October 25, 2016
Mr. Jeremy Jankoviak
Premium Concrete
712 Richmond Street
Elkhart, IN 46516
RE: Change Order No.4 - 2016 Curb and Sidewalk Construction
Project No. 116-029
Dear Mr. Jankoviak:
PHONE 574/235-9251
FAX 574/235-9171
The Board of Public Works, at its meeting held on October 25, 2016, approved the above
referenced Change Order for an increase of eight (8) days with a new completion date of
October 28, 2016.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
i
Linda M. Martin, Clerk
Enclosure
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK JAMES A. WELLER THERESE J. DORAU
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO:
CITY OF SOUTH BEND, INDIANA
.:�SQiiTH88
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
10/18/2016
116-029
SUBJECT OF CHANGE ORDER:
2016 Curb and Sidewalk Construction
4
Remove sidewalk, Remove concrete curb `--rt ME 1=6L�0'5LO-1
The original contract sum $ 359,750.00
Net change by previously authorized change orders $ 40,911.70
The contract sum prior to this change order $ 400,661.70
By this Change Order, the project amount is ❑ Increased
❑ Decreased $ 0.00
The new contract sum including this change order $ 400,661.70
This Change Order represents a total change of 0.00 %
Total change for entire project 11.37 %
Original contracted completion date/time 10/13/2016
Extension of date/time by previous change orders 7 days
Date/time extension by this change order 8 days
New completion date/time 10/28/2016
Premium Concrete
Company Name
712 Richmond
Address
Elkhart, IN 46516
City, State, Zip
RECOMMENDED FOR APPROVAL
CONST�CTION MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC JNORKS
Approved Date:
Gary A. Gil6t, President
Elizabeth A Maradik, Mem er
Therese J. Do u, mber
'/ li /�-�
Ja 's A. Mueller, Member
t viizlzn
It,
PREMIUM
CONCRETE
SERVICES. INC.
Premium Concrete Services, INC.
712 Richmond St
Elkhart, IN 46516
Phone:(574)264-0196
Fax:(574)266-5392
October 17, 2016
City of South Bend
731 S. Lafayette Blvd.
South Bend, IN 46601
Ref: 2016 Curb and Sidewalk Construction
Project No. 116-029
Premium Concrete Services, Inc. respectfully requests a time extension on the above referenced contract from 10/20/16
to 10/28/16. This request is due to the delay of time caused by the notice to proceed on the project extension of
Woodward Street in Division D.
If Premium Concrete Services, INC. is awarded Woodward Street we respectfully request an additional 7 days. From
10/28/16to 11/11/16.
• On 9/16/2016 we received a notice to stop work on Division D Woodward St. We were done
with removals on other streets and moved removal operations to other projects. We were
scheduled to be done with the project on 10/13/2016.
• On 10/6/2016 we were informed to proceed with work on Woodward Street. At that time we
had mobilized all equipment and materials out. Also, informed our subcontractors to halt work,
because more quantities are being added.
• On 10/14/2016 we were asked to wait on proceeding on Woodward Street. That is a total of 8
days. We are respectfully asking for those days.
• If we are awarded, which we hope we are, we respectfully request 14 more days to complete
Woodward Street.
• We are also worried about winter charges (starting Nov.1) that will be incurred if we are delayed
to long, and the losses incurred because of extra mobilizations.
A total of 8 days have been demonstrated. Therefore, we request 8 days as a time extension, which would extend the
completion date from 10/20/2016 to 10/28/2016. If awarded Woodward Street, we request an additional 14 days
moving the completion date to 11/11/2016. If you have any questions, comments, or require additional information
please contact me.
Sincerely,
Jeremy Jankoviak
Estimator/Project Manager
Jeremy@premiumconcreteonIine.com
Office: (574)264-0196Cell: (574)612-6405
Date
Name
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
10/18/2016
Public Works
Engineering
BPW Date 10/25/2016 Phone Extension 5796
Required Prior to Submittal to Board
Legal ® Attorney Name: Michael Schmidt
Controller ❑ Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ® George King
Check the Appropriate Item Type — Required for All Submissions
❑ Agreement
❑ Professional Services
❑ Bid Opening
❑ Quote Opening
® Change Order No. 4
❑ Ease/Encroach.
❑ Other:
Nadia Correa
Resolution
Bid Award
Quote Award
C/O & PCA No.
Traffic Control:
Department
Division/Bureau
❑ Req. to Advertise
❑ PCA
❑ Title Sheet
Required Information
Company or Vendor Name Premium Concrete
New Vendor El es ®No n If Yes Annrnvari by Pi irchacin ?
MBE/WBE Contractor ❑ ME
MBE/WBE Contractor Requested ❑ No
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Amount of
Previous Amount
2016 C
116-02'
MVH
202-061
WBE
as Name of
and Sidewalk
F31-06
Time extension, 8 days
LJ Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
Increase
Decrease $
Current Percent of Change:
New Amount
Total Percent of Change:
Copy
Origin
❑
❑