HomeMy WebLinkAboutChange Order No. 4 - Olive St & Sample St. Reconstruction - Lawson-Fisher - INDOT1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND. INDIANA 46601-1830
CITY OF SOUTH BEND PETE BUTTIGIEG, MAYOR
BOARD OF PUBLIC WORKS
November 08, 2016
Don Dietz
Lawson -Fisher Associates
525 W Washington St.
South Bend, IN 46601
RE: Change Order No. 4 — Olive Street and Sample Street Reconstruction
Project No. 113-002
Dear Mr. Dietz:
PHONE 574/235-9251
FAX 574/235-9171
The Board of Public Works, at its meeting held on November 8, 2016, approved the above
referenced Change Order with INDOT for an increase of two -hundred, six (206) days with a
new completion date of May 26, 2017 to allow for completion of the roundabout.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
c: Roger Nawrot, Engineering
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MAP ADIK TAMES A. MUELLER THERESE J. DORAU
EY CONSTRUCTION CO., INC.
100% Qualify • 100% Employee Owned • Over 100 Years
October 14, 2016
R-35727 Olive/Sample St. Reconstruction
Don Dietz — Project Engineer
Re: Continued Closure of Olive St.; North of the new round -about
Don,
As previously discussed, please take this as my official request to leave Olive Street, north of the new round-
about closed until the remaining construction of the new round -about is completed. This would extend the
Intermediate Completion Date from November 1, 2016 until May 26, 2017; prior to Memorial Day.
We are requesting this due to the safety hazard that may be presented with live traffic flowing through the
round -about and heading south on Olive while construction activities would be taking place within the
center of the round -about— directly in the potential path of a southbound car or truck. Technically all work
required for the first intermediate completion date would have been completed, aside from just opening
Olive north of the intersection.
If you have any questions please let me know.
Thanks,
A
Robert Nichols
Project Manager
P.O. Box 1775 •25200 S.R. 23 - South Bend, IN 46634
Phone: (574) 288-8321 • www.rieth-riley.com
Don Dietz
To: Krueckeberg, John
Cc: Barich, David M; Forgey, Ryan
Subject: 3S727 CO 4
Mr. Krueckeberg,
This email serves as notification for Change Order #4 for contract R 35727. This Change Order is a time extension for the
Intermediate Completion Date regarding Olive St Bridge, Change Order #4 is available for viewing in Site Manager.
Don Dietz
Lawson -Fisher Associates PC
Contract No:R -35727 Change Order No.: 004
INDIANA Department of Transportation Page: 1
Construction Change Order and Time Extension Summary
Contract Information Contract No.: R -35727 Letting Date:02117/2016
District:LAPORTE DISTRICT AE:Forgey, Ryan PE/S:Dietz, Don Status:Draft
Change Order Information Change Order No.: 004 EWA: N or Force Acct: N
Date Generated: 00/00/0000 Date Approved: 00/00/0000
Reason Code: MAINT. OF TRAFFIC SAFETY IMPROVEMENT
Description: Revised Milestone #1 Completion Date
Original Contract Amount $ 8,947,369.00
Current Change Order Amount $ 0.00 Percent: 0.000 %
Total Previous Approved Changes $ 33,550.00 Percent; 0.375 %
Total Change To -Date $ 33,550.00 Percent: 0.375 %
Modified Contract Amount $ 8,980,919.00
Time Extension Information
Date Initiated 00100/0000 Date Completed 00/00/0000
Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SP Date 00/00/0000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Time Element Description:
Current Time Extension SS Days 0 SP Days 206 SP Days Value $ 0.00
Previous Time Approved SS Days by AE: DCE: SCE: DDCM:
SS Days SP Days Value $
Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SS Date 00/00/0000 or SP Days 0
Contract No:R -35727
Change Order No.: 004
INDIANA Department of Transportation Page: 2
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority AE: DCE: SCE: " DDCM:
($ per Change Order) (- LE $ 250K-) (- LE $ 750K -) (-- LE $ 2 M —) (-- GT $ 2 M -- )
(Days per Contract) ( 50 SS days ) ( 100 SS days) (200 SS Days) ( GT 200 SS days)
Verbal Approval Required?
Y / N If Y, by Date Issued
Total Change To-Date>5%?
Y / N If Y , Copy to Program Budget Manager
Scope/Design Recommendation
Required?
Y / N If Y, Referred to Project Manager(PM)
Date to PM Date Returned
Approval Authority Concurs with PM?
Y / N If Y, Concurrence by Date
If N,Resolution: Approved Disapproved
Resolved by Date
LPA Signatures Required?
Y / N If Y, Date to LPA Date Returned
FHWA Signatures Required?
Y / N If Y, Date to FHWA Date Returned
Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer
Date
Comments:
Contract NOR -35727 INDIANA
Change Order No:004 Department of Transportation
Contract: R -35727
Project: State: 1 2985790OLC
Change Order Nbr: 004
Change Order Description: Revised Milestone #1 Completion Date
Reason Code: MAINT, OF TRAFFIC SAFETY IMPROVEMENT
Date:09/29/2016
Page: 3
CLN PCN PLN Item Code Unit Unit Price - CO qty Comment Amount Change
Total Value for Change Order 004 = $ O.OD
Milestone Time Adjustment
Milestone Nbr: 01
Milestone Description: INTERMEDIATE COMPLETION DATE: 1
Original Completion dt: 11101/2016 Adj comp) of 05/26/2017 Adj No. of Days 206
Explanation: Keeping Olive St closed for safety to the traveling public through the winter months. Olive St will open when the traffic
pattern utilizing the roundabout is completed.
Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended.
General or Standard Change Order Explanation
It was discussed at length at several progress meeting to keep Olive St north of Sample St closed until such a time that the roundabout is
constructed. MOT will open Olive St north of Sample and will include the use of the roundabout to facilitate safer traffic patterns. City to South
Bend, County of St Joseph, DLZ design firm,and LFA construction inspection teem are all in agreement to keep Olive St closed for the winter and
provide a safer traffic pattern to the public. during this time. No additional payment will be made.
Change Order Explanation for Specific Lino Item
It is the intent of the parties that this change order is full and complete compensation for the work describe above.
Notification and consent to this change order is hereby acknowledged.
Contractor.. r£� Signed B�
Dale: 1Q - %'J-- 114?
NOTE: Other required Stale and FHWA signatures will be obtained electronically through the SileManager system.
Contract No:R -35727 INDIANA
Change Order No:004 Department of Transportation
K......................... ............. ... A"ftvEa................... ..,............ .�........
Board of Public VOP&,,VED FOR LOCAL PUBLIC AGENCY
(SIGNATURE) � N. O
(SIGNATURE)
er....a_._..__...........................
SUBMITTED FOR CONSIDERATION
PEI$
(DATE)
(DATE)
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION
Date:09/29/2016
Approval Level Name of Approver Date Status
Page: 4
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date October 27, 2016
Department Public Works
Name
Roger Nawrot
Division/Bureau
Engineering
BPW Date
November 8, 2016
Phone Extension
5932
Required Prior to Submittal to Board
Legal ❑ Attorney Name:
Controller El greater
review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ❑
Check the Appropriate Item Type — Required for All Submissions
❑ Agreement ❑ Contract ❑ Proposal ❑ Addendum
❑ Professional Services ❑ Resolution
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award
® Change Order No. 4 ❑ C/O & PCA No. ❑ PCA
❑ Ease/Encroach. ❑ Traffic Control:
❑ Other:
Required Information
Company or Vendor Name Indiana Department of Transportation
❑ Yes LJ No ❑ If Yes, Approved by
New Vendor
MBE/WBE Contractor
MBE/WBE Contractor Requested
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Amount of
Increase
Decrease
Previous Amount
Current Percent of Change:
New Amount
Total Percent of Chanae:
II MBE U WBE
El No ❑ Yes Name of Company
Olive Street and Sample Street Reconstruction
Major Moves
412-0414 /542.03
t-eaerai tsu%, city 1u% tic County 10%
This change order is for changing the Intermediate Completion
Date from November 1, 2016 until May 26, 2017 for the opening
of Olive Street north of Sample Street. This is being done for the
safety of the motoring public because the roundabout is only
partially built. Traffic and Lighting division is in agreement with
LJ Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
Orders O
Copy Origin
® ❑
Nawrot