RE: Change Order No. 1
Project No. 115-086
Dear Mr. Hilary:
September 13, 2016
- Lafayette Falls Subdivision Pavement
PHONE 574/235-9251
FAx 574/235-9171
The Board of Public Works, at its meeting held on September 13, 2016, approved the above
referenced Change Order for an increase in the amount of $67,663,20 for a revised contract
total of $260,698.20.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
c: Nadia Correa, Engineering
GARY A. GILOT DAVID P. RELOS ELIZABETH A. MARADIK JAMES A. MUELLER THERESE J. DORAU
0490ITHp ,4
CITY OF SOUTH BEND, INDIANA �(o
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER \'
1865
DATE: 8/16/2016
PROJECT NO: 115-086
PROJECT NAME: Lafayette Falls Subdivision Pavement
CONTRACT DATE: 6/14/2016
CHANGE ORDER NO: 1 (Final)
SUBJECT OF CHANGE ORDER: PCR #1-HMA Quantity Adjustment
All items completed substantially as planned.
See attached Comparison of Estimate for overruns and underruns.
The original contract sum $ 193,035.00
Net change by previously authorized change orders $ 0.00
The contract sum prior to this change order $ 193,035.00
By this Change Order, the project amount is X� Increased
Decreased $ 67,663.20
The new contract sum including this change order $ 260,698.20
This Change Order represents a total change of 35.05 %
Total change for entire project 35.05 %
Original contracted completion date/time 7/30/2016
Extension of date/time by previous change orders 0 days
Date/time extension by this change order 0 days
New completion date/time 7/30/2016
/ CO , CTOR- RECOMMENDED FOR APPROVAL
5"il/�/ /04/4 / 7 ,✓fit
Printed Name and Titl
Walsh & Kelly
Company Name
24358 State Road 23
Address
South Bend, IN 46614
City, State, Zip
CONSTRUCTION MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC VYORKS
Approved
Date. q/3
Gary A. Gilot, President
David P. Relos, Member
1-71 C WL
Elizab th A Maradik, Member
Therese J. Dotab—Member
James A. Mueller, Member
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF STREETS
TO: Linda M. Martin, Clerk
Board of Public Works
FROM: Nadia Correa, Engineer I
SUBJECT: Project 115-086 Change Order Summary
DATE: Sept 7, 2016
The Lafayette Falls Subdivision Pavement project is the aftermath of a developer bankruptcy. Due
to this bankruptcy, residents of the City of South Bend were forced to live in a neighborhood with incomplete
infrastructure. After securing funds pursuant to the bankrupt developer's bond, the City bid this project and
eventually awarded to Walsh and Kelly.
The Lafayette Falls Subdivision Pavement project had expected cost overruns on HMA pavement
from the onset of the project. The construction manager, project manager, and contractor all met on site
prior to any commencement of work on the project. The consultant and construction manager verified on S
Morton Ct that certain depths of curb exposure were 2 Y4 inch, which was well over the estimated 1 '% inch
used to determine bid quantities. All parties agreed that quantities would overrun on HMA pavement as it
was necessary to meet city standards, however there was no pre -determined amount or estimate of the
overrun nor did the parties physically verify overruns on other stretches of roads. The contractor provided
the project manager with a schedule that set three consecutive week days July 26-28, 2016 for paving. On
July 26, 2016 the contractor supplied the project manager with the pavement tickets for the first portion of
the project. The project manager immediately entered these quantities into a spreadsheet for pay
application purposes; at this point, quantities were within scope and raised no red flags. On July 28, 2016
the contractor supplied the project manager with the final pavement tickets of the project. The project
manager then input the remainder of the pavement quantities into a spreadsheet and determined that the
project had already ran over 35.05%. Due to the speedy nature of this project, this high overrun was
unforeseen to the project manager until after the pavement had been completed.
If you have any questions or concerns, please contact me at (574) 235-5796 or by email at
ncorrea@southbendin.gov.
Sincerely,
Nadia Correa
Page 1 of 2
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 9/6/2016 Department
Name Nadia Correa Division/Bureau Engineering
BPW Date 9/13/2016 Phone Extension 5796
Required Prior to Submittal to Board
Legal ® Attorney Name: Michael Schmidt
Controller ❑ Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Public Works
Purchasing ® George King
Check the Appropriate Item Type — Required for All Submissions
Agreement ❑ Contract ❑ Proposal ❑ Addendum
❑ Professional Services ❑ Resolution
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award
® Change Order No. 1 ❑ C/O & PCA No. ❑ PCA
❑ Ease/Encroach. ❑ Traffic Control:
❑ Other:
Required Information
Company or Vendor Name Walsh & Kelly
New Vendor ❑ Yes ® No ❑ If Yes, Approved by Purchasina?
MBE/WBE Contractor
MBE/WBE Contractor Requested
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
MBE U WBE
No ❑ Yes M
avette Falls Su
115-086
LRSA
251.0608.380.10.99
HMA pavement overrun
L_J Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
Required For Change Orders Only
Amount of ® Increase $ 67663.20
❑ Decrease $
Previous Amount $ 193035.00
Current Percent of Change: 35.05%
New Amount $ 260698.20
Total Percent of Change: 35.05%