HomeMy WebLinkAboutChange Order No 1 - Wastewater Treatment Plant Grit Screenings & Improvements Proj No. 114-075 - Thieneman Construction Inc1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND. INDIANA 46601-1830
CITY OF SOUTH BEND PETE BUTTIGIEG, MAYOR
BOARD OF PUBLIC WORKS
November 22, 2016
Matt McCoy
Thieneman Construction, Inc.
521 W 84`h Drive, Suite A
Merrillville, IN 46410
PHONE 574/235-9251
FAx 574/235-9171
RE: Change Order No. 1 — Wastewater Treatment Plant Grit Screenings and
Improvements
Project No. 114-075
Dear Mr. McCoy:
The Board of Public Works, at its meeting held on November 22, 2016, approved the above
referenced Change Order for an increase of $2,597.84, bringing the current contract amount
to $1,148,597.84.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
c: Al Greek, Environmental Services
Jacob Klosinski, Environmental Services
Carol Kurzhal, Environmental Services
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK JAMES A. MUELLER THERESE J. DORAU
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO.
SUBJECT OF CHANGE ORDER:
All items completed substantially as
See attached Comparison of Estimate for overruns and underruns
The original contract sum $ 1,146,000.00
Net change by previously authorized change orders $ 0,00
The contract sum prior to this change order $ 1,146,000.00
By this Change Order, the project amount is ® Increased
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
❑ Decreased $ 2,597.84
$ 1,148,597.84
+0.23 %
+0.23 %
Original contracted completion date/time 10/10/2016 (Substantial Completion)
11/9/2016 (Final Completion)
Extension of date/time by previous change orders 0 days for Substantial Completion 0 days
for Final Completion
Date/time extension by this change order None
New completion date/time 10/10/2016 (Substantial Completion)
11/09/2016 (Final Completion)
RECOMMENDED FOR APPROVAL
CONTRACTOR
Contractor Signature
Matt McCoy, Project Manager
Printed Name and Title
Thieneman Construction, Inc.
Company name
521 W 84th Drive, Suite A
Address
Merrillville, Indiana 46410
UP
i onstructlOn Manager
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
Approvgd Date:
Gary A. Gilot, President
James A. Mueller, Member
Suzanna itzberg, ember �;F
City, State, Zip Elizabeth A. Maradik, Member
Therese J. Dorau, mb
SOUTH BEND GRIT AND SCREENINGS IMPROVEMENTS
To: Thieneman Construction, Inc. Work Directive Change No.: _ 01
521 W 84"' Dr., Suite A Includes PCO 1 2, 3, 4, 55
Merrillville, IN 46410---- =�-
Date: September20,2016
114-075 South Bend WWTP
Attn: Mr. Matt McCoy Project Name: Grit & Screenings
Specification Section: N/A
o imp vements Project
Drawing Reference: NIA
ITEM
1 Replacement of expanded metal viewing windows with gas tight hatches for the two (2) grit washers,
Work shall be completed for the amount of $3,268.30 as indicated in the attached PCO #001 revised
and provided by the Contractor on September 19, 2016,
2 Installation of three (3) new valves, piping, and insulation in the basement pump room to isolate
sections of the spray loop, Work shall be completed at no additional cost in exchange for deletion of
the crane testing and inspection requirement in the specifications as indicated in the attached PCO
#002 provided by the Contractor on August 8, 2016.
3 Building SCADA screens in house as opposed to on site. Work will result in a contract savings of
$3.926.22 as indicated in the attached PCO 4003 revised and provided by the Contractor on
September 19, 2016.
4 Sand blasting and coating of black iron pipe loops submerged in the East and West tanks, Work
shall be completed for the amount of $2,344.65 as indicated in the attached PCO #004 revised and
provided by the Contractor on September 19, 2016.
5 Reconfiguration of spray loops fabricated for the East and West tanks. Work shall be completed for
the amount of $911.11 as indicated in the attached PCO #005 revised and provided by the
Contractor on September 19, 2016.
REASON FOR THIS WORK DIRECTIVE CHANGE: Revisions described above will serve the intended
purpose of the project better by ensuring most efficient use of resources.
AUTHORIZATION: This Work Directive Change authorizes the work to be completed as outlined above.
PROJECT COMPLETION DATES: Add Zero 0 Days.
Recommended By: r✓ ;` - - 9 2 i j 6
PPr ject i 4wfger (Greeley and Hansen) Date
Approved By: S%4eSs� %sI• �i�I �*f 09 - 22 •ZD I fe
C�Assistant City Engineer (City of South Bend, IN) Date
WWI
TH I EI �- M,AN
LOtISIfl UCl10.4,INC.
September 20, 2016
Greeley and Hansen
7820 Innovation Blvd. Suite 150
Indianapolis, IN 46278
Attn: Mr. Trent Montemayor
Subj: South Bend Grit and Screenings
Proposed Change Order#1 RI
Mr. Montemayor:
In accordance with G & H Request for Proposal #l, Thieneman Construction, Inc. will
furnish the two grit separators with gas tight hatches. Please incorporate COR#1 RI for the
amount of Three Thousand Two Hundred Sixty Eight Dollars and Thirty
Cents ($3,268.30) when a formal change order is issued. Feel free to contact me with
any questions.
Respectfully,
Matt McCoy
Project Manager
Cc: Field, File, Accounting
INDUSTRIAL • MUNICIPAL CONTRACTOR
521 W. 8411i Dr. • Suite A . Merrillville, IN 46410 • 219-947-4700 • Fax 219-947-4711
17219 Foundation Pkwy a Westfield, IN 46074 •317-867-3462 • Fax 317-867-3463
Contractor's / Subcontractor's
TfnUcMMAN
Change Order Request Summary
Date: 9/19/2016 COR: 1 RI
General Contractor 521 W. 84th Drive
Suite A, Merrillville, IN 46410, 219-947-4700 phone/ 219-947-4711 fax
Engineer: Greeley and Hansen
Owner: City of 5cuth Bend
Project: South Bend Grit and Screenings
Improvements
_ _
TCI Job# 1511
_ _
DESCRIPTION OF CHANGE- —.---,—.—,---
_.—,—.— ------___,_._._._.—.-- _.___._._
In accordance with Greeley and Hansen Request for Change Order Proposal ffi dated April 25, 2016, TO offers the following
the expanded metal viewing windows with gas tight hatches for the two (2) grit washers.
SUMMARY OF DETAILED BREAKDOWN
LABOR
MATERIAL
EQUIPMENT
OTHER COSTS
1. SAFETY
2. EXPENDABLE TOOLS
NETTOTAL
OVERHEAD AND PROFIT
TOTAL WORK PERFORMED BY CONTRACTOR
Additions
Deletions
Net Total
$ 2,800.00
$ -
$
2,800.00
(1%of LABOR-Deletion-0-
$
-
(3.0%of LABOR)-Deletion-0-
$
-
(A+B+C+D1+D2)
$
2,800.00
(Ex1S%)- Deletion -0.
$
420.00
(Lines E+F)
$
3,220.00
CONTRACTOR'S MARK-UP ON WORK OF SUBCONTRACTORS
Detailed Breakdowns and summaries from each contractor must be attached.
SUBCONTRACTOR: Firm Name CONTRACT WORK: Description
2.
3.
4.
PROPOSAL
SUBTOTAL of all work performed by contractor's subcontractors $0.00
MARK-UP on work of subcontractors (Min. $ 00) (Line H x 5%)- Deletion -0- $0.00
PROPOSAL (Lines G+H+I) $3,220.00
BONDS (1.5%of PROPOSAL)-Deletion-0- $48.30
BUILDER'S RISK INSURANCE (0.0%of PROPOASL) -Deletion -0-
$3,268.30
TOTALPROPOSAL
TOTAL PROPOSAL for subject COR increase (decrease) in contract amount $3,268.30
An extension time of 0 day to extend the Contract dates for Completion will be required commencing on
the date when we are notified a Change Order will be issued for the price quoted herein. Approval needed In 5 days.
If the work has to be performed to continue construction with no response on pricing or if we are issued a Work
Change Directive (WCD) to proceed with this work and agreement on the price has not been reached within 30
calendar days, then this proposal shall be considered a Claim, in accordance with Article 10.5 of the
Contract General Conditions.
CONTRACTOR
Signature A&&✓Ylceary Title: PM Date: 9/19/2016
CITY OF SOUTH BEND, INDIANA
GRIT AND SCREENINGS IMPROVEMENTS
REQUEST FOR CHANGE ORDER PROPOSAL
TO: Mr. Matt McCoy
Thieneman Construction, Inc.
521 W. 8411 Dr., Suite A
Merrillville, IN 46410
I3N Inne.zliaa Boulawid, sufle 150
hdian Ois. Indiana 46218
p 317 924 3388
1 311228 9369
,ane.6eeelerh;nscn..aa
PROPOSED CHANGE NO. 1
DATE: April 25, 2016
Please prepare a detailed proposal to make the proposed changes in the Work as described below.
Include in your proposal a breakdown of costs in accordance with the General Conditions and
Specification Section 01250 and a proposed schedule for the work. Incorporate all changes on record
drawings submittal.
Specification Reference: 46 23 27
Drawing Reference: N/A
DESCRIPTION OF WORK COVERED BY THIS PROPOSED CHANGE:
1. Replace the expanded metal viewing windows with gas tight hatches for the grit washers. Refer
to the attached drawing from Weir Specialty Pumps manufacturer.
By: �.7 �—
Tren ontemayor, P.E., BCEE
CC: Jacob Klosinski (City of South Bend)
Tracy Powers (Thieneman)
Jason Davidson (Thieneman)
File (G&H)
Matt McCoy
From: Gary Prelim <Gary@blanderson.com>
Sent: Friday, April 15, 201611:44 AM
To: Matt McCoy
Subject: FW: DW10672 Conference Call
Attachments: 15DW10492BA-2 Rl.pdf
Matt,
You should have been copied on this email.
Pv,P, Fib F3 c., 9,
Gary Prehm
Executive Vice-Presi(Jent
aarv(@blanclerson.com
4801 Tazer Drive
Lafayette, IN 47905
765.463-1518 Office
765.446.8390 Fax
765.426.0829 Cell
www.blanderson.corn
From: ben.n s c weireroup.com Lailto:t)en,rig s aweimroup.corrQ
Sent: Friday, April 15, 201612:31 PM
To: Gary Prehm <Garvtwblanderson.com>; ken.poard@weireroun com; Montemayor, Trent<tmontcalay -reeled
hansen.com>
cc: Min .kavalam weigroup com
Subject: RE: DW10672 Conference Call
Gentlemen,
We can add access hatches to our scope of supply for a change order of $2,800.00. I'm attaching a drawing for reference
which shows where the hatches will be located.
If we can have approval to proceed with this by early next week, we can complete the engineering changes, release the
order, and we should be ready to ship the week of August 8th. Please let me know.
Best regards,
THI 1V1VC N"
XNSi""'ON.140
.
August 19, 2016
Greeley and Hansen
7820 Innovation Blvd. Suite 150
Indianapolis, IN 46278
Attn: Mr. Trent Montemayor
Subj: South Bend Grit and Screenings
Proposed Change Order 42
Mr. Montemayor:
In accordance with the agreement reached between Thicneman Construction, Greeley and
Hansen, and the City of South Bend, TCI offers the following Change Order Request #2.
TCI will install three (3) ball valves, associated piping, and insulation in the pump room
spray loop. hi exchange for this added work, all requirements associated with overhead
crane testing and certification in the specifications are now void. Please incorporate COR
#2 for the amount of Zero Dollars and Zero Cents ($0.00) when a formal change order is
issued. Feel free to contact me with any questions.
Respectfully,
Matt McCoy
Project Manager
Cc: Field, File, Accounting
INDUSTRIAL • MUNICIPAL CONTRACTOR
521 W. 84111 Dr. • Suite A • Merrillville, IN 46410 . 219-947-4700 • Fax 219-947-4711
17219 Foundation Pktvy . Westfield, IN 46074 . 317-867-3462 a Fax 317-867-3463
•1�i Contractor's / Subcontractor's
THIFTIAN Change Order Request Summary
Date: 8/18/2016 CO R: 2
General Contractor 521 W. 84th Drive Suite A, Merrillville, IN 46410, 219-947-4700 phone/ 219-947-4711 fax
Engineer: Greeley and Hansen Owner: City of South Bend
Project: South Bend Grit and Screenings
Improvements
_ _ __ _ _ TO Job M i511
DESCRIPTION OF CHAN6E�-----���------���--�����������—
In accordance with the agreement at progress meeting 44 on July 5, 2016, TO offers the following
will install three (3) valves, necessary piping, and insulation in the basement pump room to isolate sections of the spray loop.
work will be performed at no additional cost in exchange for deletion of the crane testing and inspection requirements in tht
cifcations. In particular, All references to load testing and certification of the plant's existing overhead cranes as required in
c section 02 4100 are now void.
SUMMARY OF DETAILED BREAKDOWN
LABOR
MATERIAL
EQUIPMENT
OTHER COSTS
1. SAFETY
2. EXPENDABLETOOLS
NET TOTAL
OVERHEAD AND PROFIT
TOTAL WORK PERFORMED BY CONTRACTOR
Additions Deletions Net Total
(1% of LABOR)- Deletion -0-
(3.0% of LABOR)- Deletion -0-
(A+B+C+D1+D2)
(Ex15%) - Deletion -0-
(Lines E+F)
CONTRACTOR'S MARK-UP ON WORK OF SUBCONTRACTORS
Detailed Breakdowns and summaries from each contractor must be attached.
SUBCONTRACTOR: Firm Name
1.
2.
3.
4.
CONTRACT WORK: Description
PROPOSAL
SUBTOTAL of all work performed by contractor's subcontractors $0D0
MARK-UP on work of subcontractors (Min.$ .00) (Line Hx 5%)-Deletion-0- $0.00
PROPOSAL (Lines G+H+I) $0.00
BONDS (1.5%of PROPOSAL)-Deletion-0- $0.00
BUILDER'S RISK INSURANCE (0.0%of PROPOASQ- Deletion-0-
$0.00
TOTAL PROPOSAL
TOTAL PROPOSAL for subject CDR increase (decrease) in contract amount $0.00
An extension time of 0 day to extend the Contract dates for Completion will be required commencing on
the date when we are notified a Change Order will be issued for the price quoted herein. Approval needed in 5 days.
If the work has to be performed to continue construction with no response on pricing or if we are issued a Work
Change Directive (WCD) to proceed with this work and agreement on the price has not been reached within 30
calendar days, then this proposal shall be considered a Claim, in accordance with Article 10.5 of the
Contract General Conditions.
CONTRACTOR
Signature Malt able ay, Title: PM Date: 8/18/2016
Tiff EIN - MAN
CONS12UCT10N.INC.
September 20, 2016
Greeley and Hansen
7820 Innovation Blvd. Suite 150
Indianapolis, 1N 46278
Attn: Mr. Trent Montcmayor
Subj: South Bend Grit and Screenings
Proposed Change Order 43 RI
Mr. Montemayor:
Please find the attached Change Order Request for a credit from Toric Engineeringwhich is being
provided for building the SCADA screens in house as opposed to on -site. Please incorporate
COR #3 R 1 for the credit amount of Three Thousand Nine Hundred Twenty Six Dollars and
Twenty Two Cents (-$3,926.22) when a formal change order is issued. Feel free to contact me
with any questions.
Respectfully,
'Yylatd'Y&j?'50
Matt McCoy
Project Manager
Cc: Field, File, Accounting
INDUSTRIAL • MUNICIPAL CONTRACTOR
521 W. 84"' Dr. • Suite A • Merrillville, IN 46410. 219-947-4700 • Fax 219-947-4711
17219 Foundation Pkwy • Westfield, IN 46074.317-867-3462 • Fax 317-867-3463
�p Contractor's / Subcontractor's
THTF. IAN Change Order Request Summary
Date: 9/19/2016 COR: 3 R1
521 W. 84th Drive
Engineer: Greeley and Hansen
of building
Owner:
Project:
TCI lob q
in house opposed to onsite. Five days of labor and
SUMMARY OF DETAILED BREAKDOWN
LABOR
MATERIAL
EQUIPMENT
OTHER COSTS
1. SAFETY
2. EXPENDABLE TOOLS
NETTOTAL
OVERHEAD AND PROFIT
TOTAL WORK PERFORMED BY CONTRACTOR
City of South Send
South Bend Grit and Screenings
Improvements
Additions Deletions Net Total
(1%of LABOR)- Deletion -0- $ -
(3.0%of LABOR)-Deletion-0- $ -
(A+B+C+D1+D2) $ -
(Exl$%) - Deletion -0- $ -
(Lines E+F) $ -
CONTRACTOR'S MARK-UP ON WORK OF SUBCONTRACTORS
Detailed Breakdowns and summaries from each contractor must be attached.
SUBCONTRACTOR: Firm Name CONTRACT WORK: Description PROPOSAL
1. Toric Credit-$3,684.00
2.
3. _
4.
SUBTOTAL of all work performed by contractor's subcontractors
-$3,684.00
MARK-UP on work of subcontractors (Min. $ 00)
(Line H x 5%)
-$184.20
PROPOSAL
(Lines GA H)
-$3,868.20
BONDS
(1.516 of PROPOSAL)-Deletion-0-
-$58.02
BUILDER'S RISK INSURANCE
(0.0% of PROPOAAL) - Deletion -0-
-$3,926.22
TOTAL PROPOSAL
TOTAL PROPOSAL for subject COR increase decrease in contract amount-$3,926.22
An extension time of 0 day to extend the Contract dates for Completion will be required commencing on
the date when we are notified a Change Order will be issued for the price quoted herein. Approval needed in 5 days.
If the work has to be performed to continue construction with no response on pricing or if we are issued a Work
Change Directive (WCD) to proceed with this work and agreement on the price has not been reached within 30
calendar days, then this proposal shall be considered a Claim, In accordance with Article 10.5 of the
Contract General Conditions.
CONTRACTOR
Signature Atatt.AdeeWj. Title: PM Date: 9/19/2016
Matt McCoy
From:
Gary Prehm <Gary@blanderson.com>
Sent:
Friday, April 01, 201612:00 PM
To:
Matt McCoy
Cc:
- Tracy Powers
Subject:
FW: South Bend RFI Cost Savings.
Matt,
Please see below from Brian at Toric on credit amount.
Thanks
Gary Prehm
Executive Vice -President
aaryCaManderson.com
4801 Tazer Drive
Lafayette, IN 47905
765.463.1518 Office
765.446.8390 Fax
765,426.0829 Cell
www.blanderson.com
From: Brian Hoffman jmailto:brian@toricenz.coml
Sent: Friday, April01, 201612:01 PM
To: Gary Prehm <Garv_@blanderson.com>
Subject: South Bend RFI Cost Savings.
Gary, in the RFI response I received from the Engineer on South Bend Grit they are asking for a cost savings for what we
proposed since we are reusing material and will not be spending as much time onsite. We can reduce our cost to the
owner by $3684.00. This cost savings is for 5 days of onsite time and material. I am sending this to you to make sure you
are alright with this. I am trying to put together a response to the RFI and would like to include this if that is the number
you want me to go with. Please let me know.
Regards,
Brian Hoffman
�C. o4-�
��
THIENEMAN
CONSl0.11CTI0N,INt.
September 20, 2016
Greeley and Hansen
7820 hmovation Blvd. Suite 150
Indianapolis, IN 46278
Attn: Mr. Trent Montemayor
Subj: South Bend Grit and Screenings
Proposed Change Order #4 RI
Mr. Montemayor:
Please refer to Change Order Request #4 RI to sand blast and coat the black iron pipe loops
submerged in the East tank and West tank. The spray loops piping was called out as black iron
pipe. The prep and coating will provide extended service life of the piping. TCI agrees to have
our subcontractor Delta Paintings perform this work without any additional markup from TCI.
Please increase the contract amount by Two Thousand Three Handred Forty Four Dollars and
65 cents ($2,344.65) in the next change order issued for COR #4 RI . Feel free to contact me with
any questions.
Respectfully,
Watt ?&I tCoq
Matt McCoy
Project Manager
Cc: Field, File, Accounting
INDUSTRIAL • MUNICIPAL CONTRACTOR
521 W. 84" Dr. • Suite A • Merrillville, IN 46410.219-947-4700 • Fax 219-947-4711
17219 Foundation Pkwy • Westfield, IN 46074 •317-867-3462 . Fax 317-867-3463
IF
THI Tf:AIAN
�.._....
521 W. 84th Drive
Engineer: Greeley and Hansen
work to
SUMMARY OF DETAILED BREAKDOWN
LABOR
MATERIAL
EQUIPMENT
OTHER COSTS
I. SAFETY
2. EXPENDABLE TOOLS
NETTOTAL
OVERHEAD AND PROFIT
TOTAL WORK PERFORMED BY CONTRACTOR
Contractor's / Subcontractor's
Change Order Request Summary
Date: 9/19/2016 COR: 4 R1
Owner: City of South Bend
Project: South Bend Grit and Screenings
Improvements
TO Job #
iron pipe fabricated for the spray loops in both tanks.
Additions
(1%of LABOR)- Deletion -0-
(3.0% of LABOR)- Deletion -0-
(A+B+C+01+D2)
(Ex15%) - Deletion -0-
(Lines E+F)
CONTRACTOR'S MARK-UP ON WORK OF SUBCONTRACTORS
Detailed Breakdowns and summaries from each contractor must be attached.
SUBCONTRACTOR: Firm Name
1. Delta
2.
3.
4.
Deletions Net Total
CONTRACT WORK: Description PROPOSAL
Add prep and painting $2,200.00
SUBTOTAL of all work performed by contractor's subcontractors
$2,200.00
MARK-UP on work of subcontractors (Min. $ Do)
(Line H x 5%)
$110.00
PROPOSAL
(Lines G+H+I)
$2,310.00
BONDS
(1.5%of PROPOSAL)
$34.65
BUILDER'S RISK INSURANCE
(0.0%of PROPOAAL) - Deletion -0-
$2,344.65
TOTAL PROPOSAL
TOTAL PROPOSAL for subject CDR increase (decrease) in contract amount $2,344.65
An extension time of 0 day to extend the Contract dates for Completion will be required commencing on
the date when we are notified a Change Order will be issued for the price quoted herein. Approval needed in 5 days.
If the work has to be performed to continue construction with no response on pricing or if we are issued a Work
Change Directive (WCD) to proceed with this work and agreement on the price has not been reached within 30
calendar days, then this proposal shall be considered a Claim, in accordance with Article 10.5 of the
Contract General Conditions.
CONTRACTOR
Signature Malt Atce'oy. Title: PM Date: 9/19/2016
An am
r1} Phone: 218-1:147-5105
Fax: 214-947-5056
INDUSTRIAL. CY)MMIIRCIA1- PAINT CONTRACT9ttS 1217 Hickey Si. Hobert, IN 46342
t: marl. ❑ rorgo3fR conneasulet
Cell: (219) 313-4103
DATE: July 18, 2016
TO: Mr. Jason Davidson
COMPANY: Thieneman Construction, Inc.
;,IIioJ P:'T' Ct1ANCU ORDER REQUEST No.1(RI)
ADDITIONAL WORK
Field Painting- 2" Black Pipe 6i! 20 LFT Submerged
At Grit Screening Project (+0 Soutll Bend IN
SENDER: Michael Georgos (E-Mail: mgeorgos n,comcast.net)
MESSAGE: Reference POli.: Pending
Reference Delta's Proposal No.: D15-042
We are requesting a change order in the amount of $ 2,200.00 for furnishing labor,
material and equipment to sandblast and apply 3 coats of Dura-Plate 235 Epoxy on 2"
submerged black pipe. Finish color to be Safety Blue No. S W4086.Pipe will be
sandblasted and painted on ground. Our price does not include the clean-up nor the
disposal of our spent abrasives. All lay out and handling of pipe will be by others.
Our price does not include any containment, dust collector, ventilation or noise
reduction.
For informational purposes:
BASEBID .................................... $
CHANGE ORDER No. I ...... ADD ............. $
Breakdown of CONo.I:
Labor; ............. ti 1,700.00
Equipment: ...... S 300.00
Material: .......... $ 200.00
Mark-up ......... $ NIA
8,400.00 (Original Contract Approved)
2,200,00 (Not approved yet)
Respectfully Submitted,
DELTA PAINTING, INC.
MichaefG- POWs
Michael G. Georgos
Cell: 1(219) 313-410
-rutENEMAN
COIISTflUC11011.1NC,
September 20, 2016
Greeley and Hansen
7820 Innovation Blvd. Suite 150
Indianapolis, IN 46278
Attn: Mr. Trent Montemayor
Subj: South Bend Grit and Screenings
Proposed Change Order#5 RI
Mr. Montemayor:
Please refer to Change Order Request #5 RI for pipe modifications to the spray loops for both the
Cast tank and West tank. The spray loops were fabricated and ready to install. At the time of
installation, TCJ noticed that a revised configuration would serve the intended purpose better. The
reconfiguration was discussed with the plant and they agreed. As much of the material as possible
in the already fabricated loops will be reused. Please increase the contract amount by Nine
Hundred Eleven Dollars and 11 cents ($911.11) in the next change order issued for COR 45 Rl .
Feel free to contact me with any questions.
Respectfully,
V&zr7/1C act
Matt McCoy
Project Manager
Cc: Field, File, Accounting
INDUSTRIAL • MUNICIPAL CONTRACTOR
521 W. 84" Dr. • Suite A • Merrillville, IN 46410 • 219-947-4700 • Fax 219-947-4711
17219 Foundation Pkwy . Westfield, IN 46074 •317-867-3462 • Fax 317-867-3463
TlIIP.NYiA1RN
Date:
521 W. 84th Drive Suite A, N
Engineer: Greeley and Hansen
spray
SUMMARY OF DETAILED BREAKDOWN
for both tanks
Contractor's / Subcontractor's
Change Order Request Summary
COR: 5 R1
10, 219-947-4700 phone/ 219-947-4711 fax
Owner: City of South Bend
Project: South Bend Grit and Screenings
Improvements
TO Job# 1511
Additions Deletions Net Total
LABOR
$ 539.00 $
- $
539.00
MATERIAL
$ 220.00 $
- $
220.00
EQUIPMENT
$ -
$
-
OTHER COSTS
1. SAFETY
(1%of LABOR)-Deletion-0-
$
5-39
2. EXPENDABLE TOOLS
(3.0%of LABOR)-Deletion-0-
$
16.17
NETTOTAL
(A+B+C+Dl+D2)
$
780.56
OVERHEAD AND PROFIT
(Ex15%) - Deletion -0-
$
117.08
TOTAL WORK PERFORMED BY CONTRACTOR
(Lines E+F)
$
897.64
CONTRACTOR'S MARK-UP ON WORK OF SUBCONTRACTORS
Detailed Breakdowns and summaries from each contractor must be attached.
SUBCONTRACTOR: Firm Name
CONTRACT WORK: Description
PROPOSAL
1.
2.
3.
4
SUBTOTAL of all work performed by contractor's subcontractors
MARK-UP on work of subcontractors (Min. $.00)
PROPOSAL
BONDS
BUILDER'S RISK INSURANCE
TOTAL PROPOSAL
$0.00
(Line H x 5%)- Deletion-0-
$0.00
(Lines G+H+I)
$897.64
(1.5%of PROPOSAL)-Deletion-0-
$13.46
(0.0% of PROPOAAL) - Deletion -0-
$911.11
TOTAL PROPOSAL for subject COR Increase (decrease) in contract amount $921.11
An extension time of day to extend the Contract dates for Completion will be required commencing on
the date when we are notified a Change Order will be issued for the price quoted herein. Approval needed in 5 days.
If the work has to be performed to continue construction with no response on pricing or if we are issued a Work
Change Directive (WCD) to proceed with this work and agreement on the price has not been reached within 30
calendar days, then this proposal shall be considered a Claim, in accordance with Article 10.5 of the
Contract General Conditions.
CONTRACTOR
Signature Awt ✓14ceory Title: PM Date: 9/19/2016
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date November 15, 2016
Name Jacob M. Klosinski Department Division of Utilities
BPW Date November 22, 2016 Phone Extension (574) 235-9496
Required Prior to Submittal to Board
Legal ® Attorney Name Michael Schmidt
Controller ® Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ® Carol Kurzhal
Check the Appropriate Item Type — Required for All Submissions
❑ Agreement ❑ Contract ❑ Proposal ❑ Addendum
❑ Professional Services ❑ Resolution
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award
® Change Order No. 001 ❑ C/O & PCA No. ❑ PCA
❑ Ease/Encroach. ❑ Traffic Control
❑ Other:
Company or Vendor Name
New Vendor
MBE/WBE Contractor
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Amount of
Thieneman Construction, Inc.
Yes ® No ❑ If Yes, Approved by Purchasing
MBE ❑ WBE
W WTP - Grit and Screenings Improvements
114-075
Environmental Services, Treatment and Disposal Equipment Account
642-0630-415-43-66
$ Change Order, see below
Division of Utilities recommends the approval of Change Order No. 1 for
the subject project. Refer to Inter -Office Memorandum and enclosures for
description of changes.
❑ Required Contractor's Certification Form Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
Required For Chanqe Orders Only
Increase
Decrease
Previous Amount
Current Percent of Change:
New Amount
Total Percent of Change:
Copy
Original
®
❑
®
❑
®
❑
+0.23%
Dispersal After Approval
Al Greek, Division Director of Utilities
Jacob M. Klosinski, Assistant City Engineer
Carol Kurzhal, Director of Financial Services, Environmental Services
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENVIRONMENTAL SERVICES
TO: Members of the Board of Public Works
Eric Horvath, Director of Public Works
Michael Schmidt, Board of Public Works Attorney
FROM: Al Greek, Director of Utilities
Jacob M. Klosinski, Assistant City Engineer
SUBJECT:
Agenda Request Form — Change Order No. 1
114-075 Wastewater Treatment Plant Grit & Screenings Improvements
DATE: November 15, 2016
The Department of Utilities (DES) is requesting the Board of Public Works approval of Change
Order No. 1 for Project No. 114-075 Wastewater Treatment Plant Grit and Screenings
Improvements. Refer to attached documents for supporting details for claims.
Change Order No. 1 addresses the following changes:
PCO 1: Provide expanded metal viewing window for grit washers
PCO 2: Provide three (3) valves for spray loop isolation
PCO 3: Build LCP-100 Cabinet Back -plate offsite, labor savings
PCO 4: Sand blast and coat spray loops for submerged condition
PCO 5: Reconfigure Spray Loops for East & West Detritus Tanks
NET INCREASE FOR CHANGE ORDER NO. 5 ITEMS
Original Contract Sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this change order, the project amount increases by
The new contract sum including this change order is
This Change Order represents a total change of
Total change for the entire project
$ 3,268.30
$ 0.00
($ 3,926.22)
$ 2,344.65
$ 911.11
$ 2,597.84
$ 1,146,000.00
$ 0.00
$ 1,146,000.00
$ 2,597.84
$ 1,148,597.84
+0.23%
+0.23%
Time Extensions: 0 Days to Substantial Completion and 0 days to Final Completion.
The primary funding sources for the construction of this project is the Environmental Services,
Wastewater, Treatment and Disposal Equipment Account (642-0630-415-43-66) or other
Wastewater Accounts. If there are any questions regarding the subject project, please contact
Al Greek (Ext. 4210) or Jacob M. Klosinski (Ext. 9496) at the Division of Utilities.