February 27, 2018
Nick Gurbick
Gibson -Lewis, LLC
100 1 W I I"' Street
Mishawaka, IN 46544
NOW,, 574/235-9251
FAX 574/ 235-9171
RE: Change Order No. 2 — 2016 Downtown Parking Garage Improvements — Project No.
115-143
Dear Mr. Gurbick:
The Board of Public Works, at its meeting held on February 27, 2018, approved the above
referenced Change Order for an increase of $44,571, bringing the current contract amount to
$1,204,587.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerl/
Enclosure
c: Toy Villa, Engineering
GARY A. GILOT SUZANNAM.FRITZERG ELIZABETHA.MARADIK JAMES A, MUELLER THERESE J . DORA LJ
N a
OWU
192ZLeak M11 MI I ,
101:4 MINIMUM
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO:
SUBJECT OF CHANGE ORDER:
12/12/2017
115-143
2016 Downtown Parking Garage Improvements
11122/2016
2
PCR #3-Wayne Fire Alarms PCR #4-Leighton Fire Alarms
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completio, date/time
CO ACTOR
C6ntradtor Sfgnatur
VJ662iksaZu-r
Printed Name and Title
,Gibson -Lewis LLC
Company Name
1001 West 1 Ith Street
Address
Mishawaka, IN 46544
City, State, Zip
$
1,145,000.00
$
15,016.00
$
1,160,016.00
[—X1 Increased
F] Decreased $
44,571,00
$
1,204,587.00
3.84 %
5.20 %
11/7/2017
108 days
0 days
2123/2018
RECOMMENDED FOR APPROVAL
CONSTTION MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC 0AR kis
pproved Date:
Gary A., Gilot, Presidept
11, �A �* - 4 �01 - M
Elizabeth A. Maradik, Member
Therese J. Dorau, Member
James A. Mueller, Member
Ar
alb
DESIGN I BUILD CONTRACTORS
SOUTH SEND - ELK14ART
November 2, 2017
Gibson -Lewis, LLC
1001 West 11' Street
Mishawaka, Indiana 46544
Attn: Mr. Nick Guirbick
Re: Leighton Parking Garage
Fire Alarm System
Dear Nick,
During our work on the 2016 Parking Garage Improvements Project we became aware that the
existing fire alarm system had problems and that the elevator recall was totally non-functional.
our recommendation to remedy this problem is to replace the existing fire alarm system with a
Notifier NFS-320 addressable fire alarm system. It is our intent to utilize the existing cabling to
save cost, if it becomes apparent that the existing cable is defective it will have to be replaced
as well. The cost of cable replacement is not included in this proposal but can be provided if it
needs replaced also. Please review the following Proposal below, based upon our inspection of
the current Fire Alarm System and the following scope of work submitted for your approval.
City of South Fend Leighton Parking Garage Fire Alarm System
Replacement
• Furnish and install fire alarm panel
• Furnish and install all fire alarm devices to replace the existing
• Furnish and install Relay Modules to provide elevator recall for the new elevators
• Program and test system
• Provide documentation to the monitoring company and test functionality with them.
• Provide Record of Completion and Frame & Post as required by NFPA 72
• Train customer representative on the operation of the system
• Provide a one-year parts and labor warranty
• Provide all required engineering drawings and submittals
P.O. Box 1190 Office: 5,74-272-2615 Fax: 574-272-2616
Granger, IN 46530-1190 Email: sgill@briteelectric.net
• Provide as -built drawings and maintenance manuals
MATERIALS PROVIDED:
• Required raceway and back boxes for elevator recall
• 100' —18/2 FPLP cable
• 1—Notifier CPU-320 Fire Alarm Panel
+ 1— Notifier UDACT2 Digital Communicator
• 18 — Notifier NBG-12LX Pull Station
• 24 — Notifier FSP-851 Smoke Detector
• 24 — Notifier B210LP Low Profile Detector Base
• 6 — Notifier FRM-1 Relay Modules
• 3 — Notifier FMM-1 Monitor Modules
• 2 —12V 7AH Batteries
• 16 —System Sensor P2RK Weatherproof Wall Horn/Strobes
• 2 -- System Sensor P2R Wall Horn/Strobes
Total Amount for the Fire Alarm System Replacement: $14,960.00
(Fourteen Thousand Nine Hundred Sixty and no/100 Dollars)
Clarifications:
• All work to be performed on straight time during normal working hours
• Equipment and scope of work required to meet expectations and life safety code
interpretations of the Local Authority Having Jurisdiction not contained in the
aforementioned quotation will be provided in addition to the quoted price via change
order.
• Fire Alarm System is to function primarily as a life safety system, with minimal
protection of facility and contents.
• Cost of ACAD drawings not included
• State plan review and site examination fees excluded
• Proposed amount includes freight and excludes sales tax
Thank you for the opportunity to submit this pricing. If you should have any questions feel free
to contact me at your earliest convenience.
Best Regards,
4&, �X-
Steve Gill
Senior Project Manager
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 02/15/2018
Department Public Works
Name Toy Villa
Division/Bureau Engineering
BPW Date 02/27/2018
Phone Extension 5920
Required Prior to Submittal to Board
Legal ❑
Attorney Name:
Controller ❑,
Controller review is requiredfor all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ❑
Check the Appropriate Item Type —,Required for All Submissions
❑ Agreement
❑ Contract El Proposal ❑ Addendum
I❑ Professional Services
❑ Resolution
E] Bid Opening
❑ Bid' Award ❑ Req. to Advertise ❑ Title Sheet
Quote Opening
❑ Quote Award
Change Order No. 2
❑ C/O & PCA No. PGA
Ease/Encroach.
❑ Traffic Control;
El Other:
Required Information
Company or Vendor Name
Gibson -Lewis, LLC
El Yes ® No If Yes, Approved by
New Vendor
Purchasing
MBE/WWBE Contractor
❑ MBE ❑ WWBE
MBE/WWBE Contractor Requested
❑ No ❑ Yes Name of Company
Project Name
2016 Parking Garage Improvements
Project Number
115-143
Funding Source
Major Moves
Account No.
412-0401-415-36.01
Amount
$
Terms of Contract
Purpose/Description
Fire Alarms at Wayne and Leighton Parking Garages
❑ Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
Required For Change Orders Only,
Amount of Increase $ 44,571.00
El Decrease $
Previous Amount
$ 1,160,016,00
Current Percent of Change:
3.84%
New Amount
$ 1,204,587.00
Total Percent of Change:
5.20%
Dispersal After Approval