HomeMy WebLinkAboutChange Order No 2 - WWTP Grit and Screenings Improvements Proj No 114-075 - Thieneman Construction1316 COUNTY-CITV BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND. INDIANA 46601-1530
CITY OF SOUTH BEND PETE BUTTIGIEG, MAYOR
BOARD OF PUBLIC WORKS
December 22, 2016
Matt McCoy
Thieneman Construction, Inc.
521 W 84"' Drive, Suite A
Merrillville, IN 46410
PHONE 574/235-9251
FAX 574/235-9171
RE: Change Order No. 2 — Wastewater Treatment Plant Grit and Screenings
Improvements - Project No. 114-075
Dear Mr. McCoy:
The Board of Public Works, at its meeting held on December 22, 2016, approved the above
referenced Change Order for an increase of $24,319.66, bringing the current contract amount
to $1,172,917.50.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
e: Jacob Klosinski, Environmental Services
Al Greek, Environmental Services
Carol Kurzhal, Environmental Services
GARY A. GrLoT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK JAMEs A. MUELLER THEREsE J. DORAU
ovTneENq
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS
r z
PROJECT CHANGE ORDER
DATE: 121131201
PROJECT NO: 114-Ui5
PROJECT NAME: WWTP Grit and Screenings Improvements
CONTRACT DATE: 12/15/2015 (Notice to Proceed)
CHANGE ORDER NO. 002
SUBJECT OF CHANGE ORDER: Add Touch Screen Panel and Analog Feed Cards
All items completed substantially as planned.
See attached Comparison of Estimate for overruns and underruns.
The original contract sum $ 1,146,000.00
Net change by previously authorized change orders $ 2,597.84
The contract sum prior to this change order $ 1,148,597.84
By this Change Order, the project amount is ® Increased
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
❑ Decreased $ 24,319.66
$ 1,172,917.50
+2.12 %
+2.35 %
Original contracted completion date/time 10/10/2016 (Substantial Completion)
11/9/2016 (Final Completion)
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
CONTRACTOR
Contractor Signature
Matt McCoy, Project Manager
Printed Name and Title
Thieneman Construction, Inc.
Company name
521 W 84th Drive, Suite A
Address
Merrillville, Indiana 46410
City, State, Zip
Completion 0 days
onstruction Manager
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
Approved Dater
J' ,
Gary A. Gilot, President
i
Jam A. Mueller, Member
Suzanna M. Fritzberg, Member
Elizabeth A. Maradik, Member
Therese J. Dor u, Mtober
TRIENAN
iKSTNUCTIONAC.
December 7, 2016
Greeley and Hansen
7920 Innovation Blvd. Suite 150
Indianapolis, IN 46278
Attn: Mr. Trent Montemayor
Subj: South Bend Grit and Screenings
Proposed Change Order #6 Revision 2: SCADA Touch Screen
Mr. Montemayor:
Please refer to the detail and proposal for Change Order Request #6 to furnish and install an Allen
Bradley Panel View Plus 12" touch screen monitor. This proposal was requested in the response
to RFI #9. A time extension of fifty (50) calendar days will be required to procure materials for
this change. The proposal includes furnishing monitor, startup, training, and one (1) year
warranty. Please process an increase to the contract amount of Sixteen Thousand Six Hundred
Seventy Two Dollars and Ninety cents ($16,672.90) for this work.
This proposed change order is being requested at a point when contractual work is near 100%
complete. Acceptance of this proposal, and the associated time extension, will not impact release
of retention on contract work complete at the original substantial completion date.
Respectfully,
Matt McCoy
Project Manager
Cc: Field, File, Accounting
INDUSTRIAL • MUNICIPAL CONTRACTOR
521 W. 84m Dr. • Suite A • Merrillville, IN 46410.219-947-4700 • Fax 219-947-4711
17219 Foundation Pkwy • Westfield, IN 46074 • 317-867-3462 9 Fax 317-867-3463
Contractor's / Subcontractor's
T111A1V VVV Change Order Request Summary
Date: 12/7/2016 COR: 6 R2
General Contractor 521 W. 84th Drive Suite A, Merrillville, IN 46410, 219-947-4700 phone/ 219-947-4711 fax
Engineer: Greeley and Hansen
Owner: City of South Bend
Project: South Bend Grit and Screenings
Improvements
TCI Job #__.___.�� 1511
and install an Allen Bradley Panel View Plus touch screen, color, 12" (2711P-T12W22A9P) monitor to the existing SCADA
s material, installation, progamming, training, and one (1) year warranty.
SUMMARY OF DETAILED BREAKDOWN
LABOR
MATERIAL
EQUIPMENT
OTHER COSTS
1. SAFETY
2. EXPENDABLE TOOLS
NETTOTAL
OVERHEAD AND PROFIT
TOTAL WORK PERFORMED BY CONTRACTOR
Additions Deletions Net Total
(1%of LABOR)-Deletion-0- $ -
(3.0%of LABOR)-Deletion-0- $ -
(A+B+C+D1+D2) $ -
(Ex15%)- Deletion -0- $ -
(Lines E+F) $ -
CONTRACTOR'S MARK-UP ON WORK OF SUBCONTRACTORS
Detailed Breakdowns and summaries from each contractor must be attached.
SUBCONTRACTOR: Firm Name
1. BL Anderson (with Toric)
2.
3.
4.
CONTRACT WORK: Description PROPOSAL
Add Touch Screen $15,644.29
SUBTOTAL of all work performed by contractor's subcontractors $15,644.29
MARK-UP on work of subcontractors (Min. $ .00) (Line H x 5%)- Deletion -0- $782.21
PROPOSAL (Lines G+H+I) $16,426.50
BONDS (1.5%of PROPOSAL)-Deletion-0- $246.40
BUILDER'S RISK INSURANCE (0.0% of PROPOASQ - Deletion -0-
$16,672.90
TOTALPROPOSAL
TOTAL PROPOSALfor subject COR increase (decrease) in contract amount $16,672.90
An extension time of 50 days to extend the Contract dates for Completion will be required commencing on
the date when we are notified a Change Order will be issued for the price quoted herein. Approval needed in 5 days.
If the work has to be performed to continue construction with no response on pricing or if we are issued a Work
Change Directive (WCD) to proceed with this work and agreement on the price has not been reached within 30
calendar days, then this proposal shall be considered a Claim, in accordance with Article 10.5 of the
Contract General Conditions.
CONTRACTOR
Signature Atatt Akear*. Title: PM Date: 12/7/2016
1.317.718.1800
www.toriceng.com
ovember 29, 2016
.L. Anderson
ttn: Gary Prehm
B01 Tazer Dr
afayette, IN 47905
RE: South Bend WWTP Grit Touchscreen Add
Dear Mr. Prehm,
Thank you for the opportunity to quote adding a T9,uchscreen for the South Bend WWTP Grit project.
Toric Engineering's price for this work is .00. This price includes following:
• Hardware: �y �C%�• 37— $ 60
o Allen Bradley PanelView Plus touchscreen, color, 12" (2711 P 2W22A9P)
o Cost - $5,382.63
o Markup ?r !o'f'—_W-r@�6 53 (1 r'-1
o Adapter pl a required due to different PanelView size, stainless steel
55 0
• Engineering Services includes: $8,679.40
o On -site startup (20 hours + travel expenses)
o On -site training
o One (1) year warranty on parts and labor
o Touchscreen graphics (80 hours)
Allow six (6) to eight (8) weeks for delivery.
Payment Terms: Net 30 days
This quote is valid for 60 days.
Please call with any questions or comments.
Sincerely,
Nathen Burkhart
Toric Engineering
i a'1"at-
em
+
,yo,
X 16 Z
l
y�yoS,63
Zt, A aDE-9 5a"� jrt s It �
37- X 6 1p
/7yWo12�7
150 West Clinton St., Suite 1 • Danville, IN 46122
P:317 718-1800 • F:317 718-1843
�i
THI
A:STRUCTION.INC.
September 19, 2016
Greeley and Hansen
7820 Innovation Blvd. Suite 150
Indianapolis; IN 46278
Attn: Mr. Trent Montemayor
Subj: South Bend Grit and Screenings
Proposed Change Order #7: Analog Feed Cards to Existing Rotork Actuators
Mr. Montemayor:
Please refer to the detail and proposal for Change Order Request 47 to furnish and install five (5)
analog feedback cards to the existing rotork actuators. This proposal was requested in the
response to RFI #9. A time extension of fifty (50) calendar days will be required to procure
materials for this change. The proposal includes furnishing, installation, and calibration of the
cards. Please process an increase to the contract amount of Seven Thousand Six Hundred Forty
Sue Dollars and Seventy Six cents ($7,646.76) in the next change order issued for PCO #7.
This proposed change order is being requested at a point when contractual work is near 100%
complete. Acceptance of this proposal, and the associated time extension, will not impact release
of retention on contract work complete at the original substantial completion date. Further,
acceptance of either PCO #6, PCO #7, or both will require only a single time extension of 50
days. Feel free to contact me with any questions.
Respectfully,
Matt McCoy
Project Manager
Cc: Field, File, Accounting
INDUSTRIAL • MUNICIPAL CONTRACTOR
521 W. 841 Dr. • Suite A • Merrillville, IN 46410 • 219-947-4700 • Fax 219-947-4711
17219 Foundation Plcwy • Westfield, IN 46074. 317-867-3462 • Fax 317-867-3463
Contractor's / Subcontractor's
THIECAN
Change Order Request Summary
$ .._
Date: 9/19/2016 COR: 7
A, Merrillville, IN 46410, 219-947-4700 phone/ 219-947-4711 fax
General Contractor
521 W. 84th Drive Suite
Engineer: Greeley and Hansen Owner: City of South Bend
Project: South Bend Grit and Screenings
Improvements
TCI Job # 1511
and install five (5) analog feedback cards to the existing rotork actuators. Proposal includes installation and
SUMMARY OF DETAILED BREAKDOWN
Additions
Deletions Net Total
LABOR
$ $
$
MATERIAL
$ - $
$
EQUIPMENT
$ -
$
OTHER COSTS
1. SAFETY
(1%of LABOR)- Deletion -0-
$ -
2. EXPENDABLE TOOLS
(3.0%of LABOR-Deletion-0-
NET TOTAL
(A+B+C+Dl+D2)
$ -
OVERHEAD AND PROFIT
(Ex15%) - Deletion -0-
$ -
TOTAL WORKPERFORMED BY CONTRACTOR
(Lines E+F)
$ -
CONTRACTOR'S MARK-UP ON WORK OF SUBCONTRACTORS
Detailed Breakdowns and summaries from each contractor must be attached.
SUBCONTRACTOR: Firm Name
1. Toric Engineering
2.
3.
4.
CONTRACT WORK: Description PROPOSAL
Add 5 Analog Cards $7,175.00
SUBTOTAL of all work performed by contractor's subcontractors $7,175.00
MARK-UP on work of subcontractors (Min. $ .00) (Line H x 5%)- Deletion -0- $358.75
PROPOSAL (Lines G+H+I) $7,533.75
BONDS (1.5"%of PROPOSAL-Deletion-0- $113.01
BUILDER'S. RISK INSURANCE (0.0% of PROPOASL) - Deletion -0-
$7,646.76
TOTALPROPOSAL
TOTAL PROPOSALfor subject COR increase (decrease) in contract amount $7,646.76
An extension time of 50 days to extend the Contract dates for Completion will be required commencing on
the date when we are notified a Change Order will be issued for the price quoted herein. Approval needed in 5 days.
If the work has to be performed to continue construction with no response on pricing or if we are issued a Work
Change Directive (WCD) to proceed with this work and agreement on the price has not been reached within 30
calendar days, then this proposal shall be considered a Claim, in accordance with Article 10.5 of the
Contract General Conditions.
CONTRACTOR
Signature .Mnft.McPary Title: PM Date: 9/19/2016
Tracy Powers
From: Gary Prehm <Gary@blanderson.com>
Sent: Wednesday, September 14, 2016 2:29 PM
To: Matt McCoy; Tom Siple; tj siple; Donna Marshall
Cc: Tracy Powers; Jason Davidson
Subject: South Bend
Attachments: South Bend WWTP Grit Touchscreen Add.docx
Dear Matt,
Please see attached Toric proposal to add touchscreen.
In addition , you had requested adding 5 analog feedback cards to existing Rotork actuators. Please find cost
as follows:
5 — Rotork CPT # WCIQ80467 cards.....................................Total $7,175 including installation and calibration.
Please review and let me know if you have any questions.
thanks
a
Gary Prehm
Executive Vice -President
aarv0blanderson.com
4801 Tazer Drive
Lafayette, IN 47905
765.463.1518 Office
765.446.8390 Fax
765.426.0829 Cell
www.blanderson.com
Total Control Panel
To: Remo a this sender from my allow list
tracypowers struction:com
From: gary@blmderson.com
Loam
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date December 20, 2016
Name Jacob M. Klosinski
Department Division of Utilities
BPW Date December 22 2016 Phone Extension (574) 235-9496
Legal ® Attorney Name Michael Schmidt
Controller ® Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ® Carol Kurzhal
❑ Agreement ❑ Contract ❑ Proposal L] Addendum
❑ Professional Services ❑ Resolution
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award
® Change Order No. 002 ❑ C/O & PCA No. ❑ PCA
❑ Ease/Encroach. ❑ Traffic Control
F— Other:
Company or Vendor Name
New Vendor
MBE/WBE Contractor
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Thieneman Construction, Inc.
Yes ® No ❑ If Yes, Approved by Purchasing
MBE I I WBE
WWTP - Grit and Screenings Improvements
114-075
Environmental Services Treatment and Disposal Equipment Account
642-0630-415-43-66
$ Change Order, see below
Division of Utilities recommends the approval of Change Order No. 2 for
the subject project. Refer to Inter -Office Memorandum and enclosures for
description of changes and additional days due to lead time on equipment.
❑ Required Contractor's Certification Form Attached (Non -
Collusion. Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
Amount of N Increase
❑ Decrease
Previous Amount
'.:
Current Percent of Change: +2.12%
New Amount $ 1,172,917.50
Total Percent of Change: +2.35%
Dispersal After Approval
Copy Original
® ❑ Al Greek, Division Director of Utilities
® ❑ Jacob M. Klosinski, Assistant City Engineer
® ❑ Carol Kurzhal, Director of Financial Services, Environmental Services
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENVIRONMENTAL SERVICES
TO: Members of the Board of Public Works
Eric Horvath, Director of Public Works
Michael Schmidt, Board of Public Works Attorney
FROM: All Greek, Director of Utilities
Jacob M. Klosinski, Assistant City Engineer
SUBJECT:
Agenda Request Form —Change Order No. 2
114-075 Wastewater Treatment Plant Grit & Screenings Improvements
D. December 0 2016
The Department of Utilities is requesting the Board of Public Works approval of Change Order
No. 2 for Project No. 114-075 Wastewater Treatment Plant Grit and Screenings Improvements.
Refer to attached documents for supporting details for claims.
Change Order No. 2 addresses the following changes:
PCO 6: Provide Allen Bradley Panel View Touch Screen, Program $ 16,672.90
PCO 7: Provide five (5) Analog Feedback Cards, Rotork Actuators $ 7,646.76
NET INCREASE FOR CHANGE ORDER NO. 5 ITEMS $ 24,319.66
Original Contract Sum $ 1,146,000.00
Net change by previously authorized change orders $ 2,597.84
The contract sum prior to this change order $ 1,148,597.84
By this change order, the project amount increases by $ 24,319.66
The new contract sum including this change order is $ 1,172,917.50
This Change Order represents a total change of +2.12%
Total change for the entire project +2.35%
Time Extensions: 52 Days to Final Completion (for procurement of Touch Screen Panel)
The funding sources for the construction of this project is the Environmental Services,
Wastewater, Treatment and Disposal Equipment Account (642-0630-415-43-66) or other
Wastewater Accounts. If there are any questions regarding the subject project, please contact
Al Greek (Ext. 4210) or Jacob M. Klosinski (Ext. 9496) at the Division of Utilities.