HomeMy WebLinkAboutChange Order - INDOT - Safe Routes to School Lincoln Primary Center Proj No 114-07813116 COUNTY -CITY BOILDING
227 W, JEFFERSON BonEVARD
Sou'ri I BEND, INDIANA 46601-1830
CITY OF Sourti BEND PETE BUTTICAEG, MAYOR
BOARD OF PUBLIC WORKS
January 9, 2018
Kyle Silveus
TheTroyer Group
550 Union Street
Mishawaka, IN 46544
PHOW, 574/235-9251
FAX 574/ 235-9171
RE: Change Order No. 2 — Safe Routes to School — Lincoln Primary Center — Project No.
114-078
Dear Mr. Silveus:
The Board of Public Works, at its meeting held on January 9, 2018, approved the above
referenced Change Order with INDOT for an additional two -hundred, thirty-eight (238) days
to complete the project. The new project completion date is April 27, 2018.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this, office at (574) 235-
9251.
Sincerely,
fi
Linda M. Martin, Clerk
Enclosure
c: Roger Nawrot, Engineering
GARY A. Git,o'r S13ZANNA M. FRITZBERG EuZABETI, I A. MARADIK JAMEs A. MUELLER 11 HiRESE J . DORAU
Contract No:R -38062 Change Order No.: 002
INDIANA Department of Transportation Page: 1
Construction Change Order and Time Extension Summary
Contract Information Contract No.: R -38062 Letting Date:11/16/2016
District:LAPORTE DISTRICT AE:Forgey, Ryan PE/S:Silveus, Kyle Status:Pending
Change Order Information Change Order No.: 002 EWA: N or Force Acct: N
Date Generated: 00/00/0000 Date Approved: 00/00/0000
Reason Code: CHANGED COND, Constructability Related
Description: Time Extension due to Spring Tree Inspection Requirements
Original Contract Amount $ 684,000.00
Current Change Order Amount $ 0.00 Percent: 0.000 %
Total Previous Approved Changes $-34,646.00 Percent: -5.065 %
Total Change To -Date $-34,646.00 Percent: -5.065 %
Modified Contract Amount $ 649,354.00
Time Extension Information
Date Initiated 00/00/0000 Date Completed 00/00/0000
Original Contract Time SS Completion Date 09/01/2017 or SS CalendarNVork Days 0
SP Date 00/00/0000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Time Element Description: Contract Completion date needed to be extended in order to include a spring inspection
of installed trees and replace trees if neccessary.
Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00
Previous Time Approved
Revised Contract Time
SS Days by AE: DCE: SCE: DDCM:
SS Days,
SP Days Value $
SS Completion Date 00/00/0000 or SS CalendarAAfork Days 0
SS Date 00/00/0000 or SP Days 0
Contract No:R -38062
INDIANA Department of Transportation
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority
($ per Change Order)
(Days per Contract)
Verbal Approval Required?
Total Change To-Date>5%?
Scope/Design Recommendation
Required?
Change Order No.: 002
Page: 2
AE: DCE: SCE: DDCM:
(-LE$250K-)(-LE$750K-)(--LE$2M--)(--GT$2M--)
( 50 SS days) ( 100 SS days ) (200 SS Days) ( GT 200 SS days)
Y 1 N If Y, by Date Issued
Y 1 N If Y , Copy to Program Budget Manager
Y 1 N If Y, Referred to Project Manager(PM)
Date to PM Date Returned
Approval Authority Concurs with PM? . Y 1 N If Y, Concurrence by Date
If N,Resolution: Approved Disapproved
Resolved by Date
LPA Signatures Required? Y 1 N If Y, Date to LPA Date Returned
FHWA Signatures Required? Y 1 N If Y, Date to FHWA
* Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer Date
Comments:
Date Returned
Contract NOR -38062 INDIANA Date:12/21/2017
Change Order No:002
Contract:
Project:
Change Order Nbr:
Department of Transportation
R -38062
State: 1 4018080OL04
002
Change Order Description: Time Extension due to Spring Tree Inspection Requirements
Reason Code: CHANGED COND, Constructability Related
Page: 3
CLN PCIJ PLN Item Code Unit Unit Price CO Qty Comment Amount Change
Total Value for Change Order 002 = $ 0.00
Contract Completion Date Time Adjustment
Original Completion dt: 09/01/2017 Adj comp) dt 04/27/2018 Adj No. of Days 238
Explanation: Contract Completion date needed to be extended in order to include a spring inspection of installed trees and replace trees if
neccessary.
Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change Is recommended.
General or Standard Change Order Explanation
The contract completion date will need to adjusted to adhere to INDOT spec 622.06 - The planting season shall be from September 1 through the
following May 25, with the exception that trees shall be planted from October 1 through the following April 15, provided the trees are dormant.
Moving the completion date to April 27 2018 will allow for a spring inspection of the trees to be planted this fall. No additional compensation will
be made with this change order.
Change Order Explanation for Specific Line Item
#}**#}##*####}##t#ii##ii###iiiii#**ii###*iiiiii#*iiiii*iiiiii**ii*i*i}iiitii}itiiii}}kk
It is the intent of the parties that this change order is full and complete compensation for the work describe above.
Notification and consent to this change order is hereby acknowledged,
Contractor:
Signed By:
NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system.
Contract NO:R -38062 INDIANA pate:12/21/2017
Change Carder No 002 Department of Transportation Page 4
###N###NkNk#kR###N#kNN#kNN�,���wN##N].:NN�QMi#kkkN#kkkNNkil9���###NNk�#�I#k#k Nk#k N#NNNNNFNkPNNkY#NNkkN
RR**11II T _ 0 APPROVED FOR LOCAL PUBLIC AGENCY
(SIGNATURE)
(SIGNATURE)
JBMI ED...r
FOR CONSIDERATION
k####N#-kk#NNkdN.#kJ#kNN###NW(YNNNNN'kkkkik#Nk:4AMNkkk#kk#ANY#k#k#k4##fk##Yk#kkNNk####k##k.NNN#NNNNkkkk Rk.N#kk#LIMO#Nk#kNNNNkNNNNN
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION
Approval Level
6arne of Approver
Date
Status
Project Engineer/Supervisor
Oaki'ey, Marc
12/21/2017
Approved
Area Engineer
Forgey, Ryan
12/21/2017
Approved
District. Construction, Director
Kruger, Jonathon
00/00/0000
Action Pending
State Construction '.Engineer
Pankow, Greg
00/00/0000
Action, Pending
Director, Div of Construction
Leckie, John
00/00/0000
Action Pending
Management
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 12/22/17
Name Roger Nawrot
Department
Division/Bureau
Public Works
Engineering
BPW Date 1/9/18 Phone Extension 5932
U Agreement
Lj Contract Lj Proposal U Addendum
❑ Professional Services
❑ Resolution
❑ Bid Opening
❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening
❑ Quote Award
® Change Order No.
❑ CIO & PCA No. ❑ PCA
❑ Ease/Encroach.
❑ Traffic Control:
R Other:
Company or Vendor Name
Indiana Department of Transportation
❑ Yes ❑ No ❑ If Yes, Approved by
New Vendor
Purchasing
MBEANBE Contractor
❑ MBE ❑ WBE
MBEIWBE Contractor Requested
❑ No ❑ Yes Name of Company
Project Name
Lincoln SRTS Contract R-38062
Project Number
114-078
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Time extension to April 27, 2018 due to include spring inspection
of trees that were installed after the fall planting date. Trees will
be replaced if necessary.
n Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
Amount of H Increase
❑ Decrease
Copy Original
® ❑ Roger Nawrot
❑ ® Kyle Silveus, Troyer Group
❑ ❑