HomeMy WebLinkAboutChange Order No. 5 - Olive St. and Sample St. Reconstruction - Lawson Fisher Assoc.1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND. INDIANA 46601-1830
CITY OF SOUTH BEND PETE BUTTIGIEG, MAYOR
BOARD OF PUBLIC WORKS
December 13, 2016
Don Dietz
Lawson Fisher Associates
525 W Washington
South Bend, IN 46601
RE: Change Order No. 5 - Olive Street and Sample Street Reconstruction
Project No. 113-002
Dear Mr. Dietz:
PHONE 574/235-9251
Fax 574/ 235-9171
The Board of Public Works, at its meeting held on December 13, 2016, approved the above
referenced Change Order for an increase of $11,752, bringing the current contract amount to
$8,992,671.50.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
c: Roger Nawrot, Engineering
INDOT
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK JAMEs A. MUELLER THERESE J. DORAU
Contract No:R -35727 Change Order No.: 005
INDIANA Department of Transportation Page: 1
Construction Change Order and Time Extension Summary
Contract Information Contract No.: R -35727 Letting Date:02/17/2016
District:LAPORTE DISTRICT AE:Forgey, Ryan PE/S:Dietz, Don Status:Draft
Change Order Information
Change Order No.: 005
EWA: Y or Force Acct: N
Date Generated: 00/00/0000
Date Approved: 00/00/0000
Reason Code: CHANGED COND, Materials Related
Description: Anchored Barrier Wall
Original Contract Amount
$ 8,947,369.00
Current Change Order Amount
$ 11,752.50
Percent: 0.131 %
Total Previous Approved Changes
$ 33,550.00
Percent: 0.375 %
Total Change To -Date
$ 45,302.50
Percent: 0.506 %
Modified Contract Amount
$ 8,992,671.50
Time Extension Information
Date Initiated 00/00/0000
Date Completed 00/00/0000
Original Contract Time
SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SP Date 00/00/0000
or SP Days
(SS = Standard Specification,
SP = Special Provision)
Time Element Description:
Current Time Extension
SS Days 0 SP Days 0
SP Days Value $ 0.00
Previous Time Approved
SS Days by AE: DCE:
SCE: DDCM:
SS Days
SP Days Value $
Revised Contract Time
SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SS Date 00/00/0000
or SP Days 0
Contract No:R -35727 Change Order No.: 005
INDIANA Department of Transportation Page: 2
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority AE: DCE: SCE: * DDCM:
($ per Change Order) (- LE $ 250K-) (- LE $ 750K -) (-- LE $ 2 M --) (-- GT $ 2 M -- )
(Days per Contract) ( 50 SS days ) ( 100 SS days) (200 SS Days) ( GT 200 SS days)
Verbal Approval Required? Y / N If Y, by
Total Change To-Date>5%?
Scope/Design Recommendation
Required?
Date Issued
Y / N If Y, Copy to Program Budget Manager
Y / N If Y, Referred to Project Manager(PM)
Date to PM
Approval Authority Concurs with PM? Y / N If Y, Concurrence
LPA Signatures Required?
FHWA Signatures Required?
If N,Resolution: Approved
Resolved by
Y / N If Y, Date to LPA
Date Returned
Date
Disapproved
Date
Date Returned
Y / N If Y, Date to FHWA Date Returned
* Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer Date
Comments:
Contract No:R -35727 INDIANA
Change Order No:005 Department of Transportation Date:11/0 a3
Page: Page: 3
Contract; R -35727
Project: 1298579 - State: 12985790OLC
Change Order Nbr: 005
Change Order Description: Anchored Barrier Will
Reason Code: CHANGED CONIC, Materials Related
CLN PCN PLN Item Code Unit Unit Price co City Comment
0253 1208570 0229 801.08401 LFT Amount Change
Item Description; TEMPORARY TRAFFIC BARRIER TYPE 2 13 t570 750.000 C Amount:$ 11,752.b0
Supplemental Description11 Metal wall replacing concrete wall
Supplemental Descdplion2: using less anchors per lineal foot
Total Value for Change Order CUB = $11,752.50
Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change Is recommended,
General or Standard Change Order Explanation
feeL This This is a meta14 l bander wall that uses only 4 anchors every 33 feet, This wall Is replares the concrete barrier wall requiring 6 anchors every tan
requested the change using a wit the north side of requiring less anchors s phe erIe st LFT torihelp extend the 5fe or te Deck Into the he new bridge deck,oured Concrete
deck. St Joseph Cawrty
Change Order Explanation for Specific Lino item
AYxfaYYAlsaFi h!!{!Y!lYIYYlIrYMYrI.11irYYYYryatrYlrYYlaaYaarlYYrYyIaYYirarrYrx......brae rn,rlanhar..Ylr.Yax}l.Y.YlYaa ......
It Is the intent of the parties that this change order Is full and complete compensation for the work describe above.
Notification and consent to this change order Is hereby acknowledged. _
contractor; F_T! -lit aY
Signed
Date:_ II . It.,..
NOTE: Other required State and FHWA Signatures will be obtained alectmnlcally through the SlteManager system.
Contract No:R -35727 INDIANA
Change Order No:005 Department of Transportation
(SIGNATURE)
(SIGNATURE)
PE/S Ok
APW�fcDllll%WCAL PUBLIC AGENCY
Board of Public Works
(DATE)
SUBMITTED FOR CONSIDERATION
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION
Date: 11 /08/2016
Approval Level Name of Approver Date Status
Page: 4
CoNsrRur.TwN
WV6 Uuality • 100% Employee Owned • Over 100 Years
November 17, 2016
R-35727 Olive/Sample St. Reconstruction
Don Dietz — Project Engineer
Re: Anchored Barrier Wall Change Order Price
Please the following for the breakdown of the change to the metal barrier wall —
The original price Included the following:
• Initial placement— includes hardware, anchor plates, and rental of wall - $15,795.00
• Reset Barrier Wall at Phase Change — includes hardware - $1,920
• Removal of wall at job completion-$3,225
• Temp CZ Units-$17,190.00 (That price was from Specialties —Can provide backup if necessary)
Total - $38,129 (for 7001ft)
Proposed Price includes —
• Initial Placement of Concrete Wall - $15,795.00
• Removal of Concrete Wall - $3,225
• Placement of Steel Zonegard Barrier Wall (Includes, delivery, rental, hardware and anchors) - $12,891.50
• Deduct for reset of concrete in original price — ($1,920)
• Removal of Zonegard wall upon completion - $2,700
• Temp CZ Units - $17,190.00
Total - $49,881.50 (for 700 Ift)
Total Price Increase would be $11,752.50 ($16.79/Ift)
Let me know if you have questions.
Thanks,
Robert Nichols
P.O. Box 1775 25200 S.A. 23 South Bend, IN 46834 \ RD Phone: (574) 288.8321 • www.deth-riley.com
Contract No:R -35727 Change Order No.: 005
INDIANA Department of Transportation Page: 1
Construction Change Order and Time Extension Summary
Contract Information Contract No.: R -35727 Letting Date:02/17/2016
District:LAPORTE DISTRICT AE:Forgey, Ryan PE/S:Dietz, Don
Status:Draft
Change Order Information Change Order No.: 005 EWA: Y or Force Acct: N
Date Generated: 00/00/0000 Date Approved: 00/00/0000
Reason Code: CHANGED COND, Materials Related
Description: Anchored Barrier Wall
Original Contract Amount $ 8,947,369.00
Current Change Order Amount $ 11,752.50 Percent: 0.131 %
Total Previous Approved Changes $ 33,550.00 0
Percent: 0.375 /a
Total Change To -Date $ 45,302.50 0
Percent: 0.506 /o
Modified Contract Amount $ 8,992,671.50
Time Extension Information
Date Initiated 00/00/0000 Date Completed 00/00/0000
Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SP Date 00/00/0000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Time Element Description:
Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00
Previous Time Approved SS Days by AE: DCE: SCE: DDCM:
SS Days SP Days Value $
Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SS Date 00/00/0000 or SP Days 0
Contract No:R -35727 Change Order No.: 005
INDIANA Department of Transportation Page: 2
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority AE: DCE: SCE: * DDCM:
($ per Change Order) (- LE $ 250K-) (- LE $ 750K -) (-- LE $ 2 M --
) (
Y
(Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) )( GT 200 SS
Verbal Approval Required?
Y / N If Y, by Date Issued
Total Change To-Date>5%?
Y / N If Y, Copy to Program Budget Manager
Scope/Design Recommendation
Required?
Y / N if Y, Referred to Project Manager(PM)
Date to PM Date Returned
Approval Authority Concurs with PM?
Y / N If Y, Concurrence by Date
If N, Resolution: Approved Disapproved
Resolved by Date
LPA Signatures Required?
Y / N If Y, Date to LPA Date Returned
FHWA Signatures Required?
Y / N If Y, Date to FHWA Date Returned
* Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer
Date
Comments:
Contract No:R -35727
Change Order No:005
Contract:
Project:
Change Order Nbr:
INDIANA
Department of Transportation
R -35727
1298579 - Stste:129857900LC
005
Change Order Description: Anchored Barrier Walt
Reason Code: CHANGED COND, Materials Related
CLN PCN PLN Item Code Unit Unit Price CO City 0253 1208679 0229 501.054of LFT 1 r Comment
Item Description: TEMPORARY TRAFFIC BARRIER TYPE 2 670 750,Og0 i
Supplemental Cosoriptlonl: Metal wall replacing concrete wall
Supplemental Descriplion2; using less anchors per lineal foot
Date: 11 /08/2016
Page: 3
Amount Change
Amounvs 11.752.50
Total Value for Change Order 006 = $11,752.50
Whomas, the Standard Specifications for this contract provides for such work to be performed, the following change Is recommended,
General or Standard Change Order Explanation
This is a metal barrier wall that uses only 4 anchors every 33 feet. This wall is replaces the concrete bather wall requiring 5 anchors eve
rael. This wall Is being placed an the north side of the Semple St Bridge Deck Into the newly poured Concrete binge deck. St Joseph County
requested the change using a will requiring less anchors per LFT to help extend the fife of the new bridge deck. N tart
Change Order Explanation for Speclflc Lino (torn
....,...,«.............. ...... ........................... ...... ..... ,............... «......... ,......... ,..........
,....
It is the intent of the parties that this change order is full and complete compensation for the work describe above.
NOt18catlon and consent to this change order is hereby acknowledged.
contractor_"? u - n�lr _
Signed
Date:_lI-iI —IIr, /
NOTE: Other required State and FHWA signatures will be obtained electronimily through the SlteManager system.
Contract No:R -35727 INDIANA
Change Order No:005 Department of Transportation
(SIGNATURE)
(SIGNATURE)
APPROVED FOR LOCAL PUBLIC AGENCY
APPROVtD _
(TITLE) �' of Pukla(�I WorrE)
(TITLE) 1(
'
SUBMITTED FOR CON
PENS J4�
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION
Approval Level Name of Approver Date
Date:11/08/2016
Status
Page: 4
TRUMnm
f00% Quality • 1007o Employee Owned • Over 100 Years
November 17, 2016
R-35727 Olive/Sample St. Reconstruction
Don Dietz -Project Engineer
Re: Anchored Barrier Wall Change Order Price
Please the following for the breakdown of the change to the metal barrier wail -
The original price included the following:
• Initial placement- includes hardware, anchor plates, and rental of wall - $15,795.00
• Reset Barrier Wall at Phase Change - includes hardware - $1,920
• Removal of Wall atjob completion-$3,225
• Temp CZ Units-$17,190.00 (That price was from Specialties - Can provide backup if necessary)
Total - $38,129 (for 700 lit)
Proposed Price includes -
• Initial Placement of Concrete Wall - $15,795.00
• Removal of Concrete Wall - $3,225
• Placement of Steel Zonegard Barrier Wall (includes, delivery, rental, hardware and anchors) - $12,891.50
• Deduct for reset of concrete in original price - ($1,920)
• Removal of Zonegard wall upon completion - $2,700
• Temp CZ Units-$17,190,00
Total - $49,881,50 (for 700 Ift)
Total Price Increase would be $11,752.50 ($16.79/Ift)
Let me know if you have questions.
Thanks,
D'- .o_ rRo
P.O. Box 1775 •25200 S.R. 23 •South Bend, IN 46834 � {
Phone: (574) 288.83P1 • www.rieth-riley.com
Date
Name
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
November 30, 2016
Roger Nawrot
Department Public Works
Division/Bureau Engineering
BPW Date December 13, 2016 Phone Extension 6932
Required Prior to Submittal to Board
Legal ❑ Attorney Name:
Controller ❑ Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ❑
Check the Appropriate Item Type — Required for All Submissions
❑ Agreement ❑ Contract ❑ Proposal ❑ Addendum
❑ Professional Services ❑ Resolution
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award
® Change Order No. 5 ❑ C/O & PCA No. ❑ PCA
❑ Ease/Encroach. ❑ Traffic Control:
F1 Other:
Company or Vendor Name
New Vendor
MBE/WBE Contractor
MBE/WBE Contractor Requested
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Amount of
Increase
Previous Amount
Current Percent of Change
New Amount
Total Percent of Chance:
Copy Original
® ❑
Required Information
Indiana Department of Transportation
❑ Yes ❑ No ❑ If Yes, Approved by
Purchasing
❑ MBE ❑ WBE
❑ No ❑Yes Name of Company
Olive Street and Sample Street Reconstruction
113-002
Major Moves
412-04 ,40542.03 y/ 1 - ay°!. y15 q2 .a3
$11,752.00
Federal 80%, City 10% & County 10%
This change order is for changing the temporary concrete barrier
wall on the new Sample Street westbound bridge to a metal
barrier wall so that the number of holes in the new bridge deck is
reduced from 300 to 60. City's share of the change order is
$1,175.20.
L Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
:ouired For Chance Orders Only
Nawrot
Fisher Associates