October 25, 2016
Mr. Jason Minne
Walsh & Kelly, Inc.
24358 State Road 23
South Bend, IN 46614
RE: Change Order No.4 - East Bank Sewer Separation, Phase 5
Project No. 114-062B
Dear Mr. Minne:
PHONE 574/235-9251
FAx 574/235-9171
The Board of Public Works, at its meeting held on October 25, 2016, approved the above
referenced Change Order for an increase amount of $25,900.00, and an extension of ninety-
three (93) days, for a revised contract amount of $5,304,900.66 and a new completion date of
August 14, 2017.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
�.��.<._�
Linda M. Martin, Clerk
Enclosure
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK JAMEs A. MUELLER THERESE J. DORAD
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO:
SUBJECT OF CHANGE ORDER:
9/30/2016
East Bank Sewer Separation - Phase 5 (Division B)
1 /26/2016
4
PCR #9-Tree Removal PCR #10-Soil Delay
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
contracted
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
CONTRACTOR
C tractor Signature
J�t.s� n � n n ,° 1 S ��oery,✓ �e�✓dc.✓�
Printed Name and I itle
Walsh Kelly Inc.
Company Name
24358 State Road
Address
South Bend, IN 46614
City, State, Zip
Increased
Decreased
$ 25,900.00
(TIF: + $0.00)
(Sewer Bond: + $25,900.00)
$ 5,304,900.66
0.49 %
RECOMMENDED FOR APPROVAL
CON CTION MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
Approved Date: —/a / l,,
President
beth A.
Therese J. Dorau, Member
Jam A. Mueller, Member
4.41 %
City of South Bend Project No. 114-062B
Change Order No. 4 - 09/30/16
OWNER: City of South Bend
ENGINEER: City of South Bend Engineering
Patrick C. Kerr, PhD., P.E.
Professional Engineer No. 10707546
CONTRACTOR: Walsh & Kelly, Inc.
PROJECT: East Bank Sewer Separation - Phase 5 (Division B)
Project No. 114-062B
SUBJECT: Change Order Explanation
ISSUE DATE: September 30, 2016
This Change Order to the Contract document shall supplement, amend, and shall become a
part of, and be incorporated as an Addendum to the Contract.
The following is a summary and description of the revisions to the Contract by this Change
Order:
Item QtY Unit Price Days Total
1. Tree Removal 1 LS $25,900 0 $25,900
2. Soil Delay 0 N/A $0.00 93 $0
1) Trees and shrubs must be removed from beyond the right-of-way to allow for the contractor
to shape the slope on Northside Blvd. The shaping of the slope is necessary for bank
stabilization.
2) Please see attached memorandum for a breakdown of the delay dates.
Walsh & GRIFFITH SOUTH BEND
1700 East Main Street 24358 State Road 23
�%% Kelly,.. Phone
Griffith, Indiana -5900 South Bend, Indiana 846614
11
PFax(21 )924- -5900 Phone
Fax(57 ) 289-71711
Fax(219)924-8768 Fax(574)289-7174
www.waishkelly.com
10/14/2016
Dan Jones
City of South Bend
RE: Eastbank Phase 5
Dan,
I am writing to request addition days due to delays on the Eastbank Sewer project. As you know
contaminated soils were found on St. Peter Street where we need to run the main storm sewer trunk
line for the western half of the project. These soils were found on August 30". Since this time no
further work has been done due to testing and waiting on a resolution from the city. Walsh & Kelly
Inc. is requesting addition days from August 30" to October 25t" 2016. This is the time period for
waiting on a resolution from the city and the required testing for the landfill. We are also asking for
addition days from October 20'" to December 1St this is because we are unable to progress on the
project due to the lack of sufficient time to restore any more streets this season.
Walsh & Kelly Inc. will also be asking for addition compensation for cost due to increases in labor,
materials, and equipment cost associated with completing the project next season. Theses exact
costs have not been calculated but will be in the near future.
Please let me lyjow if you need any further information.
d' A
Dustin Hilary
Area Manager
EQUAL OPPORTUNITY EMPLOYER
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 10/17/16
Name Toy Villa l Department Engineering
BPW Date 10/25/16 Phone Extension 5920
Required Prior to Submittal to Board
Legal ❑ Attorney Name
Controller ❑ Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ❑
Check the Appropriate Item Type — Required for All Submissions
❑ Agreement ❑ Contract ❑ Proposal ❑ Addendum
❑ Professional Services ❑ Resolution
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award
® Change Order No. 4 ❑ C/O & PCA No. ❑ PCA
❑ Ease/Encroach. ❑ Traffic Control
❑ Other:
Company or Vendor Name
New Vendor
MBE/WBE Contractor
MBE/WBE Contractor
Requested
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
red intormation
Walsh & Kelly, Inc.
❑ Yes ® No ❑ If Yes, Approved by Purchasing
r] MBE ❑ WBE
No ❑ Yes Name of
East Bank Sewer Separation — Phase 5 (Division B) Sewer Bond
114-062N R
Sewer Bond
429.1050.460.31.02
Approval of Change Order #4
❑ Required Contractor's Certification Form Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.
Required For Change Orders Only
Amount of ® Increase $ 25,900.00 93 Dols
❑ Decrease $
Previous Amount $ 5,279,000.66
Current Percent of Change: 0.49%
New Amount $ 5,304,900.66
Total Percent of Change: 4.41 %
Dispersal After Approval
Copy
Original
®
❑
®
❑
®
❑
Aaron Kobb, Judy Love, Beth Leonard
ME