HomeMy WebLinkAboutChange Order No. 1 - JMS Building New North Stair Tower Proj No. 116-098 - HGR Group, Inc.1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND. INDIANA 46601-1830
CITY OF SOUTH BEND PETE BUTTIGIEG, MAYOR
BOARD OF PUBLIC WORKS
Ty Heckaman
HGR Group, Inc.
132 Churchill Drive
South Bend, IN 46617
RE: Change Order No. 1
Project No. 116-098
Dear Mr. Heckaman:
December 13, 2016
- JMS Building New North Stair Tower
PHONE 574/235-9251
FAX 574/235-9171
The Board of Public Works, at its meeting held on December 13, 2016, approved the above
referenced Change Order for an increase of fourteen (14) calendar days, bringing the current
project completion date to January 6, 2017.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely, 1 //
Linda M. Martin, Clerk
Enclosure
c: Rich Estes, Engineering
Corbitt Kerr, Engineering
GARY A. GILGT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK JAMEs A. MUELLER THERESE J. DGRAU
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE: 12-13-2016
PROJECT NO: 116-098
PROJECT NAME: The JMS Building New North Stair
Tower
CONTRACT DATE: 10-25-2016
CHANGE ORDER NO. 1
SUBJECT OF CHANGE ORDER: Time Extension See attached explanation
of work
All items completed substantially as planned.
See attached Comparison of Estimate for overruns and underruns
The original contract sum
$ 497,097.00
Net change by previously authorized change orders
$ 0.00
The contract sum prior to this change order
$ 497,097.00
By this Change Order, the project amount is ❑ Increased
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
CONTRACTOR
Co- 'actor Signature
T 111,,44�d►n o;400-
rinted Name and Title
HGR Group, Inc.
Company name
1932 Churchill Drive
Address
South Bend, Indiana, 46617
City, State, Zip
❑ Decreased $ 0.00
$ 497,097.00
0.00 %
0.00 %
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
Approved Date: /d1/ 3/,,2U j,
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Linda M. Martin, Clerk
Board of Public Works
FROM: Richard Estes, Engineer I
SUBJECT: The JMS Building New North Stair Tower
Time Extension
Project No. 116-098
DATE: December 13, 2016
Here is an explanation for the Change Order being submitted.
The reason(s) for the Change Order request is as follows:
After the bid had been awarded, the steel fabricator informed HGR Group that the materials that were
supposed to be ready for them to use on December 61h have been delayed to being completed on
December 13th. The contractor is also claiming that due to the time between opening and awarding the
contract as well as the time taken to set up the pre -construction conference they have lost 8 working
days.
HGR Group Inc. is requesting a total time extension of 14 calendar days be added to the contract due
to delays caused by the aforementioned delays. A copy of the HGR Group letter requesting additional
time is attached.
The initially defined intermediate completion date was set at December 23, 2016. This extension would
set the intermediate completion date at January 6, 2017. The reasoning behind the initially defined
intermediate completion date was to ensure that the occupancy permit was obtained for the site owner.
Since the award of this bid, the site owner has explained that the occupancy permit deadline can be
extended to accommodate the proposed schedule by the contractor. Their written approval of the
extension can be found attached to this change order.
Please call me with your questions (5896).
Change Order No.1
The JMS Building New North Stair Tower
Project No. 116-098
OWNER: City of South Bend
ENGINEER: Hebard & Hebard Architects
CONTRACTOR: HGR Group Inc.
PROJECT: The JMS Building New North Stair Tower
SUBJECT: Change Order Number 1, Explanation of Time
ISSUE DATE: December 13, 2016
This Change Order to the Contract document shall supplement, amend, and shall become a part of,
and be incorporated as an Addendum to the Contract.
The following is a summary of events and a description of the revisions to the Contract by this Change
Order:
After the bid had been awarded, the steel fabricator informed HGR Group that the materials that were
supposed to be ready for them to use on December 6'h have been delayed to being completed on
December 13th. The contractor is also claiming that due to the time between opening and awarding the
contract as well as the time taken to set up the pre -construction conference they have lost 8 working
days.
HGR Group Inc. is requesting a total time extension of 14 calendar days be added to the contract due
to delays caused by the aforementioned delays. A copy of the HGR Group letter requesting additional
time is attached.
The initially defined intermediate completion date was set at December 23, 2016. This extension would
set the intermediate completion date at January 6, 2017. The reasoning behind the initially defined
intermediate completion date was to ensure that the occupancy permit was obtained for the site owner.
Since the award of this bid, the site owner has explained that the occupancy permit deadline can be
extended to accommodate the proposed schedule by the contractor. Their written approval of the
extension can be found attached to this change order.
The following sections of the Contract Documents are revised as a result of the above changes:
XIII. PROSECUTION AND PROGRESS
Revise the following:
Intermediate completion date of DeeemleeF 23, 2016 January 6, 2017 for obtaining a Certificate of
Occupancy to utilize the Stair from the Authority Having Jurisdiction.
END CHANGE ORDER 1
SHEET 1 OF 1
Construction Services
11-21-16
Re: Finish date extension
Mr. Estes,
We are requesting an extension of the completion date, for the Stair Tower project, at the
JMS Building.
We request it be extended from December 23rd 2016 to January 6th 2017.
The steel fabricator has indicated to us, that they can not have the steel stairs to us by the
original scheduled install date of December 6th. They believe they can have it onsite on
December 13th. We will lose 6 working days (Saturday included)
Another reason is that we lost some time between the board approval and the pre-
constrcution meeting. Since we were not allowed to start until we had our pre -con
meeting, it cost us 8 working days. (Saturday's included)
We will lose a total of 14 working days (Saturdays included), before the steel stairs even
arrive onsite.
We are working 10 hour days 6 days a week to meet the schedule. But, believe we will fall
short on meeting the December 23rd completion day, due to the reason mentioned above.
Thank you for your time
Ty Heckaman
HGR Construction Services
From: Matt Powell
To: Rich Estes
Subject: RE: Stair tower schedule extension
Date: Monday, November 21, 2016 3:59:58 PM
Yes, the time extension is approved.
Matt Powell + Director of Operations
Off: 574-968-9287 Cell: 574-780-1690
mpowellnp greltlakescapital com
From: Rich Estes [mailto:restes@southbendin.gov]
Sent: Monday, November 21, 2016 3:42 PM
To: Matt Powell <mpowell@greatlakescapital.com>
Subject: FW: Stair tower schedule extension
Matt,
Please confirm that you approve of the time extension request attached, which is the same as what
we discussed during the pre -construction meeting. If you have any additional concerns, please let
me know.
Thank you,
Richard Matthew Estes
Engineer 1
(574) 235-5896
restesPsouthber in.eov
City of South Bend
227 W. Jefferson Blvd
South Bend, IN 46601
Smart Streets South Bend link
From: Ty Heckaman [Mailto7theckaman(@hgrg[Qupinc.com
Sent: Monday, November 21, 2016 12:31 PM
To: Rich Estes <restes(a)southbend in gov>
Subject: Stair tower schedule extension
Rich,
Please see attached request.
Ty Heekaman
HGR Construction Services
Executive Director/General Manager
(574)220-7371
theckaman(@hgrgroupinc.com
Date 12/6/2016
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Department Public Works
Name Richard Estes Division/Bureau Engineering
BPW Date 12/13/2016 Phone Extension 5896
Required Prior to Submittal to Board
Legal ® Attorney Name: Michael Schmidt
Controller ❑ Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ® George King
Check the Appropriate Item Type — Required for All Submissions
Professional Services
Bid Opening
Quote Opening
Change Order No. 1
Ease/Encroach.
Other:
❑ Resolution
❑ Bid Award
❑ Quote Award
❑ C/O & PCA No.
❑ Traffic Control:
Company or Vendor Name HGR
New Vendor —�
MBE/WBE Contractor —TM_
MBE/WBE Contractor Requested ❑ N,
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Amount of
:) Inc.
No M If
Yes
rIF
324-1050-460-3102
❑ Req. to Advertise
❑ PCA
Stair T
Addendum
❑ Title Sheet
L;nange orcer to reflect delay claims of 14 calendar days
U Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
Increase Add 14
Decrease $
Previous Completion Date
Current Percent of Change:
New Completion Date
Total Percent of
Copy
Origina
®
❑
®
❑
®
7
12/23/2016
01 /06/2017
Patrick C. Kerr
Matt Douhan