HomeMy WebLinkAbout12/06/94 Board of Public Works Special Meeting MinutesSPECIAL MEETING
DECEMBER 6. 1994
A Special meeting of the Board of Public Works was convened at 1:35 p.m. on Tuesday, December
6, 1994, by Board President John E. Leszczynski, with Mr. Leszczynski, Mr. James R. Caldwell and
Mrs. Jenny Manier present. Also present was Board Attorney Anne Bruneel.
OPENING OF BIDS - CENTURY CENTER REMODELING - PROJECT NO. 94-83
This was the date set for receiving and opening of sealed bids for the above referred to project. The
Clerk tendered proofs of publication of Notice in the South Bend Tribune and the Tri-County News
which were found to be sufficient. The following bids were opened and publicly read:
CASTEEL CONSTRUCTION CORPORATION
23186 W. Ireland Road
South Bend, Indiana
Bid was signed by Mr. R.V. Casteel, President
Non -Collusion Affidavit was in order
Non -Discrimination Commitment form was completed
Five per cent (5%) Bid Bond was submitted
BID: $2,569,000.00
Alternates
General Construction (Deduct)
G-2 Delete folding partitions between Meeting Rooms A, B, C, D
G-3 Delete window between Jewelry E-108 and Corridor E-121
G-4 Delete window between Elevator Lobby E-306 and Skywalk
G-5 Delete window between Weaving E-310 and Corridor E-327
G-6 Delete vertical strip windows facing River and assoc. mech./elec.
G-7 Delete ceiling grid in Sculpture D-101 and Ceramic D-105
G-8 Delete Polish Room E-108A
G-9 Delete casework in Weaving E-310
G-10 Exchange polymer paint for standard paint in Meeting
Rooms E-109, 112, 115, 117
G-11 Substitute limestone pavers for glass block pavers in
Rotunda D-216
G-12 Provide self supporting skylights in lieu of skylight/space frame
in Rotunda D-216
G-13 Delete Rooms D-101, 102, 103, 105, 106, 107, 108, 148
G-14 Delete demolition and construction in River Level Area E
G-15 Perform demolition and partial construction in Meeting Rooms
E-109, 112, 115, 117
$ 54,000.00
$ 1,100.00
$ 2,600.00
$ 2,400.00
$175,000.00
$ 4,000.00
$ 9,000.00
$ 1,000.00
$ 1,600.00
NO CHANGE
$ 47,000.00
$110,000.00
$255,000.00
$ 88,000.00
G-16 Delete stainless steel exterior plaque $ 12,000.00
SPECIAL MEETING DECEMBER 6, 1994
General Construction (Add)
G-1 Add escalator with step width of 32" $335,000.00
G-17 Add white maple veneer plywood paneling on walls and doors $ 24,000.00
of Vestibules D-213 and 218
G-18 Add escalator with step width of 24" $283,000.00
Mechanical Construction (Deduct)
M-1 Provide standard pneumatic controls in lieu of direct $ 29,000.00
digital controls
M-2 Delete VAV boxes with AHU's 11 and 12 and revise controls $ 19,000.00
M-3 Associated cost for Alternate M-2 if M-1 is accepted $ 34,000.00
M-4 Delete humidification system with AHU-13 $ 3,600.00
M-5 NO CHANGE
Electrical Construction (Deduct
E-1 Delete communication conduit from Storage E-119 to $ 17,000.00
Building "B"
E-2 Delete 208V twist lock outlets in Meeting Rooms A,B,C,D $ 2,000.00
E-3 Delete all sound system rough -ins $ 2,300.00
E-4 Delete VISA wall sconces $ 8,200.00
E-5 Delete dimmer system rough -ins and provide switches $ 12,000.00
E-6 Delete downlight at top of skylight in Rotunda D-216 $ 1,200.00
E-7 Delete exterior walkway lights along west wall of Street $ 4,200.00
Level Area "D"
VERKLER, INC.
4406 Technology Drive
South Bend, Indiana
Bid was signed by Mr. Fred Lusk, President
Non -Collusion Affidavit was in order
Non -Discrimination Commitment form was completed
Five percent (5%) Bid Bond was submitted
BID: $2,828,000.00
Alternates
General Construction (Deduct)
G-2 Delete folding partitions between Meeting Rooms A, B, C, D $ 51,000.00
G-3 Delete window between Jewelry E-108 and Corridor E-121 $ 2,500.00
SPECIAL MEETING DECEMBER 6; 1994
G-4 Delete window between Elevator Lobby E-306 and Skywalk $ 1,800.00
G-5 Delete window between Weaving E-310 and Corridor E-327 $ 1,800.00
G-6 Delete vertical strip windows facing River and assoc. mech./elec. $217,000.00
G-7 Delete ceiling grid in Sculpture D-101 and Ceramic D-105 $ 50,000.00
G-8 Delete Polish Room E-108A $ 3,000.00
G-9 Delete casework in Weaving E-310 $ 2,000.00
G-10 Exchange polymer paint for standard paint in Meeting $ 2,000.00
Rooms E-109, 112, 115, 117
G-11 Substitute limestone pavers for glass block pavers in $ 10,000.00
Rotunda D-216
G-12 Provide self supporting skylights in lieu of skylight/space frame $ 1,200.00
in Rotunda D-216
G-13 Delete Rooms D-101, 102, 103, 105, 106, 107, 108, 148 $133,000.00
G-14 Delete demolition and construction in River Level Area E $321,000.00
G-15 Perform demolition and partial construction in Meeting Rooms $ 90,000.00
E-109, 112, 115, 117
G-16 Delete stainless steel exterior plaque $ 10,000.00
General Construction (Add)
G-1 Add escalator with step width of 32" $366,000.00
G-17 Add white maple veneer plywood paneling on walls and doors $ 5,000.00
of Vestibules D-213 and 218
G-18 Add escalator with step width of 24" $360,000.00
Mechanical Construction (Deduct
M-1 Provide standard pneumatic controls in lieu of direct $ 29,000.00
digital controls
M-2 Delete VAV boxes with AHU's 11 and 12 and revise controls $ 20,000.00
M-3 Associated cost for Alternate M-2 if M-1 is accepted $ 34,000.00
M-4 Delete humidification system with AHU-13 $ 3,500.00
Electrical Construction (Deduct)
E-1 Delete communication conduit from Storage E-119 to $ 17,000.00
Building "B"
E-2 Delete 208V twist lock outlets in Meeting Rooms A, B, C, D $ 1,700.00
SPECIAL MEETING DECEMBER 6, 1994
E-3
Delete all sound system rough -ins
$
2,500.00
E-4
Delete VISA wall sconces
$
8,500.00
E-5 Delete dimmer system rough -ins and provide switches $ 12,000.00
E-6 Delete downlight at top of skylight in Rotunda D-216 $ 1,200.00
E-7 Delete exterior walkway lights along west wall of Street $ 4,500.00
Level Area "D"
All work can be completed in the River Level Area E by September 20, 1995, and all remaining
work can be completed by October 31, 1995.
THE ROBERT HENRY CORPORATION
404 South Frances Street
South Bend, Indiana
Bid was signed by Mr. Robert A. Henry, President
Non -Collusion Affidavit was in order
Non -Discrimination Commitment form was completed
Five percent (5%) Bid Bond was submitted
BID: $3,048,000.00
Alternates
General Construction (Deductl
G-2 Delete folding partitions between Meeting Rooms A, B, C, D
G-3 Delete window between Jewelry E-108 and Corridor E-121
G-4 Delete window between Elevator Lobby E-306 and Skywalk
G-5 Delete window between Weaving E-310 and Corridor E-327
G-6 Delete vertical strip windows facing River and assoc. mech./elec.
G-7 Delete ceiling grid in Sculpture D-101 and Ceramic D-105
G-8 Delete Polish Room E-108A
G-9 Delete casework in Weaving E-310
G-10 Exchange polymer paint for standard paint in Meeting
Rooms E-109, 112, 115, 117
G-11 Substitute limestone pavers for glass block pavers in
Rotunda D-216
G-12 Provide self supporting skylights in lieu of skylight/space frame
in Rotunda D-216
G-13 Delete Rooms D-101, 102, 103, 105, 106, 107, 108, 148
G-14 Delete demolition and construction in River Level Area E
$ 60,000.00
$ 1,500.00
$ 1,000.00
$ 1,000.00
$285,000.00
$ 1,000.00
$ 2,000.00
$ 4,500.00
$ 1,000.00
$ 8,000.00
$ 12,000.00
$110,000.00
$335,000.00
SPECIAL MEETING DECEMBER 6, 1994
G-15 Perform demolition and partial construction in Meeting Rooms $120,000.00
E-109, 112, 115, 117
G-16 Delete stainless steel exterior plaque
$ 10,000.00
General Construction (Add)
G-1 Add escalator with step width of 32" $389,000.00
G-17 Add white maple veneer plywood paneling on walls and doors $ 17,500.00
of Vestibules D-213 and 218
G-18 Add escalator with step width of 24" DEDUCT $ 6,500.00
Mechanical Construction (De ductl
M-1 Provide standard pneumatic controls in lieu of direct $ 28,000.00
digital controls
M-2 Delete VAV boxes with AI U's 11 and 12 and revise controls $ 19,000.00
M-3 Associated cost for Alternate M-2 if M-1 is accepted $ 33,400.00
M-4 Delete humidification system with AHU-13 $ 3,300.00
Electrical Construction (Deduct)
E-1 Delete communication conduit from Storage E-119 to $ 16,000.00
Building "B"
E-2 Delete 208V twist lock outlets in Meeting Rooms A, B, C, D $ 1,500.00
E-3 Delete all sound system rough -ins $ 2,000.00
E-4 Delete VISA wall sconces $ 7,000.00
E-5 Delete dimmer system rough -ins and provide switches $ 11,000.00
E-6 Delete downlight at top of skylight in Rotunda D-216 $ 1,100.00
E-7 Delete exterior walkway lights along west wall of Street $ 4,000.00
Level Area "D"
BATTEAST CONSTRUCTION COMPANY, INC.
430 East LaSalle Avenue
South Bend, Indiana
Bid was signed by Mr. Robert V. Batteast, Jr., Vice President
Non -Collusion Affidavit was in order
Non -Discrimination Commitment form was completed
Five percent (5%) Bid Bond was submitted
BID: $3,191,200.00
f vwr
SPECIAL MEETING
Alternates
DECEMBER 6, 1994
General Construction (Deductl
G-2 Delete folding partitions between Meeting Rooms A, B, C, D
G-3 Delete window between Jewelry E-108 and Corridor E-121
G-4 Delete window between Elevator Lobby E-306 and Skywalk
G-5 Delete window between Weaving E-310 and Corridor E-327
G-6 Delete vertical strip windows facing River and assoc. mech./elec.
G-7 Delete ceiling grid in Sculpture D-101 and Ceramic D-105
G-8 Delete Polish Room E-108A
G-9 Delete casework in Weaving E-310
G-10 Exchange polymer paint for standard paint in Meeting
Rooms E-109, 112, 115, 117
G-11 Substitute limestone pavers for glass block pavers in
Rotunda D-216
G-12 Provide self supporting skylights in lieu of skylight/space frame
in Rotunda D-216
G-13 Delete Rooms D-101, 102, 103, 105, 106, 107, 108, 148
G-14 Delete demolition and construction in River Level Area E
G-15 Perform demolition and partial construction in Meeting Rooms
E-109, 112, 115, 117
G-16 Delete stainless steel exterior plaque
General Construction (Add1
G-1 Add escalator with step width of 32"
G-17 Add white maple veneer plywood paneling on walls and doors
of Vestibules D-213 and 218
G-18 Add escalator with step width of 24"
Mechanical Construction (Deduct)
M-1 Provide standard pneumatic controls in lieu of direct
digital controls
M-2 Delete VAV boxes with AHU's 11 and 12 and revise controls
M-3 Associated cost for Alternate M-2 if M-1 is accepted
M-4 Delete humidification system with AHU-13
$ 48,536.00
$ 3,670.00
$ 3,850.00
$ 3,010.00
$238,070.00
$ 2,895.00
$ 4,100.00
$ 5,450.00
$ 2,000.00
$ 11,800.00
$ 8,270.00
$260,350.00
$410,060.00
$133,330.00
$ 19,800.00
$251,710.00
$ 9,800.00
$236,710.00
$ 26,350.00
$ 17,250.00
$ 38,390.00
$ 3,660.00
0'N-447
SPECIAL MEETING DECEMBER 6; 1994
Electrical Construction (Deduct)
E-1 Delete communication conduit from Storage E-119 to $ 16,960.00
Building "B"
E-2 Delete 208V twist lock outlets in Meeting Rooms A,B,C,D $ 1,700.00
E-3 Delete all sound system rough -ins $ 2,265.00
E-4 Delete VISA wall sconces $ 8,055.00
E-5 Delete dimmer system rough -ins and provide switches $ 11,475.00
E-6 Delete downlight at top of skylight in Rotunda D-216 $ 1,150.00
E-7 Delete exterior walkway lights along west wall of Street $ 4,120.00
Level Area "D"
Work completed in River Level Area E by September 20, 1995 and all remaining work completed
by October 31, 1995.
REINKE CONSTRUCTION CORPORATION
1216 W. Sample Street
South Bend, Indiana
Bid was signed by Mr. H.G. Reinke Jr., President
Non -Collusion Affidavit was in order
Non -Discrimination Commitment form was completed
Five percent (5%) Bid Bond was submitted
BID: $2,547,000.00
Alternates
General Construction (Deduct)
G-2 Delete folding partitions between Meeting Rooms A, B, C, D $ 52,800.00
G-3 Delete window between Jewelry E-108 and Corridor E-121 $ 1,300.00
G-4 Delete window between Elevator Lobby E-306 and Skywalk $ 1,300.00
G-5 Delete window between Weaving E-310 and Corridor E-327 $ 1,300.00
G-6 Delete vertical strip windows facing River and assoc. mech./elec. $186,000.00
G-7 Delete ceiling grid in Sculpture D-101 and Ceramic D-105 $ 2,100.00
G-8 Delete Polish Room E-108A $ 2,000.00
G-9 Delete casework in Weaving E-310 $ 3,300.00
G-10 Exchange polymer paint for standard paint in Meeting $ 1,800.00
Rooms E-109, 112, 115, 117
G-11 Substitute limestone pavers for glass block pavers in $ 8,500.00
Rotunda D-216
SPECIAL MEETING DECEMBER 6, 1994
G-12 Provide self supporting skylights in lieu of skylight/space frame $ 48,000.00
in Rotunda D-216
G-13 Delete Rooms D-101, 102, 103, 105, 106, 107, 108, 148 $120,000.00
G-14 Delete demolition and construction in River Level Area E $320,000.00
G-15 Perform demolition and partial construction in Meeting Rooms $ 92,000.00
E-109, 112, 115, 117
G-16 Delete stainless steel exterior plaque $ 10,000.00
General Construction (Add)
G-1 Add escalator with step width of 32" $365,000.00
G-17 Add white maple veneer plywood paneling on walls and doors $ 7,800.00
of Vestibules D-213 and 218
G-18 Add escalator with step width of 24" $358,000.00
Mechanical Construction (Deduct)
M-1 Provide standard pneumatic controls in lieu of direct $ 28,000.00
digital controls
M-2 Delete VAV boxes with AHU's 11 and 12 and revise controls $ 19,500.00
M-3 Associated cost for Alternate M-2 if M-1 is accepted $ 34,000.00
M-4 Delete humidification system with AHU-13 $ 3,060.00
M-5 Provide Barber Coleman pneumatic controls in lieu NO BID
of Johnson Controls
Electrical Construction (Deduct
E-1 Delete communication conduit from Storage E-119 to $ 17,000.00
Building "B"
E-2 Delete 208V twist lock outlets in Meeting Rooms A,B,C,D $ 1,700.00
E-3 Delete all sound system rough -ins $ 2,300.00
E-4 Delete VISA wall sconces $ 8,100.00
E-5 Delete dimmer system rough -ins and provide switches $ 11,500.00
E-6 Delete downlight at top of skylight in Rotunda D-216 $ 1,150.00
E-7 Delete exterior walkway lights along west wall of Street $ 4,100.00
Level Area "D"
All work can be completed in the River Level Area E by September 20, 1995, and all remaining
work can be completed by October 31, 1995.
SPECIAL MEETING DECEMBER 6. 1994
H.G. CHRISTMAN CONSTRUCTION CO. INC.
850 South Fellows Street
South Bend, Indiana
Bid was signed by Mr. Howard E. Emmons, President
Non -Collusion Affidavit was in order
Non -Discrimination Commitment form was completed
Five percent (5%) Bid Bond was submitted
BID: $2,970,000.00
Alternates
General Construction (Deduct)
G-2 Delete folding partitions between Meeting Rooms A,B,C,D $ 49,000.00
G-3 Delete window between Jewelry E-108 and Corridor E-121 $ 3,000.00
G-4 Delete window between Elevator Lobby E-306 and Skywalk $ 2,800.00
G-5 Delete window between Weaving E-310 and Corridor E-327 $ 2,800.00
G-6 Delete vertical strip windows facing River and assoc. mech./elec. $200,000.00
G-7 Delete ceiling grid in Sculpture D-101 and Ceramic D-105 $ 3,800.00
G-8 Delete Polish Room E-108A $ 3,800.00
G-9 Delete casework in Weaving E-310 $ 2,400.00
G-10 Exchange polymer paint for standard paint in Meeting $ 1,500.00
Rooms E-109, 112, 115, 117
G-11 Substitute limestone pavers for glass block pavers in $ 9,400.00
Rotunda D-216
G-12 Provide self supporting skylights in lieu of skylight/space frame $ 48,000.00
in Rotunda D-216
G-13 Delete Rooms D-101, 102, 103, 105, 106, 107, 108, 148 $124,000.00
G-14 Delete demolition and construction in River Level Area E $300,600.00
G-15 Perform demolition and partial construction in Meeting Rooms $ 72,000.00
E-109, 112, 115, 117
G-16 Delete stainless steel exterior plaque $ 10,000.00
General Construction (Add)
G-1 Add escalator with step width of 32" $364,000.00
G-17 Add white maple veneer plywood paneling on walls and doors $ 10,800.00
of Vestibules D-213 and 218
G-18 Add escalator with step width of 24" $357,000.00
(YET)
SPECIAL MEETING DECEMBER 6. 1994
Mechanical Construction (Deduct)
M-1 Provide standard pneumatic controls in lieu of direct $ 28,000.00
digital controls
M-2 Delete VAV boxes with AHU's 11 and 12 and revise controls $ 19,000.00
M-3 Associated cost for Alternate M-2 if M-1 is accepted $ 33,000.00
M-4 Delete humidification system with AHU-13 $ 3,000.00
Electrical Construction (Deduct)
E-1 Delete communication conduit from Storage E-119 to
Building "B"
E-2 Delete 208V twist lock outlets in Meeting Rooms A,B,C,D
E-3 Delete all sound system rough -ins
E-4 Delete VISA wall sconces
E-5 Delete dimmer system rough -ins and provide switches
E-6 Delete downlight at top of skylight in Rotunda D-216
$ 16,500.00
$ 1,700.00
$ 2,200.00
$ 8,000.00
$ 11,400.00
$ 1,100.00
E-7 Delete exterior walkway lights along west wall of Street $ 4,000.00
Level Area "D"
Upon a motion made by Mrs. Manier, seconded by Mr. Caldwell and carried, the above bids were
referred to Mathews-Purucker-Anella, Inc., Architects, 218 S. Frances Street, South Bend, Indiana
for review and recommendation.
ADJOURNMENT
There being no further business to come before the Board, upon a motion made by Mr. Caldwell,
seconded by Mrs. Manier and carried, the meeting adjourned at 1:42 p.m.