, a ls`
Source Improvement Escrow and a Host
Improvement Escrow. Those are the three
4
South Bend Redevelopment Commission
Regular Meeting -December 28, 2010
6. NEW BUSINESS (CONT.)
B. South Bend Central Development Area
(1) continued...
accounts that the city's $6.SM will be
deposited into. The MOU requires that the
private parties put their own money into the
improvements before any of the city money
is spent. The Board of Public Works will be
appointed as the city's agent to ensure that
those improvements are done in the manner
they are supposed to be.
Pursuant to the MOU there were conveyance
payments made by ls` Source and Host as a
result of the garage. Those conveyance
payments are being terminated. That
amounted to about $36,000 per year.
Mr. Nussbaum also noted that an additional
document indicates that Doubletree will be
an approved hotel for the Host site even
though for 2011 its ranking dropped from
Upper Upscale to Upscale. All parties agree
to this.
Upon a motion by Ms. King, seconded by
Mr. Downes and unanimously carried, the
Commission approved the Garage Purchase
Agreement, the Third Amendment to the
Operation, Maintenance and Easement
Agreement, the Atrium Escrow Agreement,
the 1 S` Source Improvement Escrow
Agreement, the Host Improvement Escrow
Agreement, the 1 S` Source Termination
Conveyance Agreement, the Host
Termination Conveyance Agreement, and the
Doubletree Side Letter Agreement.
COMMISSION APPROVED THE GARAGE
PURCHASE AGREEMENT, THE THIRD
AMENDMENT "r0 THE OPERATION,
MAINTENANCE AND EASEMENT AGREEMENT,
TIiF. ATRIUM ESCROW AGREEMENT, THE 1ST
SOURCE IMPROVEMENT ESCROW AGREEMENT
'fHE HOST IMPROVEMENT ESCROW AGREEMENT,
THE 1ST SOURCE TERMINATION CONVEYANCE
AGREEMENT, THE HOST TERMINATION
CONVEYANCE AGREEMENT, AND THE
DOUBLETREE SIDE LETTER AGREEMENT
South Bend Redevelopment Commission
Regular Meeting -December 28, 2010
6. NEW BUSINESS (CONT.)
B. South Bend Central Development Area
Mr. Inks asked that Item 6.B.(3) be moved up on
the agenda as it also relates to the 1 S` Source/
Marriott project. There was no objection and the
item was moved up to be considered at this time.
(3) Resolution No. 2834 authorizing the
Director of Economic Development to
approve and execute documents related to
I`` Source Parking Garage Project
Mr. Inks noted that there is a closing
scheduled for 12:00 p.m. today on this
project. In case there are additional
documents that need to be signed at closing,
Resolution No. 2834 authorizes Mr. Inks to
sign those documents.
Upon a motion by Mr. Downes, seconded by
Ms. King and unanimously carried, the
Commission approved Resolution No. 2834
authorizing the Director of Economic
Development to approve and execute
documents related to 1 S` Source Parking
Garage Project.
(2) Proposal for professional services in the
South Bend Central Development Area
(Fred's Transmission Demolition
Oversight and Environmental Review)
Mr. Schalliol noted that Wightman Petrie
was awarded a contract for a Phase I
environmental assessment, preparation ol~
demolition specifications and some
instruction services related to the Fred's
Transmission & Clutch site and the
Coveleski Housing Block. That contract was
for $27,220. Since then, there were many
COMMISSION APPROVED RESOLUTION NO.2834
AUTHORIZING THE DIRECTOR OF ECONOMIC
DEVELOPMENT TO APPROVE AND EXECUTE
DOCUMENTS RELATED TO 1ST SOURCE PARKING
GARAGE PROJECT
6
South Bend Redevelopment Commission
Regular Meeting -December 28, 2010
6. NEW BUSINESS (CONT.)
B. South Bend Central Development Area
(2) continued...
unforeseen circumstances, including
discovery of seven underground storage
tanks. Therefore, the scope of services has
been expanded to include curb and walk and
site grading and landscaping, additional
demolition oversight and environmental
testing and some demolition management.
The fee for the additional scope of services is
$17,000, making the total contract $44,220.
Staff requests approval of the fee for
additional services.
Upon a motion by Ms. King, seconded by
Mr. Downes and unanimously carried, the
Commission accepted the proposal from
Wightman Petrie for the additional scope of
services and fee proposed.
C. Airport Economic Development Area
(1) Proposal for professional services in the
Airport Economic Development Area
(Planning and Survey Word to Create
Minor Subdivision in the Oliver Plow
Industrial Park)
Mr. Relos noted that staff solicited a proposal
from Danch Harner and Associates to do the
necessary planning and survey work to create
a minor subdivision of proposed Lot 8 in the
Oliver Plow Industrial Park. An interested
party would like to relocate its business to
the eastern portion of Lot 8, the lot occupied
by the new Underground Pipe and Valve
building. Lot 8 was originally laid out as a
7.84 acre lot. The amount of land required
COMMISSION ACCEPTED THE PROPOSAL. FROM
WIGHTMAN PETRIE FOR THE ADDITIONAL SCOPE
OF SERVICES AND FEE PROPOSED
7
South Bend Redevelopment Commission
Regular Meeting -December 28, 2010
6. NEW BUSINESS (CONT.)
C. Airport Economic Development Area
(1) continued...
for this business is 4.64 acres. The proposal
from Danch Harner is in the amount of
$3,850 plus possible review fees of $325.
Staff requests approval of a fee of $4,175 to
subdivide the lot so that the new
development can occur.
Upon a motion by Ms. King, seconded by
Mr. Downes and unanimously carried, the
Commission accepted the proposal from
Danch Harner and Associates in the amount
of $4,175 for the scope of services proposed.
D. West Washington-Chapin Development Area
There was no business in the West Washington-
Chapin Development Area.
E. South Side Development Area
There was no business in the South Side
Development Area.
F. Northeast Neighborhood Development Area
There was no business in the Northeast
Neighborhood Development Area.
G. Douglas Road Economic Development Area
There was no business in the Douglas Road
Economic Development Area.
7. PROGRESS REPORTS
COMMISSION ACCEPTED THE PROPOSAI. FROM
DANCH HARNER AND ASSOCIATES IN THE
AMOUNT OF $4,175 FOR "THE SCOPE OF SERVICES
PROPOSED
There was no report. PROGRESS REPORTS
South Bend Redevelopment Commission
Regular Meeting -December 28, 2010
8. NEXT COMMISSION MEETING
The next meeting of the Redevelopment Commission is NEXT COMMISSION MEETING
its Annual Organizational Meeting schedule for
January 3, 2011 at 10:00 a.m.
9. ADJOURNMENT
There being no further business to come before the ADJOURNMENT
Redevelopment Commission, Ms. King made a motion
that the meeting be adjourned. Mr. Downes seconded
the motion and the meeting was adjourned at 10:18 a.m.
Donald E. Inks, Director
9