HomeMy WebLinkAboutChange Order No. 1 Martin Luther King, Jr. Recreation Center HVAC Revisions Project No. 116-064 Herrman & Goetz, Inc.1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND. INDIANA 46601-1830
CITY OF SOUTH BEND PETE BUTTIGIEG, MAYOR
BOARD OF PUBLIC WORKS
October 25, 2016
Mr. Thomas Adams
Herrman & Goetz, Inc.
225 S. Lafayette Blvd.
South Bend, IN 46601
PHONE 574/235-9251
FAX 574/235-9171
RE: Change Order No.I - Martin Luther King, Jr. Recreation Center HVAC Revisions
Project No. 116-064
Dear Mr. Adams:
The Board of Public Works, at its meeting held on October 25, 2016, approved the above
referenced Change Order for an increase of twenty-one (21) days with new completion date
of January 13, 2017.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
GARY A. GILOT SUZANNA M. FRITZBERG ELIZABETH A. MARADIK JAMES A. MUELLER THERESE J. DORAU
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO:
SUBJECT OF CHANGE ORDER:
10/5/2016 0:00:00
116-064
MLK HVAC Revisions
8/23/2016
PCR #1-Extend final completion date
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
oq SpU�H 6F4'..
� d
Y
1865
$ 379, 708.00
$ 0.00
$ 379,708.00
Increased
Decreased $ 0.00
$ 379,708.00
0.00 %
0.00 %
Original contracted completion date/time 12/23/2016 0:00:00
Extension of date/time by previous change orders 0 days
Date/time extension by this change order 21 days
New completion date/time 1/13/2017
NTRACTOR
Contractor Signature
Rom& , f1L SeZ-1- r)o"rt. 0,
Printed Name and Title
Herrman & Goetz, Inc.
Company Name
225 S. Lafayette Blvd
Address
South Bend, IN 46601
City, State, Zip
RECOMMENDED FOR APPROVAL
CONST CTION MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC WQRKS
Approved Date: /.I ,J5J/'-�>� /(,
President
t
Elizabeth A Maradidik, Member
Therese J. Dora , M&rRber c
/ l `�
Jam s A. Mueller, Member
Herrman & Goetz, Inc.
225 S. Lafayette Blvd., South Bend, IN 46601
(574) 282-2596 FAX (574) 237-6767
(800) 528-1696
9-26-2016
City of South Bend
Engineering Division
1316 County -City Building
South Bend IN 46601
Attention: Nadia Correa
Reference: Martin Luther King Center HVAC
Dear Ms. Correa,
I am writing you this letter to express my concern regarding the specified date of
substantial and final completion for the HVAC project at the MLK Center. We were
anticipating an earlier start date when we submitted the bid for this project. The bid was
due on August 23rd. Our primary concern is the RTU equipment from Trane. This
equipment has a 10 week lead time, after it is ordered. We have not received any
authorization to order the RTU's to date. Due to the start date being later than expected,
and the long equipment lead time, we will not be able to complete this project by the
specified date of December 29, 2016.
H&G Services is officially requesting that the date of substantial completion be changed
to accommodate the delay in the start time, and long equipment lead time. We would like
to move the substantial completion date to December 28, 2016, and the final completion
date to January 13, 2017.
Sincerely,
H&G Services
Tom Adams
/ /E DESIGN SERVICES
Mechanical/Electrical
Consulting Engineers
September 26, 2016
City of South Bend
Engineering Division
1316 County -City Building
South Bend, IN 46601
Attention: Nadia Correa
Reference: Martin Luther King Center HVAC
M/E File #5735
Dear Ms. Correa,
As discussed in our Pre -Construction Conference on Friday, September 23', we are in favor of granting
the Contractor's request for extending the project completion date as outlined in the attached letter from
Herrman & Goetz.
The project has two major parts. The first is the replacement of the heating system boilers and associated
pumps. The second is the replacement of the Gymnasium heating and air conditioning equipment.
Herrman and Goetz has indicated that they can maintain the partial completion date indicated in the
documents which requires that the updated boiler and pump system be on-line by November 2, 2016.
The concern is with delivery and completion of the packaged Gymnasium HVAC units. These units have
a ten (10) week delivery after approval of equipment submittals. We have already completed review of
most of the Contractor's submittals. After we do a final re -check of the submittals, we plan to forward
them to you for processing on Tuesday, September 27. If you are able to process and return the
submittals to the Contractor by Wednesday, September 28", ten weeks would put the delivery date
around December 7'. Because of this delivery date, the existing Gymnasium hydronic heating units
would be maintained in operation until the new units can be installed and made operational, which we
would anticipate to be approximately three (3) weeks after delivery. Based on this, we would
recommend changing Substantial Completion from December 9, 2016 to December 28, 2016, with Final
Completion on Friday, January 13, 2017.
The Contractor is aware that they will need to maintain heating operation through the existing
Gymnasium units until the new units are on-line.
As further justification of this change, I would like to point out that we had originally anticipated that the
project would be released for bids on approximately July 19, 2016 with bids due August 9'. After
various coordination issues, the bids ended up being due on August 23`s. In discussions with you and
John Martinez, the original intent (because of the very tight project schedule) was to quickly review the
bids and then award on that date. Because the project came in over budget, additional review and
coordination became necessary. The project was not actually approved until Tuesday, September 13'".
120 South Hill Street • P.O. Box 1028 • Mishawaka, IN 46546
(574) 256.1914 • FAX (574) 256-1975
memaii@m-e-design.net
/ /E DESIGN SERVICES
Mechanloal/Electrical
Consulting Engineers
Page 2
If you need additional clarification, please do not hesitate to contact our office.
Sincerely,
M/E Design Services
Tbomas R. Cook, Sr., P.E.
Principal Engineer
cc: John Martinez, South Bend Parks Department
120 South Hill Street • P.O. Box 1028 • Mishawaka, IN 46546
(574) 256-1914 • FAX (574) 256-1975
memail ®m-e-design.net
Date
Name
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
10/14/16
Nadia Correa
Department
Division/Bureau
Public Works
Engineering
BPW Date 10/25/16 Phone Extension 5796
I
Required Prior to Submittal to Board
Legal ®
Attorney Name: Michael Schmidt
Controller ❑
Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ®
George King
Check the Appropriate Item Type — Required for All Submissions
❑
Agreement
® Contract ❑ Proposal ❑ Addendum
❑
Professional Services
❑ Resolution
❑
Bid Opening
❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑
Quote Opening
❑ Quote Award
®
Change Order No. 1
❑ C/O & PCA No. ❑ PCA
❑
Ease/Encroach.
❑ Traffic Control:
❑
Other:
Required Information
Company or Vendor Name
Herrman & Goetz, Inc.
❑ Yes ® No ❑ If Yes, Approved by
New Vendor
Purchasing
MBE/WBE Contractor
❑MBE ❑ WBE
MBE/WBE Contractor Requested ❑ No ❑ Yes Name of Company
Project Name
Martin Luther King, Jr. Recreation Center HVAC Revisions
Project Number
116-064
Funding Source
Parks Bond
Account No.
Amount
$379,708.00
Terms of Contract
Final completion date December 29 2016
Purpose/Description
Extend final completion date to January 13, 2017
❑ Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
For Chanqe Orders
Amount of ❑ Increase $
❑ Decrease $
Previous Amount $
Current Percent of Change: %
New Amount $
Total Percent of Chanae:
Copy
Origin
Patrick C. Kerr
I om Adams (Herrman & Goetz, Inc.)