HomeMy WebLinkAboutChange Order No. 2 - Calvert Street Lift Station Replacement - HRP Construction Inc9� �
Date
Name
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
ust 11. 2017
Jacob M. Klosinski
Department Utilities Wastewater
Purchasing ® Carol Kurzhal
Check the. 'Approp riate Item Type ReouiredforAll Submissions
L J Agreement LJ Contract L] Proposal LJ Addendum
❑ Professional Services ❑ Resolution
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award
® Change Order No. 2 ❑ CIO & PCA No. ❑ PCA
❑ Ease/Encroach. ❑ Traffic Control
�I Other:
Company or Vendor Name HRP Construction, Inc.
New Vendor ❑ Yes ® No ❑ If Yes, Approved by Purchasing
MBEIWBE Contractor ❑ MBE ❑ WBE
MBE/WBE Contractor Requested ❑ No ❑ Yes Name of Company
Project Name Calvert Street Lift Station Replacement
Project Number
Funding Source
Account No.
Amount
Terms of Contract
116-053
Wastewater Capital Account
642-0630-415-43-66
Lump Sum and Unit Prices
Purpose/Description The Division of Utilities recommends the Board of Public Works
approval of Change Order No. 2 which includes changes to the
scope of work adjusted guantities, and 30-dayextension to Final
Completion (see Inter -Office Memorandum for Details).
❑ Required Contractor's Certification Form Attached (Non -
Collusion. Non -Discrimination, Non -Debarment, E-Verifv. Iran, etc.)
Amount of ❑ increase $
® Decrease $ 7,197.60, +30 Days to Final Completion (Utility Conflict)
Previous Amount $ 927,805.80
Current Percent of Change:--0.78%; Previous +1.18%%
New Amount $ 920,608.20
Total Percent of Change: +0.40%
Dispersal After Approval
Copy Original
® ❑ Al Greek, Director of Utilities
® ❑ Jacob M. Klosinski, Assistant City Engineer
® ❑ Carol Kurzhal, Director of Financial Services, Environmental Services
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF UTILITIES
TO: Members of the Board of Public Works
Eric Horvath, Director of Public Works
Michael Schmidt, Board of Public Works Attorney
FROM: Al Greek, Director of Utilities
Jacob M. Klosinski, Assistant City Engineer
SUBJECT: Agenda Request Form — Change Order No. 2
Project No. 116-053: Calvert Street Lift Station Replacement
DATE: August 11, 2017
The Division of Utilities is requesting the Board of Public Works approval of Change Order No. 2
for Project No. 116-053 Calvert Street Lift Station Replacement. Refer to attached documents
for supporting details.
Change Order No. 2 addresses the following changes:
Item 22: Lift Station
Lift Station, decrease in cost due to change in wall sleeve arrangement ($ 2,305.60)
Item 5: Temporary Erosion and Sediment Control
Erosion Control, decrease in cost due to silt fence quantity reduction ($ 998.00)
Item 16: Doghouse Manhole
Manhole Structure No. 4, decrease in cost due to reduction of fittings ($ 3,454.00)
Item 16: Doghouse Manhole
Doghouse Manhole, Testing Credit ($ 308.00)
Item 22: Lift Station
Concrete, Testing Credit ($ 132.00)
NET DECREASE FOR CHANGE ORDER NO. 2 ITEMS ($ 7,197.60)
Original Contract Sum $ 917,000.00
Net change by previously authorized change orders $ 10,805.80
The contract sum prior to this change order $ 927,805.80
By this change order, the project amount decreases by ($ 7,197.60)
The new contract sum including this change order is $ 920,608.20
This Change Order represents a total change of -0.78%
Total change for the entire project +0.40%
Time Extensions resulting from Change Order No. 2:
Substantial Completion. + 0 days
Final Completion: +30 days
The time extension addresses an adjustment to Final Completion to compensate for
American Electric Power's delay in completing the permanent power connection to the Lift
Station. AEP's delay impacted the demolition schedule of the decommissioned lift station.
The funding sources for the construction of this project is Utilities, Wastewater Capital Account
(642-0630-415-43-66). If there are questions regarding the subject change order, please
contact Al Greek (Ext. 4210) or Jacob M. Klosinski (Ext. 9496) at the Division of Utilities.
Z.11
Excavar1REQUE `r lTO: City of South Bend
Attn: Jacob Klosinski
3113 Riverside Drive
South Bend, IN 46628PROJECT: Calvert Street Lift Station
HRP project: 1483
RE: Wall Sleeve CreditDescription of Request: Credit for materiacd;
using double link eBasis of Proposal: Lead time to man f (
I�P
STR�UCTIONi
•SEW,ERS•WATER4
19 a of c�EtiUieE
FOR CHANGE ORDI
ENGINEER:
difference between
in then lift station.
ire wail sleeves.
DATE: July 25, 2017
RFCO #: 3 Rev. 1
South Bend
pI ind wall sleeves and coring a hole and
CITY
U.O.M.
Desction
CbsC
Each l Extended Cost;
4
EA
8" x 1' Fig X PE
$
E224,00 I $ 896.00
2
EA
8" MJ Plug wl
Accessories
$
1315.00 $ 630.00
3
EA
8" x 1' MJ X MJ Wall
Sleeve wl Megalugs
$
1846.00
$ 2,538.00
4
EA
8" SS Flange Pack
$ I
. ' 33.00 $ 132.00
I $ 4,196.00
Add:
9—Ty
U.O.M.
Description
:C
stlEach
; Extended Cost
3
FA
8" x 3' Flg X PE
$
: 1373A0
$ 1,119.00 E
.3
EA
8" Zip Flange
$
60.00
$ 180.00
2
EA
8" Blind Flange
$ I
j351.00
$ 702.00
3
EA
8" SS Flange Pack
i $
j 33.00
$ 99.00 "
$ 2,100.00 .
Net Credit wl HRP mark-up
E $ 2,305.60
Shipping: 5777 Cleveland
Mailing: P.O. Box 266
Joe Sagga s
HRP Const uc ion Inc.
Date I
Bend, IN 466 8- 418 Phone 574-271-7800
Bend, IN 466; - 266 FAX 574-271-0524
HRP
CONSTRUCTION1
r
EXCAVATING•SEWERS•WATERMAINS
"CW0%k&29 90 BE Of e gwicz If
REQUEST FOR CHANGE ORDER
r
DATE: July 25, 2017
+ RPCO #: 4 Rev. 1
TO: City of -South Bend
Attn: Jacob Klosinski
3113 Riverside Drive
South Bend, IN 46628 '
PROJECT: Calvert Street Lift Station OWNER:' City of South Bend
HRP Project: 1483
RE: Silt Fence Credit ENGINEER: DLZ
Description of Request'. - Credit for not installing slit fence on the south and east sides of the site as Indicated on
the erosion control plan sheet.
Basis of Proposal: Silt fence was not needed. Owner asked for credit.
Length not installed = 3B0' Cost for Installation & removal per foot = $2.50
Credit with HRP mark-up = $998.00
Joe Saggars
HRP Construction Inc.
-7-as—/-7
Date
Shipping: 5777 Cleveland Road South Bend, IN 46628-9418 Phone 574-271-7800
Mailing: P.O. Box 266 South Bend, IN 46624-0266 FAX 574-271-0524
ExCAVA rr1
E '
..
o,
REQUE!
IRP
3T FOR CHANGE ORD
1
Il
f
i
TO: City of South Bend 1
Attn: Jacob Klosinski
3113 Riverside Drive
South Bend, IN 466281
PROJECT: Calvert Street Lift Statlon: OWNER:
t
HRP Project: 1483 i
ROE: Structure 4 piping j ENGINEER*
Description of Request: Credit for notlir'stalling a portion of the piping
Basis of Proposal: Piping would Ibe; Into the existing flow chanty
credit. I
Ns
DATE: August 2, 2017
RFCO #: 5 Rev. 2
City of South Bend
DLZ
1 inside structure 4.
.I. Owner modified plumbing and asked for
Deduct:
1
I
QTY
U.O.M.
Description I
Cost Each
Extended Cost
1
EA
8" x 2' Fig X PE
; $ 330.00
$ 330.Q0
1
EA
8" Flanged 90 1 $ 618,00
$ 618.E30
1
EA
8" Mind Flange i 351.00
$ 351,00
1
EA
8" Flanged Tee $ 1,067.00
$ 1,067.
i
0
4
EA
8" Flange Pack I $ 33.00
$ 132.i
0
2
EA
8" Pipe Anchor ; $ 195'00
!E
$ 390:Q0
II
2
HR
2-Man Sewer Crew:
w/ Equipment
$ 126.00
$ 252.10
I
i
I
$ 3,140.gO
* 401 lined
pipe & fittings
Net Credit wl HRP mark-up i
$ . 3,454.10
Joe(�Iggars "-
HRP Qdnstruction Inc.
21-4-1_?
Date
Shipping:
Mailing:
5777 Cleveland Road ' South Bend, IN
P.O. Box 266 South Bend, IN
3
$ Phone 574-271-7800
6 FAX 574-271-0524
HRP
GUNSTRUCTION1
EXCAVATING-SEWERS•WATERMAINS
"('W'Juz9 9, B, Cry -&-Ivtae ",
REQUEST FOR CHANGE ORDER
DATE: July 25, 2017
{ R1FCO #: 6
TO: City of South Bend
Attn: Jacob Klosinski
3113 Riverside Drive
South Bend, IN 46628 '
PROJECT: Calvert Street Lift Station OWNER. City of South Bend
HRP Project: 1483
RE: Structure #1 & ##4 vacuum test ENGINEER: DLZ
Description of Request: Structures ##1 & #4 are doghouse manholes. Doghouse manholes are not vacuum
tested.
Basis of Proposal: Owner asked for credit.
Description _,ty Unit Unit Price Extension
2-man sewer crew with equipment 2 HR $126.00 $252.00
Testing Equipment 2 HR $28.00 $56.00
Total for Change Order $308.00
Jd%Sagga►s °0
HRP Construction Inc.
%—-7
Date
Shipping: 5777 Cleveland Road South Bend, IN 46628-9418
Mailing: P.O. Box 266 South Bend, IN 46624-0266
Phone 574-271•-7800
FAX 574-271-0524
HRP
z
CUNSTRUCTIUN1
EXCA VA TING-SEWERS-WA r7 fI TERMAI NS
npJ EZo
REQUEST FOR CHANGE ORDER
DATE: July 25, 2017
TO: City of South Bend-
RFCO M 7
Attn: Jacob Klosinski
3113 Riverside Drive
South Bend, IN 46628 '
PROJECT: Calvert Street Lift Station OWNER:
City of South Bend
HRP Project: 1483
RE: Concrete testing ENGINEER:
DLZ
Description of Request: Concrete testing company failed to make field
cylinders on two occasions.
Basis'of Proposal: Owner asked for credit.
Description f3ty unit
Unit Price Extension
Field Cylinder wl Pioneer mark-up 8 EA
$15.75 $126.00
Total Change Order w/ HRP mark-up
$132.00
J16e Saggars
HRP Construction Inc.
7
Date
Shipping: 5777 Cleveland Road South Bend, IN 46628-9418
Mailing: P.O. Box 266 South Bend, IN 46624-0266
Phone 574-271-7800
FAX 574-271-0524