BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
June 6. 2017
Jacob M. Klosinski
Department Utilities Wastewater
BPW Date .tune 13, 2017 Phone Extension 574 235-9496
Required Prior to Submittal to Board
Legal ® Attorney Name Michael Schmidt
Controller ® Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing
® Carol Kurzhal
U Agreement
U Contract U Proposal Addendum
❑ Professional Services
❑ Resolution
❑ Bid Opening
❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening
❑
Quote Award
® Change Order No. 10
❑
CIO & PCA No. ❑ PCA
❑
Ease/Encroach.
❑ Traffic Control
F]
Other:
Ke uirea inrormation
Company or Vendor Name
Thieneman Construction Inc.
New Vendor
❑ Yes ® No ❑ If Yes, Approved by Purchasing
MBE/WBE Contractor
❑ MBE ❑ WBE
MBEIWBE Contractor
Requested ❑ No ❑ Yes Name of Company
Project Name
Wastewater Treatment Plant Secondary Treatment Improvements
Project Number
114-053
2012 Sewer Bond, Capital Improvement Wastewater Treatment
Funding Source
Plant (subject to 3rd Quarter Appropriation)
Account No.
661-0630-415-42-06
Amount
$
Terms of Contract
Lump Sum and Unit Prices
Purpose/Description
The Division of Utilities recommends the approval of Change Order
No. 10 which includes dewateri_ng _delay costs_, 79 days additional
time, omission of any liguidated damages for Shutdown C.
❑ Required Contractor's Certification Form Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.
R'equir d For Change Orders O'nl
Amount of
Increase $ 422,000; 79 Days to Subst. & Final Completion
Decrease $
Previous Amount
$ 13,046,684.87
Current Percent of Change: 3.56%
New Amount
$ 13,468,684.87
Total Percent of Change: +13.33%
Dispersal After Approval
Copy Original
® ❑
Al Greek, Director of Utilities
® ❑
Jacob M. Klosinski, Assistant City Engineer
® ❑
Carol Kurzhal, Director of Financial Services, Environmental Services
INTEROFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF UTILITIES
TO: Members of the Board of Public Works
Eric Horvath, Director of Public Works
Michael Schmidt, Board of Public Works Attorney
FROM: Al Greek, Director of Utilities
Jacob M. Klosinski, Assistant City Engineer
SUBJECT: Agenda Request Form — Change Order No. 10
Project No. 114-053: Wastewater Treatment Plant Secondary Treatment
Improvements
DATE: June 6, 2017
The Division of Utilities is requesting the Board of Public Works approval of Change Order No.
10 for Project No. 114-053 Wastewater Treatment Plant Secondary Treatment Improvements.
Refer to attached documents for supporting details for claims.
Change Order No, 10 addresses the following changes:
Keep Dewatering Well #7 in Service $ 13,225.50
Temporary Pumping at RAS Pump Station $ 6,977.00
Overtime Premium from August 2016 thru December 2016 $ 49,959.00
Management Costs $169,412.20
Construction Equipment Costs and Idle Time $146,596.25
Winter Conditions $ 12,723.24
Lost Productivity — Winter Work $ 19,000.00
Premiums for Electrical Work $ 4,106.81
NET INCREASE FOR CHANGE ORDER NO. 10 ITEMS $422,000.00
Original Contract Sum $11,885,000.00
Net change by previously authorized change orders $ 1,161,684.87
The contract sum prior to this change order $13,046,684.87
By this change order, the project amount increases by $ 422,000.00
The new contract sum including this change order is $13,468,684.87
This Change Order represents a total change of +3.56%
Total change for the entire project +13.33%
Time Extensions resulting from Change Order No. 10:
Substantial Completion: +79 days
Final Completion: +79 days
In addition to the costs and time extension, the City of South Bend agrees to omit any
liquidated damages associated with the delays for Shutdown C (Final Clarifier 6 and Final
Clarifier 7 Long Shutdown). The circumstances surrounding the dewatering operation were a
vital part of the project and work continued despite the delays. Start-up occurred after the
original schedule date. Good faith efforts were made by the City of South Bend, Thieneman
Construction (General Contractor), and Arcadis U.S. (design engineer) to maintain progress
and adjust work sequence despite the dewatering delays.
The primary funding sources for Change Order No. 10 is the 2012 Sewer Bond (661-0630-415-
42-06). This approval is subject to a 311J Quarter Appropriation that will move bond funds from
Sewer to Wastewater Treatment Plant for the purposes of paying for this Change Order No. 10
work. if there are questions regarding the subject change order, please contact Al Greek (Ext.
4210) or Jacob M. Klosinski (Ext. 9496) at the Division of Utilities.
114-053
WWTP Secondary Treatment Improvements
Dewatering Delay Cost Breakdown - Change Order No. 10
Item No.
Description
Amount
1
Temporary Well #3
$ -
2
Temporary Well #5 & #6
$ -
3
Temporary Well #7
$ -
4
Leave Temporary Well 7 In Service
$ 13,22550
5
Temporary Well #8
$ -
6
Temporary Pumps at RAS Pump Station
$ 6,977.00
7
Overtime August -December 2016
$ 49,959.00
8
Management Costs
$ 169,412.20
8
Construction Equipment Costs
$ 146,596.25
10
Winter Conditions
$ 12,723.24
11
Lost Productivity - Winter Work
$ 19,000.00
12
Premiums for Electrical Work
$ 4,106.81
TOTAL Change Order No. 10 Value
$ 422,000.00
Value Agreed upon 06/06/2017---------------- >
$422,000.00
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date June 6, 2017
Name Jacob M. Klosinski Department Utilities Wastewater
BPW Date June 13, 2017
Phone Extension (574) 235-9496
Rego ired Prior to Submittal to Board
Legal ®
Attorney Name Michael Schmidt
Controller ®
Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ®
Carol Kurzhal
. Check the`A
ro riate ltbhi`T e 4 Required f&A11:SdbmJssJons
❑ Agreement
❑ Contract ❑ Proposal ❑Addendum
❑ Professional Services
❑ Resolution
❑ Bid Opening
❑ Bid Award. ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening
❑ Quote Award
® Change Order No. 11
❑ CIO & PCA No. ❑ PCA
❑ EaselEncroach.
❑ Traffic Control
❑ Other:
Re aired Information77771
Company or Vendor Name
Thieneman Construction Inc.
New Vendor
❑ Yes ® No ❑ If Yes, Approved by Purchasing
MBEIWBE Contractor
❑ MBE ❑ WBE
MBEIWBE Contractor Requested
❑ No ❑ Yes Name of Company
Project Name
Wastewater Treatment Plant Secondary Treatment Improvements
Project Number
114-053
2012 Sewer Bond, Capital Improvements Wastewater Treatment
Funding Source
Plant (subject to 3rd Quarter Appropriation)
Account No.
661-0630-415-42-06
Amount
$
Terms of Contract
Lump Sum and Unit Prices
Purpose/Description
The Division of Utilities recommends the approval of Change Order
No. 11 which includes necessa concrete work saw cutting, and
grating required but not detailed in the original scope of work.
❑ Required Contractor's Certification Form Attached (Non -
Collusion. Nan -Discrimination. Non -Debarment. E-Verifv. Iran. etc.)
Amount of ® Increase $ 31,550.00
❑ Decrease $
Previous Amount $ 13,468,684.87
Current Percent of Change: 0.26%
New Amount $ 13,500,234.87
Total Percent of Change: +13.59%
Dispersal After Approval
Copy Original
® ❑ Al Greek, Director of Utilities
® ❑ Jacob M. Klosinski, Assistant City Engineer
® ❑ Carol Kurzhal, Director of Financial Services, Environmental Services
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF UTILITIES
TO: Members of the Board of Public Works
Eric Horvath, Director of Public Works
Michael Schmidt, Board of Public Works Attorney
FROM. Al Greek, Director of Utilities
Jacob M. Klosinski, Assistant City Engineer
SUBJECT: Agenda Request Form — Change Order No. 11
Project No. 114-053: Wastewater Treatment Plant Secondary Treatment
Improvements
DATE: June 6, 2017
The Division of Utilities is requesting the Board of Public Works approval of Change Order No.
11 for Project No, 114-053 Wastewater Treatment Plant Secondary Treatment Improvements.
Refer to attached documents for supporting details for work.
Change Order No. 11 addresses the following changes:
Wall Opening (sawcutting, drilling and demolition)
Concrete Gate Pockets and Masonry Patching at Gallery #3 for Final Clarifier 4 & 5 Gates
New Aluminum Walkways for Access to Gate Actuators
Electrical Relocations
Refer to Cost Breakdown Sheet for Line Item Cost Details.
Notes:
Cost breakdown for "Request for Proposal No. 2" herein described as Change Order No. 11.
Approval of Change Order No. 11 with Change Order No. 12 provides cost savings.
Original Cost Estimate $41,892.55 - $10,343.00 (reduction) = $31,549.55
Final Cost for Change Order No. 11 = $31,550.00
NET INCREASE FOR CHANGE ORDER NO. 11 ITEMS
Original Contract Sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this change order, the project amount increases by
The new contract sum including this change order is
This Change Order represents a total change of
Total change for the entire project
Time Extensions resulting from Change Order No. 11.
Substantial Completion:
Final Completion:
$ 31,550.00
$11, 885, 000.00
$ 1,583,684.87
$13,468, 684.87
$ 31,550.00
$13,500,234.87
+0.26%
+13.59%
+0 days
+0 days
The funding source for Change Order No. 11 is the 2012 Sewer Bond (661-0630-415-42-06).
This approval is subject to a 310 Quarter Appropriation that will move bond funds from Sewer to
Wastewater Treatment Plant for the purposes of paying for this Change Order No. 11 work. If
there are questions regarding the subject change order, please contact Al Greek (Ext. 4210) or
Jacob M. Klosinski (Ext. 9496) at the Division of Utilities.
'7-7','a:a- ?"`,:: "-
iadi'ux�rl...sx� �
r
_
pp
J
,u
a'
�1
e
t
o
�»
s
-.:
#3 above), as the reduced staff time for RFP #3 adder may be offset by late release delay
costs.
In the meantime the owner has acknowledged that we are removing access ways
associated with RFP 42, and has stated that they will provide means for temporary access
of plant personnel until our replacement metals can be fabricated and installed.
Since 01
C •aig Steele
Contract Manager
Cc; Jacob Klosinski, City of South Bend
File
INDUSTRIAL • MUNICIPAL CONTRACTOR
521 W. 84th Drive *Merrillville, IN 46410 . 219-947-4700 + Fax 219-947-4711
17219 Foundation Pkwy s Westfield, IN 46074 •317-867-3462 • Fax 317-867-3463
PRICING SHEET W_
�-
PAGE
1
�OP
-
PAGES
NAME:
ARCH. OR CONTRACTOR:
South Bend STi Pra'ecE
Arcadia
I
_
LOCATION:
TYPE OF WORK:
Soutb Bend WWTP
RIiP 42
ESTIMATED BY: Craig Steele
PRICED BY:
FXTENDED BY:
CHECKED BY:
DATE:
�. -----_-�_
CIS
_
IS C
__
Cis
-_
512512017
LABOR/EQUIP
I MATERIAL.
DESCRIPTION
QUAN.
UNIT
UNITS
TOTAL
UNITS
TOTAL
SUB
TOTAL
core drilling s sawcuItting------
I
LS
$3,500.00
Pamo -11 l3u4 +crane)
1
LS
$ 2 5o0.98
$ 2 500.88
- ----
----_
$ -
-$3,500.00
$2 500,88
nump.t-
0.5
EA
S
$ 400.00
$ 200.00
S200.00
Gate Pockets
$I OD0.00
$1000.00w
Hand de=o wall opeeinva (2md)
I
LS -
$ 1,555,84
$ 1555 84
$ -
$1,555.84
onm ecer
O.S
EA
$ -
$ 400.00
S 200.00
$2WOO
Backside formwork 2nrd
I
LS
S 932.00
$ 932.00
$ 150.00
$ 150.00
S1 082.00
Dowels and rebar 2md
I
LS
$ 932.00
$ 932.00
$ 300.00
$ 30000
$1232.00
Fo_ ]a 5vreck and mb (Bmd)
1
LS___
$ 3,728.00
S37226 00
$ 0.00
$ 400,00
$A 128.00
Mason alchin not needed based en elevation of cast stone band
L$
$
$
3
New Aluminum\►'allnv------�-
__ __
__ __ _
-
---
--
- _
New aluminum walkv y (3md + ne)
I
LS
$ 2,500.88
$ 2,500,88
$ 4,000,09
$ 4,000,00
$6 M0.88
Electrical - - - - - - - -
--
Electrical
--�
$ ----
---
$ ----
$4 070,00
$4 020.00
Contract Mana er-Cltxngeorder re emtion
S 140.00
$ 1,120.00
$1,120.00
Contract Manager 40% of time extension $0 if RFP#3 approved)
$ 140.00
$ 2,240,00
$2,240.00
Project Manager
S 125.00
$
Su eriatendent(80%oftime ezlension)(S0 ifRFP#3 approved --
-
EHR
S II0,00
$ 3,520.00
$3,520.00
Field Enginecr 80% oftime extension $0 ifRPPN3 a roved
$ 75.00
$ 2,400.00
$2400,00
Project Coordinator 20%oftime extension SO ifRFP#3 a raved
$ 50.00
$ 400.00
S400.00
Subtotal=
$21,829.60
Subtotal
$5,250.00
$8 520.00
$35 599,60
Small Tools 3%
$1067.99
Bond 1 %
$366.68
Insurance(I%)
$370.34
-
Markup
on Sub 5°/
$426,00
-____----------- --
------
Markup on LlElh4 15 %
$4 06194
TOTALAdds
$41 892.55
NETCHANGE
$41,892.55
CIRANGEORDER REQUEST
$41,893.00
--�__
ADDITIONAL
CONTRACT TIME:
5 Data
Notes / Clarifications:
Formu)ll besbaudwedbebbid eleclticai gciral gale pocicu
--
-
Eketdcal re,,o,k included m gate locations
-
Costs &[ Time:
-
If RFP1l2 & RFP p3 an: bodrapV-d, ynu can deduct (510.343) & 5 days from RFP N2
----
--
----
zmm
�'`��
�f �y..
L4 PI
........
...
77 74.,
lll�
A �j:,sa
a.
F "71"
7
17,17 -
#3 above), as the reduced staff time for RFP #3 adder may be offset by late release delay
costs.
In the meantime the owner has acknowledged that we are removing access ways
associated with RFP #2, and has stated that they will provide means for temporary access
of plant personnel until our replacement metals can be fabricated and installed.
Sigw'gasteele
C
Contract Manager
Cc: Jacob Klosinski, City of South Bend
File
INDUSTRIAL • MUNICIPAL CONTRACTOR
521 W. 84th Drive •Merrillville, IN 46410.219-9474700 + Fax 219-947-4711
17219 Foundation Pkwy . Westfield, IN 46074 . 317-867-3462 • Fax 317-867-3463
PRICING SHEET
PAG ]
--- --
-�..-_.---- ----
-
- Or
PAGES ----
NAME:
ARCH. OR CONTRACTOR:
_
South Bend STI Project
Arcadis I
_
I
_
TYPE OFSVORK:
South Bend WWTP _ --
RFP #3 - Witit VG
ESTIMATED BY.-CraiStcele--------
PRICED BY:
EXTENDED BY:
CHECKED BY:
DATE:
cis
Cis
cis
512612017
LABOR/EQUIP
MATERIAL
DESCRIPTION
QUAN.
UNIT
I UNITS
TOTAL
UNITS
TOTAL
SUB
TOTAL
Demolition__.__..
-------
-----`---
-
----
Demo note Ad (15md + excl-aae/apider)
1
LS
$ t1,7779.00
S 11,779.00
- -
$ -
$12,785.00
-- $24,564.00
Demo not. is (9md + avator)
cadd
I
LS
S- 5752.00
5 5,752.00
5
$l 625.00
$7 377.00
demo note 95 - VE, s for base RFP scope
1
LS
$
$
_
Demo note 47 4md+exc/cranels ides
1
LS
$ 5672.00
$ 5,672.00
$
$600.00
$6272.00
Democoncretewallnviysbel(wmd+excicranels ider
I
LS
$ 5672.00
$ 5672.00
$ -
$1750.00
$7422.00
Dum sters
IO
EA
$ 400.OD
1 $ 4,000.00
$4000.00
Concrete ------
-
--
--
----
____
aeration deck lincludes ste a, nosingrs, and e,p jointa) 116nm
8593
SF
$ 11.02
$ 94,694.86
$ I0.33
$ 75,765.69
$13 000.00
$lea 460.55
Elevated walkways _VE_oee base RF8 add
SF
$_ -
$
slab on grade ramp lad +equip ment)
391
Sr
$-- 5.50
$ 2e50,S0
$ - 6,00
$-c346.00
Railings
L4,d4fyr eL14tjEg (newt eailings (contract F it price - no addi
79
LF
$ -
$ -
$ -
$ -
$4,89&00
$4,898,00
Remove & r�uaee railings contract unit price = no additional m/s
1077
LF
$ -
-
$ -
-
$- -
$ -
$66,774.00
_
- $66,774.00
-------------------------
Metals....
Hatches 2 0 40" x 72" (4md + oranel
_. I
LS
$-3032.0O
$ 3032.00
$ 4006.00
$ - 4006T(5
Al --- in. co r plates 3 0 5' x lei land_+ ne) (macerial i
I
LS
$ 3632.00
$ 303200
$
$
$3032.00
Misc base bid modificaeions -
I
LS
$
$
$ 25,000.00
$25000.00
Coatings
Touchup wall tops - VE, see base RPP add -
1
LS
$
$
Electrical
F.l catrfcal -_-
- I
LS-__
$ ---�
---
$ ----
- $y7653.00
-
$7653.00
Cantmcl Manager - Chan a order preperation
40
HR
S 140.00
S 5,600.00
$5 600AO
Contracl Manager 40% or billable hours for time extension
69.28
HR
$ 140.00
S 9,699.20
$9 699.20
PJect Manager -
HR
$ 125.00
$ -
Superin[endentl80%ofbillablehours for time extension
138.56
HR
S 110.00
$ 15,241.60
$15,24L60
Field Engineer 80% of billable hours for time extension
138.56
HR
$ 75.00
$ 10,392.00
$10 392.00
ProiectCoordinator (20/ofbillablehours for lime extension)
34.64
HR
$- 50.00
$-1�732A0
---
---__--
-----
--
$1732,00
Subtotal=
$174,449.16
Subtolak
$I11,117.09
1 $109,085.00
$394,651.85
Small'fools 3%
$9699.40
Bond l%
$3 326.69
I Insurance 1%
$4076.68
-
--
-
Markup
on Subs 51/.
$] 870.65
Markupon L/FAf I5%
542 835 03
----------
----
---
----
---
-
TOTAL Adds
$456 456.29
----------------
NETCHANCE
$456 450.29
CHANGE ORDER REQUEST
$456,450.00
ADDITIONAL CONTRACT TIME:
30 Days
Notes Clarifications:
F-W-%Vest clwl wl crossing Ir,ndmils,rid bo cut orf at 8151 side of nendo,, ch. .1.
_
Additional C1ariGcalions I
Inclusions:
North -South handrails at Fast side ofchanne) are NOT included
Sequencing & material handling
-
-
All new handrails will be anchored vs cared and grouted
_
Safety decks
£xis[in checker Iates to be shored and used as farms for new deck and remain'ut
--�--------------�
New deck to receive a light broom finish p. rpendicular to traffic
lace
�
---
----
-----
Material lestin
_ . _._.__g..,_
Rubbing-
_. ..
-----
_--_
-----
Decking and handrails have been included on bath East & West sides of the Aearation deck for access and safe
Haunch pockets
We have assunted that concrete re9uirentents are the sable as the main'ob I r
Shoring existing meW covers
Electrical rework included for deck traffic box and rerouti n- conduit on handrail and existin- racks to refeed Soutlt li Itting
Equipment Exe Cranes Punts Lu11
Medium tools elc-
Hatch Pricing based oil Halliday Products W2S ACCESS F&C, and X2S RETRO-GRATE
_
-
Curing
Expansion 'oinls
VE;
Drillin Dowels
Tlds pricing includes the VE credil to ° rovee the t existin cel hanncrossia s, iri lieu of removing m K lace- tbam
Accessories
The new "step" location will be East of the existin- grating,
Casts & Tittle;
If RPP 41 & RFP #3 are bathe mred, youandeducl S10,141 & i da ys fmm RFP 02
Nola if this PCO is no[ a roved b the next Progress Meeting on 4/18117, our remaining East side work may he dela
ed
Page I °f l
PRICING SHEET
—___-_—
OF
1PAGES
NAM£:
ARCH. OR CONTRACTOR:
—
South Bend STI PrdecE
Areadis I1
----
-------
---
—
LOCATION:
TYPE OF WORK:
South Bend WWTP
RPP N3 - Base bid add
ESTIMATED BY: Craig Steele
PRICED BY:
EXTENDED BY:
CHECKED BY:
DATE:
C15
CJS
C35
5/26/2017
LABOR IEQUIP
MATERIAL
DESCRIPTION
QUAN.
UNIT
UNITS
TOTAL
I UNITS
TOTAL
SUB
TOTAL
Demo€itioa
nemo note ti6 add for base RFP scone €7md , ac/cyan
— m..—
— I
LS —
$ 10 I37.00
$ 10137A0
_14
$
$4,585.00
71_22.00
S--$400.00
Dum stets
1
EA
5 400.00
$ 400,.00
Concrete
Elevated walkways - VE, see base RFP add 16md + equip-0
242
SF
$ 12.33
$ 2,983.86
$ 5.87
$ 1,420.54
S4,404A0
Y......_
Touchup s 11 tops - VE, see base "P add
l
LS—
$
$
$3 000,00
$3 000.00
Contract Manager - Change order preperation
4
HR
$ 140.00
$ 560_00
— $560.00
Contract ManagerL 0/a of billable hours for lime extension
__.
..
HR
$ I40 m
$ —.
---
Pra ect Mana ter
lit
$ 125.00
$
Superintendent 60% ofbillable hours for time extension
HR
$ 110.00
$
Field Enaianeer 800/6 of billable hours for time extension)
FIR
$ 75,00
$ -
Pro ecl Coordinator 20%of billable hours for time extension
HR
$ 50.00
$ -
Subtotal—
$13 690.86
Subtotal—
$1,820.54
$7 585.00
$23,096.40
$malt Tools 30/
$692.59
Hond 1%
$237.79
]nsurance I%
$240.17
Marp
on Subs 5%
$379,25
_
—--------- ---
—
____—
--
_ Marku oa LlFJIt4 15%
-- $2y325.21
— — ------ �
--
—
---
---
TOTAL Adds
$26 961 A I
NET CHANGE
$26 961.41
CHANGE ORDER
REQUEST
$26 961.00
ADDITIONAI. CONTRACT TIME:
0 Days
Notes/ Clarifications:
This work will require a dry channel, and will be completed after all of the other work is
done
This revision assumes that the City will drain & clean the entire Aeration side channel allo%%ing us simultaneous
access to all 4 deck re lacemeuts concurrent with our other deck work
VE,
This n includes the costs to n:moce and re tare the d esistin channel crossi inlicu oi' i ored' them
Costs & Time:
Costs and fame for this scope stand alone
mm
Date
Name
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
June 6, 2017
Jacob M. Klosinski
Department Utilities Wastewater
BPW Date June 13, 2017 Phone Extension 574 235-9496
Re aired Prior to Submittal to Board
Legal ® Attorney Name Michael Schmidt
Controller ® Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing
® Carol Kurzhal
U Agreement U Contract LJ Proposal U Addendum
❑ Professional Services ❑ Resolution
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award
® Change Order No. 12 ❑ CIO & PCA No. ❑ PCA
❑ Ease/Encroach. ❑ Traffic Control
I-1 Other:
Company or Vendor Name
Thieneman Construction, Inc.
New Vendor
❑ Yes ® No ❑ If Yes, Approved by Purchasing
MBEIWBE Contractor
❑ MBE ❑ WBE
MBENVBE Contractor Requested ❑ No ❑ Yes Name of Company
Project Name
Wastewater Treatment Plant Secondary Treatment Improvements
Project Number
114-053
2012 Sewer Bond, Capital Improvements Wastewater Treatment
Plant (subject to 3rd Quarter Appropriation) and Wastewater
Funding Source
Equipment Purchases 1 Treatment and Disposal
Account No.
661-0630-415-42-06 (2012 Bond); 642-0630-415-43-66
Amount
$
Terms of Contract
Lump Sum and Unit Prices
Purpose/Description
The Division of Utilities recommends the approval of Change Order
No. 12 which includes additional concrete decking, handrail, ramps,
transitions. and adiustments to miscellaneous metals to remedv
U Required Contractor's Certification Form Attached (Non -
Collusion. Non -Discrimination. Non -Debarment, E-Verifv. Iran, etc.
Amount of Increase $ 483,411.00; 30 days to Substantial and Final Completion
Decrease $
Previous Amount $ 13,500,234.87
Current Percent of Change: +4.07%
New Amount
Total Percent of Change:
Copy
Original
®
❑
$ 13,983,645.87
+17.66%
Dispersal After Approval
Al Greek. Director of Utilities
Jacob M. Klosinski, Assistant City Engineer
Carol Kurzhal, Director of Financial Services, Environmental Services
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF UTILITIES
TO: Members of the Board of Public Works
Eric Horvath, Director of Public Works
Michael Schmidt, Board of Public Works Attorney
FROM: Al Greek, Director of Utilities
Jacob M. Klosinski, Assistant City Engineer
SUBJECT: Agenda Request Form — Change Order No. 12
Project No. 114-053: Wastewater Treatment Plant Secondary Treatment
Improvements
DATE: June 6, 2017
The Division of Utilities is requesting the Board of Public Works approval of Change Order No.
12 for Project No. 1144-053 Wastewater Treatment Plant Secondary Treatment Improvements.
Refer to attached documents for supporting details for the subject work.
Change Order No. 12 addresses the following changes:
Demolition of Concrete Walkways
Demolition of Containment Area at the south end of Aeration
New Concrete Aeration Gallery Decking
New Aeration Gallery Handrail to replace obsolete and damaged rails
New Hatches for Aeration Gallery 1 Tunnel Access
Access Step Modifications for Gallery #1, #2 and #3 (WWTP Buildings #8, #9, and #10)
Concrete Coatings and Coating Touch-up
Electrical Relocations for Lighting and Receptacles
Concrete Slab -on -Grade at south end of Aeration 1 Secondary Treatment for Vehicle Access
NET INCREASE FOR CHANGE ORDER NO. 12 ITEMS $483,411.00
Original Contract Sum $11,885,000.00
Net change by previously authorized change orders $ 1,615,234.87
The contract sum prior to this change order $13,500,234,87
By this change order, the project amount increases by $ 483,411.00
The new contract sum including this change order is $13,983,645.87
This Change Order represents a total change of +4.07%
Total change for the entire project +17.66%
Time Extensions resulting from Change Order No. 9:
Substantial Completion: +30 days
Final Completion: +30 days
Notes:
Change Order No. 12 addresses "Request for Proposal No. 3" which the City requested pricing
for after Arcadis U.S. completed the design effort previously approved by the Board of Public
Works. The cost for this proposal includes value engineering costs from by Thieneman
Construction in conjunction with the proposal pricing supplied for Change Order No. 12. This
proposal was requested as an additional scope of work. The Aeration Gallery Deck had
originally been omitted from the project as a cost saving measure during design. Low costs
during bidding provided an opportunity to address safety and access deficiencies while the
General Contractor is mobilized and performing work at the Aeration Gallery. The resultant
effort results in an increase in costs and will providing better access to the Aeration Gallery,
Aeration Tanks 1-4 and Final Clarifiers 1-5.
The funding sources for the construction of this project are the 2012 Sewer Bond (661-0630-
415-42-06) and Wastewater Equipment Purchases / Treatment and Disposal (642-0630-415-43-
66). This approval is subject to a 3rd Quarter Appropriation that will move bond funds from
Sewer to Wastewater Treatment Plant for the purposes of paying a portion of Change Order No.
12. The expected split is $78,742.04 from the 2012 Sewer Bond and $404,668.96 from the
Wastewater Equipment Purchases / Treatment and Disposal Account. If there are questions
regarding the subject change order, please contact Al Greek (Ext. 4210) or Jacob M. Klosinski
(Ext. 9496) at the Division of Utilities.