To: Redevelopment Commission
From: Bill Schalliol, Economic Development Planner
Subject: Oliver Industrial Park -Planning & Design Proposal
Date: April 19, 2010
Attached is a proposal from Danch, Harner & Associates to provide a variety of planning
and design services related to planned improvements within and adjacent to the Oliver
Industrial Park on Chapin Street.
The scope of work proposed within this proposal would allow for planning and design for the
Oliver Chilled Plow Memorial Sculpture Plaza, incorporation of a pedestrian pathway
system through the park connecting the Arnold Street bike network corridor to the
Chapin/United Drive bike network corridor, and would plan and design park entry signage
for the industrial park. With the near completion of the Underground Pipe & Valve complex,
the work at the Kroc Center site north of the park, and the planned Ignition Park
development, it is time to complete the Oliver Industrial Park.
The proposal for the project is projected to be $32,535.00 with cost for Bidding &
Negotiation (Task 4) and Construction Inspection (Task 5) to be expensed at a time &
materials amount. Staff would propose approval of Tasks 1-4 at this time with aNot-
To-Exceed amount of $40,000.00. Staff would bring Task 5 back before the Commission
as part of a project proposal for the final development of the scope of work.
Staff requests Commission approval of this proposal.
What We Do Today Makes A Difference!
~~ Danch, Hamer & Associates, Inc.
AMchael J. Danch, L.A
Ron Hamer, P.S.
April 5, 2010
Mr. Bill Schalliol
Community ~ Economic Development
12"' Floor County City Building
South Bend, Indiana 46601
Land Surveyors • Professional Engineers
Landscape Architects • Land Plsru~ers
Re: Proposal for Landscape Architecture, Planning, and Engineering services for:
a) Proposed trail route west to east through Oliver Industrial Park, crossing Prairie
Avenue and linking to Coveleski Stadium by means of United Boulevard.
b) Proposed Oliver Chilled Plow Memorial Sculpture Plaza
Dear Mr. Schalliol,
Danch Hamer 8~ Associates is pleased to submit this proposal for professional
Landscape Architecture, Planning, and Engineering services for your consideration. It
is our understanding that this project will include a pedestrian trail system within the
boundary and easements of Oliver Industrial Park, crossing Prairie Avenue and heading
east along United Boulevard, connecting to Coveleski Stadium. This trail will provide
access and connectivity to the surrounding neighborhoods and other commercial uses.
This project also includes the incorporation of a Memorial Sculpture Plaza that
commemorates the historical significance of the Oliver Chilled Plow.
Task 1: Toooarauhic Survev:
a) Topographic Survev: This work will include a detailed topographic survey of the
above-mentioned area to delineate existing conditions, features, infrastructure,
and grade elevations. This survey will be used as a base for the trail and
memorial plaza design & construction drawings.
Cost for this task would be $5,950
1843 Commerce Drive • South Bend, IN 48828 208 West Mars • Berrien Springs, MI 49103
OtTice: (574)234003 / (800)594-4003 • Fax: (57434-4119 Ofllce: (818}471-3010 • Fax: (816~g1-7237
- 2 - Apri17, 2010
Task 2: Protect Kick-0ff and Preliminary Desi~tn:
a) Proect Kids-off: This will include a meeting with City staff to gather input on
design requirements, trail routing, and project scheduling.
b) Preliminary Desi4n (Trail): This will include the submission of conceptual design
options to the City staff. The conceptual drawings will address various
components of the design including the proposed trail alignment 8 material usage,
trail connectivity to the surrounding community, wayFnding trail signage, amenity
types and styles (benches, litter containers, and bike racks) along with their
proposed locations, pedestrian lighting, landscape planting locations, and probable
construction cost estimates. The conceptual plans will be submitted to the City for
review and comment. We anticipate two to three additional meetings with the City
staff to finalize the conceptual design before moving to final design.
Cost for this task would be $5,450
c) Oliver Memorial Sculpture Plaza: A memorial sculpture plaza/park area located
adjacent to the Oliver Boiler House was proposed in 2004. This task starts with
the re-evaluation of those past efforts. From there, Danch Hamer, Inc., will design
and incorporate an updated memorial sculpture plaza that is integrated into the
proposed Oliver Industrial Park Trail. Danch Hamer, Inc. will meet with City staff
and other stake holders to define the plaza by confirming it's proposed location,
identifying design elements, materials, and financlal considerations. Conceptual
design options and cost estimates will be submitted along with the preliminary trail
concepts. The approved Memorial Plaza design will be incorporated with the trail
project for final design drawings and construction documents.
Cost for this task would be $6,900
Task 3: Construction Documents:
a) Construction Documents: After review and approval from City staff, Danch Hamer
will provide bid ready, final construction drawings that will include existing
conditions, layout plan, grading plans, utility coordination plans, landscape plans,
details, specifications, and final construction cost estimates.
Cost for this task would be $14,225
Task 4: Biddinc:
a) Bidding: Danch Hamer will provide bidding and negotiating services at a time and
material basis.
-3-
Task 5: Construction Inspection:
Apri17, 2010
a) Construction inspection: If required, construction inspection services will be
provided at a time and material basis and will consist of monitoring day to day
construction methods and practices to insure proper installation of the trail,
amenities, landscape, and any other project components. Weekly progress
reports will be sent to the City and Contractor for review and action. A final punch
list would be developed and issued to the City and Contractor before issuing
substantial completion.
Summary of Fees•
Task
1 Topographic Survey $5,950
2 Project Kick-off 8 Preliminary Design $12,350
3 Construction Documents $14,225
4 Bidding 8~ Negotiation Time 8~ Materials
5 Construction Inspection Time & Materials
Project Total: ;32,525
Revisions to the plans requested by the City would be completed at our standard hourly
rates (attached).
If you have any questions, please I free to call our office.
Items approved to proceed:
Approved By ~ Date:
Sincerely,
J~~ r. ~•~
Jeffrey T. Ballard, RLA, ASLA, LEED AP
Senior Landscape Architect
Danch Hamer 8 Associates, Inc.
Danch, Harner & Associates, Inc.
Effective Date: January 25, 2007
SCHEDULE OF HOURLY RATES AND DIRECT EXPENSES
CLASSIFICATION HOURLY BILLING RATE
Senior Professional Engineer $138.00
Engineerin Desi ner $80.00
Project Engineer $70.00
Senior Professional Land Surveyor $138.00
Senior Survey/En ineering Tech $80.00
Survey/Engineering Tech $55.00
Senior Professional Landscape Architect $138.00
Survey Mana er $70.00
Two Person Field Crew $120.00
Princi al $138.00
Clerical $45.00
ITEM UNITS UNIT PRICE
Milea a Miles $0.50
Copies* Each $0.25
Standard Size Prints (24 x 36) Each $4.00
Oversize Prints S uare Foot $1.00
Vellums (24 x 36 size) Each $10.00
Overni ht Travel:
Meals Cost
Lod in Cost
Public Trans ortation Cost
*Note: Copies include 81/2 x 11, 81/2 x 14, or 11 x 17 size sheets.
Other direct expenses may include cost to obtain copies of documents such as deeds or plats, maps, or
other items purchased as a direct result of employment on the project. NOTE THAT MILEAGE IS
NOT CHARGED FOR PROJECTS WITHIN ST. JOSEPH COUNTY, INDIANA OR BERRIEN
COUNTY, MICHIGAN.