HomeMy WebLinkAboutChange Order No. 1 - Michiana Brick Site Demolition Proj No 116-138 - Indiana Earth, Inc.i ��`. _ �I� k 0 'Amin City of South Bend Project No. 116-138 OWNER: City of South Bend ENGINEER: City of South Bend Engineering Kara M. Boyles, P.E. Professional Engineer No. 10809510 CONTRACTOR: Indiana Earth, Inc. PROJECT: Michiana Brick Site Demolition Project No. 116-138 SUBJECT: Change Order Explanation ISSUE DATE: April 20, 2017 Change Order No. 1 - 4120/17 This Change Order to the Contract document shall supplement, amend, and shall become a part of, and be incorporated as an Addendum to the Contract. The following is a summary and description of the revisions to the Contract by this Change Order: Item Qtv Unit Price Days Total 1. Varying Site Condition 1 LS $700.00 0 $700.00 Net Change Order amount $700.00 1) One of the building had metal roofing and siding that were removed after the bid award by an unknown party. The scrap value (minus the laborltrucking costs) was estimated at $700 and was factored in to reduce the original bid. 7 k - � _ I,