BIDS OPENED - CLEVELAND ROAD SEWER
This being the date set for receiving bids for the construction of approximately
700 linear feet of 21 inch vitrified clay sewer on Cleveland Road, the Clerk
tendered proofs of publication of notice in the South Bend Tribune and the
Tri County News on June 19 and June 26, 1970, which were read.and found to be
proper. The following bids were received:
Cowles Construction Company, Elkhart, Indiana. Non collusion affidavit was
found to be proper. The bid was accompanied by a bid bond of 5% of the bid.
Financial statement of bidder (Form 96-a) being on file in the office of the
Board of Public Works and Safety. Total bid - $14,924.00. Completion time
90 days.
Dye Plumbing and Heating, 712 Madison Street, LaPorte, Indiana. Non collusion
affidavit was found to be proper. Bid was accompanied by a bid bond of 5% of
the bid, together with financial statement of bidders (Form 96-a). Total
bid - $18,707.00. Completion time 60 days.
Haskins, Inc., 64704 U.S. #31, Lakeville, Indiana, 46536. Non collusion affi-
davit was found to be proper. Bid was accompanied by a bank draft in the
amount of $800.00, together with financial statement of bidders (Form 96-a).
Total bid $15,396.00.
Woodruff Sons, Inc., P. 0. Box 315, Michigan City, Indiana, 46360. Non
collusion affidavit was found to be proper. The bid was accompanied by a bid
bond of 5% of the bid. Total bid - $14,606.00. Completion time 20 days.
NO BIDS RECEIVED - THREE -WHEEL MOTORCYCLES
This being he date set for receiving bids for four (more or less) three
wheel motorcycles for the Police Department, the Clerk tendered proofs of
publication of notice in the South Bend Tribune and the Tri County News, which
were read and found to be proper.
No bids having been received, it was moved, seconded and unanimously carried
that the Police Department be authorized to seek quotations on the open market
for four (more -or less) three -wheel motorcycles.
NO BIDS RECEIVED - RADIOS FOR THREE -WHEEL MOTORCYCLES
This being the date set for receiving bids for four (more or less) radios
for three -wheel motorcycles for the Police Department, proofs of publication
of notice in the South Bend Tribune and the Tri County News on June 26 and
July 3, 1970, having been read and found sufficient, and no bids having
been received, it was moved, seconded and unanimously carried that the Police
Department be authorized to seek quotations on the open market for four (more
or less) radios for three wheel motorcycles.
F1.RE DEPARTMENT - RESIGNATION OF RICHARD L. HEIDRICH
Upon motion made, seconded and unanimously carried, the Board accepted and
approved the resignation of Richard L. Heidrich from the South Bend Fire De-
partment effective July 5, 1970.
POLICE DEPARTMENT - EXCUSED FOR MILITARY DUTY
Upon motion made, seconded and unanimously carried, upon the.approval of
Chief of Police Loren M. Bussert, the Board approved the requests of officers
Robert L. Lanchsweerdt and Ernest Nybo to be excused for military duty at Camp
McCoy, Wisconsin, from July 11 to July 25, 1970.
POLICE DEPARTMENT - APPLICATIONS FOR APPOINTMENT
The applications of Dennis Paul Graber and Leonard Michael Grummell for appoint-
ment to the South Bend Police Department were filed with the Board and referred
to the Personnel Director for further processing.
1
HEARING ON ASSESSMENT ROLL - VACATION RESOLUTION NO. 3314 - SOUTH BEND RANGE CORP.
7/6/70
This being the date set, hearing was held on the assessment roll in Vacation
Resolution No. 3314, being for the vacation of:
Part of Napier Street, located immediately south of and ad-
jacent to Lot 32 as shown in John F. Kirby's Subdivision of
Bank Out Lot 83; and a part of Cherry Street, beginning at
the northwest corner of Lot 37 of John F. Kirby's Subdivision
of Bank Out Lot 83; thence. north to the northwest corner of
Lot 29; thence west to the west line of Cherry Street; thence
south along the west line of Cherry Street to a point directly
west of the northwest corner of Lot 37; thence east to the
point of beginning.
Proofs of publication of notice in the South Bend Tribune and the Tri County
News on June 12, June 19 and June 26, 1970, were read and found to be
sufficient. No remonstrators having appeared and no written remonstrances
having been filed, upon motion made, seconded and unanimously carried, the
assessment roll was adopted as presented and the Vacation Resolution in all
things .confirmed and ratified and the proceedings concluded.
X9 HEARING ON VACATION RESOLUTION NO. 3317 - MILL RACE, INC. (30 FT. EASEMENT)
Hearing on Vacation Resolution No. 3317 for the vacation of an easement
described as that part of the west leg of the East Race which is located
northerly of a line parallel to and 30 feet southerly of the southerly line
of Hydraulic Avenue and located westerly of the west line of the East Race,
which said west leg of the East Race is the -Race located on the southeasterly
and east sides of Hydraulic Avenue in Section 1 and in Section 12, Township
37 north, Range 2 east, in the city of South Bend, Indiana, having been
continued from June 29, lg70, and the drainage problem having been now
resolved, upon motion made, seconded and unanimously carried, the adoption of
Vacation Resolution No. 3317 on May 25, 1970, is ratified and confirmed.
And the City/Engineer,is directed to prepare an assessment roll showing the assess-
ment of benefits and damages to the surrounding property.
Attorney Bruce Stewart attended the meeting.
ASSESSMENT ROLL FILED - VACATION RESOLUTION NO. 3308 - DONALD F. HICKEY
Lloyd S. Taylor, City Engineer, files assessment roll showing award of
damages:.: and assessment of benefits in the matter of the vacation of:
The north -south alley lying between Lots 2 and 4 in Chapin's
Subdivision of Bank Out Lot 182, and running south from the
south line of Lincolnway blest to the southeast corner of Lot 2
and the southwest corner of Lot 4 in Chapin's Subdivision.
The followin7 property may be injuriously or beneficially affected by such
vacation: ,
Lots.I to 11, inclusive, in Chapin's Subdivision of Bank Out
Lot 182 and lots 13, 14, 15, 16, 17 in Rebecca Studebaker's
Subdivision, and a parcel of land lying west and adjacent to
Lots 1 and 3 in Chapin's Subdivision of Bank Out Lot 182 and
running from Lincolnway west to LaSalle Avenue.
Net benefits
Net damages
$00.00
$00.00
August 3, 1970, at ?:30 A.M., is set as the time for hearing and>receiv=i.-
1ng remonstrances from all persons interested in or affected by such
vacation. And the Clerk is directed to give notice of such hearing by
publication in the South Bend Tribune and the Tri County News on July 10,
July 17 and July 24, 1970.
PETITION FILED - TO VACATE IVY ROAD, SOUTH BEND AVENUE TO EDISON ROAD -
NOTRE DAME UNIVERSITY AND STANLEY PIETZAK
Attorney Irving Smith, on behalf of the University of Notre Dame and Stanley
and Patricia Pietzak, 302 Ostemo Place, South Bend, Indiana, filed a petition
to vacate Ivy Road, from South Bend Avenue to Edison Road. Upon motion made,
seconded and carried, the petition was referred to the City Engineer for
drawing of the area and referrat to Area Plan Commission for study and
recommendation to the Board.
:'
7/6/70
CONTRACT WITH ARCHITECT SIGNED - DRAINAGE FACILITIES AND STREET IMPROVEMENT
CHIPPEWA AT MAIN
Upon motion made, seconded and unanimously carried, the Board approved and
executed an agreement (Form 97-A of the Indiana State`Board of Accounts)
with Engineering Planning Services, 'Inc., consulting engineers, 1520 N. Main
Street, Mishawaka, Indiana, for professional services in the matter of the
construction of drainage facilities and street improvement on Chippewa Avenue
at Main Street, in the city of South Bend, Indiana.
POTAWATOMI PARK DISPLAY BARN
Upon motion made, seconded and carried, the matter of -awarding contract for
construction of a display barn for Potawatomi Park was further continued one
week.
COMMUNICATION FROM CITY ENGINEER
A copy of report of the City Engineer under date of June 26, 1970, to members
of the Common Council in reference to street paving was ordered filed.
INDIANA.'; DELUXE CAB 4CORP. - APPLICATION FOR -CERTIFICATE OF PUBLIC CONVENIENCE
AND NECESSITY
Application for certificate of public convenience and necessity for the operation
of taxicabs for hire on the Streets of South Bend, Indiana, was filed with the
Board and, upon motion made, seconded and carried, referred to the City Con-
troller for review and recommendation.
INDIANA CRIMINAL JUSTICE AGENCY - IN -KIND RENT FOR JUNE, 1970
Indiana Criminal Justice Agency reports in -kind rent of $150.00 for the month of
June; 1970, for 1427 County City Building (exchanged for Stowe -Davis executive
desk and chair to the office of the Deputy Controller).
REQUEST - TO MOVE PORTABLE SCHOOL UNITS - LEWIS MITCHLEN
Lewis Mitchlen appeared before the Board and requested permission to move three
portable school units (from Jefferson School to Clay, Franklin to Hamilton and
Linden School to Hamilton). Upon motion made, seconded and unanimously
carried, permission was granted for the moving of such portable school units
over the city streets on condition that the routing be worked out with the
Traffic Director.
REQUEST TO CLOSE CHAPIN STREET FOR ST. ANNE FESTIVAL
Upon motion made, seconded and unanimously carried, the Board approved the
request of Mrs. Thomas Arch, 823 Sherrill Street, South Bend, Indiana for Chapin
Street, from Calvert Street to Bruce Street, to be closed between the hours of
3:00 P.M. and 10:00 P.M., on July 18, 1970, during the annual St. Anne festival
of the Our Lady of Hungary Church, providing proper insurance to hold the City
harmless is obtained.
REQUEST TO HOLD PARADE (1971) - SOUTH BEND SHRINE CLUB, INC.
Upon motion made, seconded and unanimously carried, the Board approved the re—
quest of John R. Kagel for the South Bend Shrine Club, Inc., 107 Lincolnway East,
South Bend, Indiana, to hold a hold a Shrine parade in the downtown area of
South Bend on Saturday, June 26, 1971.
REQUEST TO BLOCK MAIN STREET - FIRST CHRISTIAN CHURCH
Upon motion;made,'seconded and unanimously carried, the Board approved the re-
quest of Frank W. Edgerton for the First Christian Church, 320 S. Main Street,
South Bend, Indiana, for permission to block South Main Street, between Wayne
Street and Western Avenue, on Sunday, July 12, 197.0, between the hours of 8:30
A.M. and 10:00 A.M., in connection with the march of the congregation to their
new Church location at 1101 E. Jefferson Boulevard and granted permission for
northbound traffic within the block during this time.
n
7/6/70
PETITION FOR STREET LIGHT - 800 BLOCK DUBAIL
A petition for a street light in the 800'block of East Dubai] Avenue was
filed by Winthrop Sharp, 317 E. Dubai] Avenue, South Bend, Indiana and 10
others, and, upon motion made, seconded and carried, was referred to the
Traffic Engineering Department for study and recommendation.
STREET LIGHTING APPROVED
Upon motion made, seconded and unanimously carried, the Board approved
.the .recommendation of the Traffic Engineering Department for street lighting
as follows:
Area bounded by Logan, Mishawaka, 30th and Jefferson:
Install 32
7,0001-
MV OH WP
15
7,0001-
MV OH WP
2
20,0001-
MV OH WP
Remove 29
4,0001-
INC OH WP
2
4,0001-
INC OH WP
1
2,500L
INC OH WP
1
1,000L
INC OH WP
at a cost of
$1,126.20
per year.
6�1
Area bounded by Ford, Kentucky, Sample and Illinois:
Install 22 7,0001- MV OH WP
13 7,0001- MV OH WP
�v Remove 19 4,0001- INC OH WP
3 4,0001- INC OH WIP
at a cost of $802.80 per year.
1
r
CONTRACTOR'S BOND CANCELLED
Upon motion made, seconded and carried, the request of United States Fidelity
and Guaranty Company for cancellation of contractor's bond #69014-11-580-69
for Ten-M Builders was approved by the Board for any and all work done by
Ten-i•", Builders on and after August 26, 1970.
CONTRACTORS' BONDS APPROVED
Upon motion made, seconded and unanimously carried, the following contractors'
bonds were approved:
Edward Bennett, d/b/a Penn Construction Co. - to 6/19/71.
South Bend Christian Reformed Church - to 6/26/71.
STREET LIGHT OUTAGE REPORTS
Street light outage reports for the period 6/23/70 to 7/1/70 were ordered filed.
There being no further business to come before the Board, the meeting ad-
iourned at 10:40 A.M.
ATTEST:
���-