HomeMy WebLinkAboutChange Order No 9 - South Bend One Way to Two Way Conversion Proj No 116-001- - Rieth Riley Construction1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND. INDIANA 46601-1830
CITY OF SOUTH BEND PETE BUTTIGIEG, MAYOR
BOARD OF PUBLIC WORKS
November 22, 2016
Scott Kirkpatrick
Rieth-Riley Construction Co., Inc.
25200 State Road 23
South Bend, IN 46614
PHONE 574/235-9251
FAx 574/235-9171
RE: Change Order No. 9 — South Bend One -Way to Two -Way Conversion, Division B
Project No. 116-001
Dear Mr. Kirkpatrick:
The Board of Public Works, at its meeting held on November 22, 2016, approved the above
referenced Change Order for an intermediate completion time adjustment of eight (8) days,
revising the current intermediate completion date to November 23, 2016.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
c: Michael Divita, Community Investment
Toy Villa, Engineering
Beth Leonard, Community Investment
Judy Love, Community Investment
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK JAMES A. MUELLER THERESE J. DORAU
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
11 /16/2016
116-001 DIV B
CHANGE ORDER NO:
SUBJECT OF CHANGE ORDER:
116-001 South Bend One-way to Two-way Conversion
2/26/2016
9
PCR #9-Saint Joseph Street Intermidiate Completion Time
Extension (chanqe order 34)
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
❑ Increased
❑ Decreased
$ 1,174,552.37
$ 17,306,460.73
Mgt]
17,306,460.73
0.00 %
7.28 %
Original contracted completion date/time 6/1/2017
Extension of date/time by previous change orders 0 days
Date/time extension by this change order 0 days
New completion date/time 6/1/2017
�j CONTRACTOR RECOMMENDED FOR APPROVAL
Contractor Signat e
Printed Name and Title
Rieth-Riley Construction CO. INC.
Company Name
25200 State Road 23
Address
South Bend, Indiana, 46614
City, State, Zip
CONST TION MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC
Approved Dale: ///
Gary A. Gilot, President
U) 41--
Suzanna P. Fritzber , Membe
Elizabeth A Maradik, Member
Therese J. Do au, P16mber
James A. Mueller, Member
Change Order No. 34
One- Way to Two -Way Street Conversion
Division B
Project No. 116-001
OWNER: City of South Bend
ENGINEER: Lochmueller Group, Inc.
Myron Cohagan
CONTRACTOR: Rieth-Riley Construction
PROJECT: South Bend One -Way to Two -Way Street Conversion, Division B
Project No. 116-001
SUBJECT: Saint Joe Street Time Extension
ISSUE DATE: November 7, 2016
This Change Order to the Contract document shall supplement, amend, and shall become a part of,
and be incorporated as an Addendum to the Contract.
SPECIFICATIONS:
The following special provisions have been amended or added to the Contract Documents and are
issued as a part of this Change Order:
XIV PROSECUTION AND PROGRESS
A. Prevailing Specifications: 2016, INDOT Standard Specifications Sec. 108
B. Additions:
1. The project, both Division A and Division B, will have a completion date of June 1, 2017.
The contract time will start when the Notice to Proceed is delivered and signed.
2. The project will have intermediate completion dates as listed in the table below for roads
open to bi-directional traffic and traffic control devices shall be functioning at all
intersections on Saint Joe/Michigan with the exception of Washington, Jefferson
and South Street and on Main with the exception of Bronson. The intersections of
Saint Joe/ Michigan .-nd .lefferson, W-3hington and South along with Main and
Bronson will folio, This includes all travel and parking lane
asphalt and concrete work, structures, curb and permanent pavement markings complete
and in place. This wouk:i iJoseph
Street that could not be .,,arn _ �c r�s ,� _ �,, N .,.!, pie street
lighting on Saint Joe from Wayne to LaSalle needs to be functioning on the west
side of the street by December 16, 2016. With the east side being completed by the
December 25, 2016.
Change Order No. 34
One- Way to Two -Way Street Conversion
Division B
Proiect No. 116-001
Roadway
Intermediate Completion Date
Intersection of Main Street and Chippewa
September 7,
2016
Avenue
Main Street between Chippewa Avenue and
September 7,
2016
Sample Street and between LaSalle Street and
Marion Street
Intersection of Michigan Street and Chippewa
September 7,
2016
Avenue
Michigan Street between Chippewa Avenue
September 7,
2016
and Sample Street and between LaSalle Street
and Angela Blvd.
Main Street between Sample Street and
_October 15, 2016
LaSalle Avenue
St Joseph/Michigan Street between Sample
November 23,
2016
Street and LaSalle Avenue
a. A minimum of one travel lane in each direction on each corridor street shall be open
to traffic on or before the specified date. Once bi-directional traffic is established on
each corridor street, bi-directional traffic shall be maintained on each corridor street
for the duration of the project.
b. A minimum of one travel lane shall be open to traffic during construction except
whereas noted in the full closure construction period.
c. Two (2) northbound travel lanes must be open for the duration of Saturdays on which
there is a home Notre Dame football game. This can be achieved either through two
(2) northbound travel lanes on Michigan/St. Joseph or one (1) northbound travel lane
on both Michigan/St. Joseph and Main St. after Main St. has been converted to bi-
directional traffic. The dates of concern are provided below. (REVISED)
(i) September 10th, 2016
(ii) September 17th, 2016
(iii) September 24'h, 2016
(iv) October 15th, 2016
(v) October 29th, 2016
(vi) November 12th, 2016
(vii) November 19th, 2016
d. The Contractor shall coordinate maintenance of traffic with the City for any sidewalk,
streetscape, trees, pavers, and/or landscaping activities following the intermediate
completion date for any subsequent work. Road closures will o lowed where
the City deems it necessary.
Change Order No. 34
One- Way to Two -Way Street Conversion
Division B
Project No. 116-001
2. The table below lists the dates by which the identified roads shall be available to begin full
closure and the intermediate completion dates for full road closure.
Roadway
Starting Date for Full
Intermediate
Completion Date for
Closure
Full Road Closure
Intersection of Michigan Street and
June 6, 2016
August 5, 2016
Chippewa Avenue
Intersection of Michigan Street and
Mav 17, 2016
September 7, 2016
Bartlett Street
Intersection of Michigan Street and
May 17, 2016
September 7, 2016
Marion Street
a. The identified roads shall not be closed before the starting date and shall maintain a
minimum of two travel lanes prior to such date.
b. The work specified shall be arranged and prosecuted such that these roads are open
to traffic on or before the specified intermediate completion date.
3. The City, Engineer, and Contractor will hold a pre -construction meeting following award
of the contract. The date of the Notice to Proceed will be agreed upon at that meeting.
DRAWINGS:
The following sheets have been revised or issued as new sheets.
END OF CHANGE ORDER NO. 34
OWNER: City of South Bend
Signature
Date
CONTRACTOR: Rieth-Riley Construction
Signature
//// 7 //%
Date
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 11/17/16
Name
Toy Villa
Department
Engineering
BPW Date
11/22/16
Phone Extension
5920
Required Prior to Submittal to Board
Legal ® Attorney Name Michael Schmidt
Controller ❑ Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ❑
Check the Appropriate Item Type — Required for All Submissions
❑ Agreement ❑ Contract ❑ Proposal ❑ Addendum
❑ Professional Services ❑ Resolution
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award
® Change Order No. 9 ❑ C/O & PCA No. ❑ PCA
❑ Ease/Encroach. ❑ Traffic Control
❑ Other:
Company or Vendor Name
New Vendor
MBE/WBE Contractor
MBE/WBE Contractor
Requested
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Required Information
Reith Riley Construction Co., Inc.
❑ Yes ® No ❑ If Yes, Ap
7—MBE I I WBE
L_J No L j Yes Name of Company
South Bend One Way to Two Way Conversion — Division B
2015 TIF Bond
Approval of Change Order #9 — Time Extension
❑ Required Contractor's Certification Form Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.
Required For Chanqe Orders Onlv
Amount of ❑ Increase
❑ Decrease
Previous Amount
Current Percent of Change:
New Amount
Total Percent of Change:
Copy
Original
®
❑
tv.
Michael Divita
Toy Villa
Beth Leonard, Judy Love
Approva