HomeMy WebLinkAboutChange Order No. 1 - Potawatomi Zoo Parking Lot Expansion Proj No. 115-129A - Ritschard Bros., Inc.1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND. INDIANA 46601-1830
CITY OF SOUTH BEND PETE BUTTIGIEG, MAYOR
BOARD OF PUBLIC WORKS
December 13, 2016
Donald Ritschard
Ritschard Bros., Inc.
1204 W Sample St.
South Bend, IN 46619
RE: Change Order No 1 - Potawatomi Zoo Parking Lot Expansion
Project No. I I5-129A
Dear Mr. Ritschard:
PHONE 574/235-9251
FAX 574/235-9171
The Board of Public Works, at its meeting held on December 13, 2016, approved the above
referenced Change Order for an increase of $9,381 plus twenty-two (22) days, bringing the
current contract amount to $113,622 and new completion date to December 7, 2016.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
t
Linda M. Martin, Clerk
Enclosure
c: Corbitt Kerr, Engineering
Rich Estes, Engineering
John Martinez, Parks
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK JAMEs A. MUELLER THERESE J. DORAU
"t QF
4�
CITY OF SOUTH BEND j
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE: 12-13-2016
PROJECT NO: 115-129A
PROJECT NAME: Potawatomi Zoo Parking Lot Expansion
CONTRACT DATE: 10-11-2016
CHANGE ORDER NO. 1
SUBJECT OF CHANGE ORDER: Cost of additional work. Time Extension for Delays
All items completed substantially as planned.
See attached Comparison of Estimate for overruns and underruns.
The original contract sum $ 104,241.00
Net change by previously authorized change orders $ 0.00
The contract sum prior to this change order $ 104,241.00
By this Change Order, the project amount is ® Increased
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
IV/V'ftA 2 r S C.1AAA
Printed Name and Title
Ritschard Bros., Inc.
Company name
1204 W. Sample St.
Address
South Bend, Indiana, 46619
City, State, Zip
❑ Decreased $ 9,381.00
$ 113,622.00
9.00 %
9.00 %
22 days
12-07-2016
RECOMMENDED FOR APPROVAL
-�
Project Manager
Gary
CITY OF SOUTH BEND
BOARD OF PUBLIC WORI
Approved Dates /a3' IV
L
Member
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Linda M. Martin, Clerk
Board of Public Works
FROM: Richard Estes, Engineer I
SUBJECT: Potawatomi Zoo Parking Lot Expansion
Change Order 1
Project No. 115-129A
DATE: December 13, 2016
Here is an explanation for the Change Order being submitted.
The reason(s) for the Change Order request is as follows:
During final preparation of the subbase for laying the asphalt pavement, the contractor
noticed that the original plan to mill down the existing asphalt drive was not possible due to
the significant elevation difference between what existed and what was proposed. The mill
would have been over 8 inches which would have gone beyond the depth of the existing
asphalt pavement. To correct this and still provide a method of drainage for the new
parking lot, the decision was made to raise the proposed elevations near the area of the
existing asphalt crown enough to allow for the mill to occur, while also providing a minimum
slope of 1 % to promote drainage of the parking lot. The cost for the work will be $9,381.00.
2. Also during this project, the contractor was forced to wait for AEP to relocate 2 existing light
poles that were in the location of the new parking lot expansion. This delay, along with the
additional time needed to perform the additional grading work, resulted in a time extension
request of twenty-two (22) calendar days from the originally scheduled completion date.
Please call me with your questions (5896).
Change Order No. 1
Potawatomi Zoo Parking Lot Expansion
Project No. 115-129A
OWNER: City of South Bend
ENGINEER: City of South Bend
CONTRACTOR: Ritschard Bros., Inc.
PROJECT: Potawatomi Zoo Parking Lot Expansion
SUBJECT: Change Order Number 1, Explanation of Costs and Extension
ISSUE DATE: December 13, 2016
This Change Order to the Contract document shall supplement, amend, and shall become a part of,
and be incorporated as an Addendum to the Contract.
The following is a summary and description of the revisions to the Contract by this Change Order:
During final preparation of the subbase for laying the asphalt pavement, the contractor noticed that the
original plan to mill down the existing asphalt drive was not possible due to the significant elevation
difference between what existed and what was proposed. The mill would have been over 8 inches
which would have gone beyond the depth of the existing asphalt pavement.
To correct this and still provide a method of drainage for the new parking lot, the decision was made to
raise the proposed elevations near the area of the existing asphalt crown enough to allow for the mill to
occur, while also providing a minimum slope of 1 % to promote drainage of the parking lot. This process
required additional labor and material that came to a total cost of $9,381.00
Also during this project, the contractor was forced to wait for AEP to relocate 2 existing light poles that
were in the location of the new parking lot expansion. This delay, along with the additional time needed
to perform the additional grading work, resulted in a time extension request of twenty-two (22) calendar
days from the originally scheduled completion date.
A copy of the contractor's justification of additional costs and time is attached to this document.
The following sections of the Contract Documents are revised as a result of the above changes:
BID/PROPOSAL:
Add Line Item No. 5: Est. City. 1 LS, "Additional Grading Material',
Unit Price of $9,381.00 LS, Total Cost: $9,381.00
END CHANGE ORDER 1
SHEET 1 OF 1
From: John Martinez
To: Rich Estes
Cc: Toy Vim; Patrick C. Kerr
Subject: RE: Potawatami Zoo Grades
Date: Thursday, November 17, 2016 10:10:27 AM
Rich. Thank you.
We will allocate $9,381 to cover this new item.
Please let me know if you need me to assist with a change order. Thank you- John
-----Original Message -----
From: Rich Estes
Sent: Thursday, November 17, 2016 8:21 AM
To: John Martinez
Cc: Toy Villa; Patrick C. Kerr
Subject: FW: Potawatami Zoo Grades
John,
I have good news and bad news.
Good news is that the contractor is just about ready to start paving at the zoo parking lot.
Bad news is that they ran into an issue with the crown of the existing driveway that prohibits them from putting in
the parking lot as originally designed. However, we were able to come up with a solution that would allow them to
adjust the proposed elevations within a small area of the new parking lot that would still promote drainage and not
raise the cost too significantly.
Attached is the proposal from Ritschard which shows an increase of $9,381.00 to account for additional material
needed. Please advise if we have the funds to do this work and I will forward to Don.
Thanks,
Richard Matthew Estes
Engineer
(574) 235-5896
restes@southbendin.gov
City of South Bend
227 W. Jefferson Blvd.
South Bend, IN 46601
Smart Streets South Bend link
-----Original Message -----
From: ritl204@datacruz.com Finailto7r0t1204Qdatacruz com]
Sent: Thursday, November 17, 2016 8:06 AM
To: Rich Estes <restes@southbendin.gov>
Subject: Potawatami Zoo Grades
Please see attached.
Don Ritschard
Ritschard Bros., Inc.
1204 W. Sample Street
South Bend, IN 46619
Phone574-288-4777
Fax 574-288-5438
RITSCHARD
BROS., INC.
EXCAVATING AND DEMOLITION
November 18, 2016
City of South Bend
1316 County -City Building
South Bend, IN 46601
Attention: Mr. Rich Estes
RE: Potawatomi Zoo Time Extension
Dear Rich:
We are requesting a contract time extension on the Potawatomi Zoo Parking Lot project.
We have been delayed two times on this project. The first delay was caused by AEP.
We had to wait to get utility poles moved. We also lost additional time revising grades to
make the parking lot drainage work due to unknown existing conditions. Our revised
completion date will be Wednesday, December 7.
If you have additional questions or we may be of further service, please call.
Sincerely,
3ARD BROS INC.
J. Rt , Jr.
1204 West Sample Street • South Bend, Indiana 46619 • PHONE (574) 288-4777 • FAX (574) 288-5438 • E-MAIL: ritl204@datacruz.com
i�
RITSCHARD
BROS., INC.
EXCAVATING AND DEMOLITION
November 17, 2016
City of South Bend
1316 County -City Building
South Bend, IN 46601
Attention: Mr. Rich Estes
RE: Additional Agg to Adjust Finished Grades
Dear Rich:
Our price to furnish and place #53 recycled concrete as required to adjust the elevations
to make the water drain over the crown is $9,381.00.
If we install storm drainage at the low point in lieu of raising the finished grades, our
price will be in the same ballpark, depending on how much storage capacity would need
to be added.
If you have any questions or we may be of further service, please call.
Sincerely,
1204 West Sample Street • South Bend, Indiana 46619 • PHONE (574) 288-4777 • FAX (574) 288-5438 • E-MAIL: ritl204@datacruz.com
Date 11/18/2016
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Department Public Works
Name Richard Estes Division/Bureau Engineering
BPW Date 12/13/2016 Phone Extension 5896
Required Prior to Submittal to Board
Legal ® Attorney Name: Michael Schmidt
Controller ❑ Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ® George King
Check the Appropriate Item Type — Required for All Submissions
Agreement ❑ Contract ❑ Proposal ❑Addendum
❑ Professional Services ❑ Resolution
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award
® Change Order No. 1 ❑ C/O & PCA No. ❑ PCA
❑ Ease/Encroach. ❑ Traffic Control:
n Other:
Company or Vendor Name
New Vendor
MBE/WBE Contractor
MBE/WBE Contractor Requested
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Amount of
Previous Amount
Ritschard B
Inc.
Parks Capital Improvements
$9,381.00
Reflects additional required material to overcome the crown of
the existing drive so that the new parking lot expansion will
properly drain, as well as addressing delays caused by existing
utilities and adjustments to the grading plan
LJ Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
Increase $ 9,381
Decrease $
W1111
and an additional 22 calendar
® ❑ Patrick C. Kerr
® ❑ Don Ritschard (Ritschard Bros)
® ❑ John Martinez