HomeMy WebLinkAboutChange Order No. 4 - WWTP Secondary Treatment Improvements Proj No. 114-053 Thieneman1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND. 1NDIANA 46601-1830
CITY OF SOUTH BEND PETE BUTTIGIEG, MAYOR
BOARD OF PUBLIC WORKS
August 9, 2016
Mr. Vince Rock
Thieneman Construction, Inc.
17241 Foundation Parkway, Ste. 100
Westfield, IN 46074
PHONE 574/235-9251
FAX 574/235-9171
RE: Change Order No. 4 — Waste Water Treatment Plant -Secondary Treatment
Improvements —Project No. 114-053
Dear Mr. Rock:
The Board of Public Works, at its meeting held on August 9, 2016, approved the above
referenced Change Order for an increase of $606,776.00 and the addition of twenty-one (21)
days, bringing the current contract amount to $12,592,997.75 and the completion date to
September 15, 2017.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
c: Michael Divita, Community Investment
Toy Villa, Engineering
Beth Leonard, Community Investment
Judy Love, Community Investment
GARY A. GILOT DAVID P. RELOS ELIZABETH A. MARADIK JAMES A. MUELLER THERESE J. DORAU
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO.
SUBJECT OF CHANGE ORDER: Various modifications to the contract. See attached.
All items completed substantially as planned.
See attached Comparison of Estimate for overruns and underruns
The original contract sum $ 11,885,000.00
Net change by previously authorized change orders $ 101,221.75
The contract sum prior to this change order $ 11,986,221.75
By this Change Order, the project amount is ® Increased
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
❑ Decreased $ 606,776.00
$ 12,592,997.75
+5.11 %
+5.96 %
Original contracted completion date/time 08/25/2017
Extension of date/time by previous change orders 0 days
Date/time extension by this change order 21 days
New completion date/time 9/15/2017
RECOMMENDED FOR APPROVAL
CONTRACTOR
Contractor Signatur
V, ulz Rzol I �fe i Man
Printed Name and Title
Thieneman Construction, Inc.
Company name
17241 Foundation Parkway - Suite 100
Address
Westfield, Indiana 46074
City, State, Zip
"onstruction Manager
CITY OF SOUTH BEND
BOARD OFPUBL4C }2KS
Approved Date: b oY�
Gary A. Gilot, Piresident
e idD V P. Relos, M—ember
Jame—Iler, A ember
=�
Elizabeth A. Maradik, Member
Therese J. Dorau, Member
I.JCDC
IN4�N[[Pt IiNYI COMRatI
OOLVMLNiS COCA AIi[I$[
Change Order No. 4
Date of Issuance: July 29,2016 Effective Date:
Owner: City of South Bend Owner's Contract No.: 114-053
Contractor: Thieneman Construction Contractor's Project No.:
Engineer: Arcadis US Engineer's Project No.: 03029034.0000
Project: Secondary Treatment Improvements Contract Name:
The Contract is modified as follows upon execution of this Change Order:
Description: Incorporation of Contractor's COPS:
COP 12-DI-R2 —Air Header Pipe Replacement...........................................................................
$206,823.00
COP 14 —Groundwater Pump Level Sensors..................................................................................
$3,091.00
COP15 — RFI 81 Costs......................................................................................................................
$3,167.00
COP 16-R1— Fiber Optic Additional Work...................................................................................
$118,631.00
COP 17 — Lower Dewatering Wells................................................................................................
$26,685.00
COP 20 — Nitrification Pipe Demo...................................................................................................
$1,492.00
COP 21— Remove 4 Pipes From Aeration.......................................................................................
$3,108.00
COP22 — Concrete Baffle Wall......................................................................................................
$10,713.00
COP 29-R1— Clarifier Pressure Reducing Valves...........................................................................
$22,406.00
COP 30— Mixed Liquor Valve Replacement................................................................................
$210,660.00
Attachments: Contractor's Change Order Proposals
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIMES
Original Contract Price:
Original Contract Times:
Substantial Completion: July 26, 2017
$ 11,885,000 00
Ready for Final Payment: August 25, 2017
dates
Increase from previously approved Change Orders:
No Change from previously approved Change Orders:
Substantial Completion: 0
$ 101,221.75
Ready for Final Payment: 0
days
Contract Price prior to this Change Order:
Contract Times prior to this Change Order:
Substantial Completion: July 26, 2017
$ 11,986 221.75
Ready for Final Payment: August 25, 2017
dates
Increase of this Change Order:
Increase of this Change Order:
Substantial Completion: 21
$ 606,776.00
Ready for Final Payment: 21
days
Contract Price incorporating this Change Order:
Contract Times with all approved Change Orders:
Substantial Completion: August 16, 2017
$ 12,592,997.75
Ready for Final Payment: September 15, 2017
dates
E DMMEND D: ACCEPTED:
By: By: t e�n ' By:
Engineer (if required) V Owner (Authorized Signature)
Title: 4jr r_ Title ASSISTAriTCll4 0461J4F.4L Title
Date: _ ej ZZZ Date
08-o5-Zolfo Date
AGGEP -
Contractor(Aut orized Signature
�PPA m 2Vt ZrY4'Y
g y�(—ZI1/Cr
EJCDC' C-941, Change Order.
Prepared and published 2013 by the Engineers Joint Contract Documents Committee.
Pace 1 of 1
CITY OF SOUTH BEND, INDIANA
WWTP SECONDARY TREATMENT IMPROVEMENTS
CITY PROJECT NO. 114-053
CHANGE ORDER PROPOSAL
Change Order Proposal No.: 114-053-0012-DI(R2) Date: 6/21/16
Submitted in Response to Proposal Request No.:
Contract Name and No.: 114-053 South Bend W WTP Secondary Treatment Improvements
Contractor: Thieneman Construction, Inc.
Subject: Demo and Replace Eight (8) Existing 14" Air Lines with New Foreign Ductile Iron
Piping. The use foreign steel materials is prohibited by CO #2, but was specifically requested by
Jacob Klosinski, City of South Bend.
The following changes to the Contract are proposed:
SCOPE OF WORK: (attach and list supporting information as required)
1. Item: TCI — See attached Breakdown $156,319
2. Item: Davidson -Finch Painting — Prep/Paint Piping and New Concrete $8,888
3. Item: Indiana Concrete Cutting $16,880
JUSTIFICATION:
1. Item: Owner Request
CHANGES IN CONTRACT PRICE AND CONTRACT TIMES:
We propose that the Contract Price and Contract Times be changed as follows:
For Contract Price, when requested by Engineer, attach detailed cost breakdowns for Contractor and
Subcontractors, Supplier quotations, and other information required.
For the Contract Times, state increase, decrease, or no change to Contract Times for Substantial Completion,
readiness for final payment, and Milestones, if any. If increase or decrease, state specific number of days for
changes to the Contract Times.
Description
Amount
Contract Times (days)
Substantial
Final
1. Item—TCl/Davidson-Finch/ICC
$182,087
56
56
2. Item — Marku : TCI 15% / Subs 5%
$24, ?36
0
0
Total This Change Order Proposal
$206,823
56
56
Changes to Milestones, if any:
The adjustment proposed is the entire adjustment to the Contract to which the proposer believes it
is entitled as a result of the proposed change.
Change Order Proposal By: Allen Gaarder
Signature of Proposer:
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date August 1, 2016
Name Jacob M. Klosinski Department Division of Utilities
BPW Date August 9, 2016 Phone Extension (574) 235-9496
Required Prior to Submittal to Board
Legal ® Attorney Name Michael Schmidt
Controller ® Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ® Carol Kurzhal
Check the Appropriate Item Type — Required for All Submissions
❑ Agreement ❑ Contract ❑ Proposal ❑Addendum
❑ Professional Services ❑ Resolution
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award
® Change Order No. 004 ❑ C/O & PCA No. ❑ PCA
❑ Ease/Encroach. ❑ Traffic Control
or Vendor Name
New Vendor
MBE/WBE Contractor
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Thieneman Construction, Inc.
J Yes ® No ❑ If Yes, Approved by Purchasing
MBE ❑ WBE
WWTP - Secondary Treatment Improvements
114-053
2012 Sewer Bond
661-0630-415-42-06
Sum
Division of Utilities recommends the approval of Change Order No. 4.
Refer to Inter -Office Memorandum and enclosures for description of
changes (additions).
❑ Required Contractor's Certification Form Attached (Non -
Required For Change Orders Only
Amount of ® Increase $ 606,776.00
❑ Decrease $
Previous Amount $ 11,986,221.75
Current Percent of Change: +5.11%
New Amount $ 12,592,997.75
Total Percent of Change: +5.96%
Dispersal After Approval
Copy Original
® ❑ Al Greek, Division Director of Utilities
® ❑ Jacob M. Klosinski, Assistant City Engineer
® ❑ Carol Kurzhal, Director of Financial Services, Environmental Services
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENVIRONMENTAL SERVICES
TO: Members of the Board of Public Works
Eric Horvath, Director of Public Works
Michael Schmidt, Board of Public Works Attorney
FROM: Al Greek, Director of Utilities
Jacob M. Klosinski, Assistant City Engineer
SUBJECT: Agenda Request Form — Change Order No. 4
Project No. 114-053: Wastewater Treatment Plant Secondary Treatment
Improvements
DATE: August 1, 2016
The Department of Environmental Services (DES) is requesting the Board of Public Works
approval of Change Order No. 4 for Project No. 114-053 Wastewater Treatment Plant
Secondary Treatment Improvements. Refer to attached documents for supporting details.
Change Order No. 4 addresses the following changes:
Remove and Replace, Eight (8) Aeration Air Header Pipes
$206,823.00
Dewatering Pump Timing Relays
$
3,091.00
Gallery 4, Heating Panel Conduit Reroute
$
3,167.00
Fiber Optic Cable and Conduit Reroute
$118,631.00
Lower Dewatering Wells
$
26,685.00
Nitrification Pipe Removals
$
1,492.00
Remove Five (5) Four Inch Diameter Conduits at Aeration Channel $
3,108.00
Aeration Tank Pass 1 Concrete Baffle Wall Removals
$
10,713.00
Pressure Relief Valves, Full Depth Removals
$
22,406.00
Remove and Replace Four (4) 36" Diameter Knife Gates Valves
$210,660.00
NET INCREASE FOR CHANGE ORDER NO. 3 ITEMS $606,776.00
Original Contract Sum $11,885,000.00
Net change by previously authorized change orders $ 101,221.75
The contract sum prior to this change order $11,986,221.75
By this change order, the project amount increases by $ 606,776.00
The new contract sum including this change order is $12,592,997.75
This Change Order represents a total change of +5.11%
Total change for the entire project +5.96%
Time Extensions: 21 Days added to Substantial Completion, August 16, 2017
21 Days added to Final Completion, September 15, 2017
The primary funding sources for the construction of this project is the 2012 Sewer Bond (661-
0630-415-42-06). If there are any questions regarding the subject project, please contact Al
Greek (Ext. 4210) or Jacob M. Klosinski (Ext. 9496) at the Division of Utilities.