Loading...
HomeMy WebLinkAboutChange Order No 1 - Newman Center Site Development Divisions B & C Proj No 117-060R - HRP Construction Inc1316 COUNTY -Ow BuiLDINU 227 W. JETFERSON BouLLWARD Sou'rii BEND. INDIANA 4060'1-1830 E 10 ".1 FE oft I W.,C] December 12,2017 Matthew Cain HRP Construction, Inc. 5777 Cleveland Road, PO Box 266 South Bend, IN 46624 1'1-10Nt,' 574/235-925t FAX 574/ 235-9171 RE: Change Order No. I - Newman Center Site Development, Divisions B and C — Project No. 117-06OR Dear Mr. Cain: The Board of Public Works, at its meeting held on December 12, 2017, approved the above referenced Change Order for an increase of $22,403.42, bringing the current contract amount to $206,756.54. Enclosed is a copy of the Change Order for your records. If you have any further questions regarding this matter, please call this office at (574) 235- 9251. Sincerely, Linda M. Martin, Clerk Enclosure c: Toy Villa, Engineering Y GARY A. GILOT SUZANNAM.FRITZBERo EL1ZABFn-iA.MARADIK JAW's A, MuLi,fx�R THRESE J. DORAU we] IV&*] F-Alki I I a] 21 WEI 0.4 9 ITI ye. DATE: PROJECT NO: PROJECT' NAME: CONTRACT'DATE: CHANGE ORDER NO: SUBJECT OF CHANGE ORDER: 12/12/2017 117-06OR Newman Center Site Development, Division B and C 8/21/2017 PCR #I -HMA Surface 1PCR #2-Drvw0 The original contract sum Net change by previously authorized change orders The contract sum prior to this change order By this Change Order, the project amount is The new contract sum including this change order This Change Order represents a total change of Total change for entire project Original contracted completion date/time Extension of date/time by previous change orders Date/time extension by this change order New completion date/time CON TRA4j]E9R Contractor Sign Matthew D. Cain, President Printed Name and Title FIRP Construction Inc. Company Name 5777 Cleveland Road, P.O. Box 266 Address South Bend, IN. 46624 City, State, Zip $ 184,353,12 $ 0.00 $ 184,353,12 Increased! Decreased $ 22,403.42 $ 206,756.54 12.15 % 12.15 % 11/14/2017 0 days 0 days 11/14/201I7 RECOMMENDED FOR APPROVAL CONSTRUC,JION MANAGER CITY OF SOUTH SEND BOARD OF PUBLIC WORKS Approved D91b- Gary A. Tilot, President ritzb Suzan I' FMember Elizabeth A. IMaradilc, Member Therese J. Dorau, Meniber James A. Mueller, Member City of South Bend Project No. 117-06OR Change Order No. 1-12112/17 OWNER: City of South Bend ENGINEER: City of South Bend Engineering Kara M. Boyles, P.E. Professional Engineer No. 10809510 CONTRACTOR: HRP Construction PROJECT: Newman Center Site Development, Division B & C Project No. 117-06OR SUBJECT: Change Order Explanation ISSUE DATE: December 12, 2017 This Change Order to the Contract document shall supplement, amend, and shall become a part of, and be incorporated as an Addendum to the Contract. The following is a summary and description of the revisions to the Contract by this Change Order: Item QtV Unit Price Total 1. HMA Surface 120.73 TON $106.05 $12,803.42 2. Drywell 1 LS $9,600.00 $9,600.00 Total: $22,403.42 1. HMA Surface Eddy St. needs to be milled and resurfaced to allow for proper drainage to newly proposed and existing structures. 2. Drywell A drywell is needed to be installed on Eddy St. in order to capture storm water on the west side of the crown. HMA will be graded to reach the grate without any curb or sidewalk removal. BOARD OF PUBLIC WORI(S, AGEND�A ITEM REVIEW REQUEST FORM Date 11/30/2017 Department Public Works Name Toy Villa Division/Bureau Engineering BPW Date 12/12/20117 Phone Extension . .. ....... 5920 Legal M Attorney Name: Michael Schmidt Controller 0 Controller review is required for all Contracts $5,000.00 or more and greater than one year in length per the City Purchasing Policy Purchasing Z George King Check the Appropriate item Type — Required for All Submissions Q Agreement F Contract F-1 Proposal E] Addendum F Professional Services F Resolution F-1 Bid Opening F-1 Bid Award ❑ Req. to Advertise ❑ Title Sheet [:] Quote Opening [:] Quote Award Z Change Order No. 1 F-1 C/O & PCA No. E] PCA F-1 Ease/Encroach. F-1 Traffic Control: F-1 Other: Company or Vendor Name, New Vendor MBEIWBE Contractor MBEANBE Contractor Requested Project Name Project Number Funding Source Account No. Amount Terms of Contract Purpose/Description Amount of 0 El HRP Construction Inc. (Divisions B & C) El Yes Z No [J If Yes, Approved by Purchasing ❑ MBE [:1 WBE ❑ No 0 Yes Name of Company Newman Center Site Development 117-06OR REDA TIF 429,.1050.460.42.03 (Division B & C) Approval of C.O. #1 n Required Contractor's Certification Forms Attached (Non - Collusion. Non -Discrimination, Non -Debarment, E-Verifv. Iran. etc, Increase $22,403.42 Decrease $ Previous Amount Current Percent of Change: New Amount Total Percent of Change: $ 184,353.12 12.15% $ 206,756.54 12.15% Copy Original 0 F] Brad Embe,rton - Developer ❑ F] ❑ El