HomeMy WebLinkAboutChange Order No. 1 - Century Center CEO Suites Suite 17 Remodel Proj No. 116-010 - Holladay Construction Group1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND_ INDIANA 46601-1830
CITY OF SOUTH BEND PETE BUTTIGIEG, MAYOR
BOARD OF PUBLIC WORKS
January 24, 2017
Al Lusk
Holladay Construction Group
227 S Main Street, Suite 200
South Bend, IN 46601
RE: Change Order No. 1 - Century Center CEO Suites — Suite 17 Remodel
Project No. 116-010
Dear Mr. Lusk:
PHONE 574/235-9251
FAx 574/235-9171
The Board of Public Works, at its meeting held on January 24, 2017, approved the above
referenced Change Order for a decrease of $12,078 and an additional twenty-eight (28)
calendar days, bringing the current contract amount to $205,984 and the new project
completion date to January 23, 2017.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
LC4 �2
Linda M. Martin, Clerk
Enclosure
c: Rich Estes, Engineering
Scott Herczeg, Century Center
Leanna Belew, Century Center
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK JAMES A. MUELLER THERESE J. DORAU
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO.
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
01-24-2017
116-010
Century Center — CEO Suites — Suite 17 Remodel
9-6-2016
SUBJECT OF CHANGE ORDER: Time Extension and additional work. See attached explanation
of work
All items completed substantially as planned.
_See attached Comparison of Estimate for overruns and underruns
The original contract sum $ 218,062.00
Net change by previously authorized change orders $ 0.00
The contract sum prior to this change order $ 218,062.00
By this Change Order, the project amount is ❑Increased
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
® Decreased $ (12,078.00)
$ 205,984.00
(5.86) %
(5.86) %
Original contracted completion date/time 12-27-2016
Extension of date/time by previous change orders 0 days
Date/time extension by this change order 28 days
New completion date/time 01-23-2017
--RECOMMENDED FOR APPROVAL
'//l�
CONTRACTOR Project Manager
1► �, Al_
.ck oi1
Printed i
Name
andTitle
Holladay Construction Group
Company name
227 S. Main Street Suite 200
Address
South Bend Indiana 46601
City, State, Zip
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
Approved Date:
Gary
President i
Elizabeth A. Maradik, Member
A
Suzanna MSuzanna FrAberg, Mem erMem er
Therese J. Dorau, Member
Ja es A. Mueller, Member
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Linda M. Martin, Clerk
Board of Public Works
FROM: Richard Estes, Engineer I
SUBJECT: Century Center — CEO Suite — Suite 17 Remodel
Costs related to change in scope of work resulting from unforeseen
conditions and program changes
Project No. 116-010
DATE: January 24, 2017
Here is an explanation for the Change Order being submitted.
The reason(s) for the Change Order request is as follows:
1. Removal of mirrors, delete solid surface restroom doors, delete new exterior window, and
new entry door and sidelite, etc. were deleted from the scope of work as directed by the
Owner.
2. Changes to casework in Wet Bar / Closet Room No. 205 resulting from unforeseen existing
conditions.
3. Changes to electrical feed above ceiling serving receptacles above wet bar in Lounge
Room No. 202, as a result of unforeseen conditions.
4. Add stainless steel bar sink and faucet in Lounge Room No. 202 to replace existing unit.
5. Remove and replace existing ceiling tile and grid in Lounge Room No. 202 to make entire
ceiling uniform.
The deduct amount for this work shall be $12,078.00. This represents a decrease of 5.86% for the
overall project cost. 28 calendar days are also being added to the completion date.
Please call me with your questions (5896).
Change Order No.1
Century Center
CEO Suite - Suite 17 Remodel
Project No. 116-010
OWNER: City of South Bend
ENGINEER: Alliance Architects
CONTRACTOR: Holladay Construction Group
PROJECT: Century Center — CEO Suites — Suite 17 Remodel
Project No. 116-010
SUBJECT: Change Order Number 1, Explanation of Costs
ISSUE DATE: January 24, 2017
This Change Order to the Contract document shall supplement, amend, and shall become a part of,
and be incorporated as an Addendum to the Contract.
The changes to the scope of work listed herein result from corrections to existing, and unforeseen,
conditions involving both general construction and electrical items. The changes to eliminate the new
door and sidelight to Suite 17 Room No. 101 and new exterior window in Conference Room No. 207,
and others, were directed by the Owner.
The work description for the changes applied to this change order is describe below:
Work Description:
1.
Delete all mirrors from the scope of work
Deduct
$640.00
2.
Delete solid surface stall door from Toilet Room #103
Deduct
$970.00
3.
Add 3 (three) Type "A" wall mounted light fixtures to
Suite 17 Room No. 101
Add
$964.00
4.
Add door frames in Suite 17 (total 3)
Add
$400.00
5.
Delete solid surface bar sink in Suite 17 — Room No. 101
Deduct
$300.00
6.
Add stainless steel bar sink to Lounge Room No. 200
Add
$610.00
7.
Delete new exterior window in Conference Room
No. 207 from the scope of work
Deduct
$7,892.00
8.
Revise casework and add access panel in
Wet Bar/Closet Room No. 205
Deduct
$440.00
9.
Delete new entry door and sidelight to Suite 17
Room No. 101 from the scope of work
Deduct
$4,442.00
10.
Remove and replace existing acoustical ceiling tile
in Lounge Room No. 202—CCD No.5
Add
$733.00
SHEET 1 OF 2
Change Order No.1
Century Center
CEO Suite - Suite 17 Remodel
Project No. 116-010
11. Delete full -height backsplash at each wet bar counter,
Suite 17 Room No. 101 and Lounge Room No. 202 Deduct $1,350.00
12. Provide overhead electrical feed to receptacles
above wet bar in Lounge Room No. 202; Provide
custom trim for new downlights in Hall Room No. 102 Add $1,064.00
13. Change lockset (Door C-1) between Ticket Office Room
No. 200 and Lounge Room No, 202 to keyed function
each side. Add $185 00
Subtotal Deduct ($12,078.00)
XIII. PROSECUTION AND PROGRESS
Revise the following:
1. The project will have a Substantial Completion date of 443 141 calendar days from the date
that the Notice to Proceed is issued and a Final Completion date of 4-20 148 calendar days
from the date that the Notice to Proceed is issued.
Total Change Order Request: Deduct $12,078.00 and add 28 calendar days.
END CHANGE ORDER 1
SHEET 2 OF 2
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 01/06/2017 Department Public Works
Name Richard Estes Division/Bureau Engineering
BPW Date 01/24/2017 Phone Extension 5896
Required Prior to Submittal to Board
Legal ® Attorney Name: Michael Schmidt
Controller El greater
review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ® George King
r Check the Appropriate Item Type — Required for All Submissions
❑ Agreement ❑ Contract ❑ Proposal ❑ Addendum
❑ Professional Services ❑ Resolution
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award
® Change Order No. 1 ❑ C/O & PCA No. ❑ PCA
❑ Ease/Encroach. ❑ Traffic Control:
I-1 Other:
Company or Vendor Name
New Vendor
MBE/WBE Contractor
MBE/WBE Contractor Requested
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Amount of L I Increase
® Decrease
116-010
Hotel -Motel Tax
7304-42010-0000-0099
Change order to reflect changes to scope of work due to
unforeseen conditions involving both General Construction and
Electrical, as directed by the Owner.
❑ Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
Previous Amount $ 218
Current Percent of Change: (5.K
New Amount $ 205
Total Percent of Change: (5.86)
Copy
Original
®
❑
®
❑
and add 28 calendar
s:-
Leanna Belew, Scott Herczeg (Century Center)
Bill Lamie. Joe Nucciarone (Alliance)
AI Lusk, Holladay Construction Group